BLD-Final | 11/6/2006 | 11/7/2006 | 11/7/2006 | A | PASS |
Jim Storey
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 11/7/2006 | 11/7/2006 | 11/7/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 11/6/2006 | 11/6/2006 | 11/6/2006 | P | FAIL |
Jim Storey
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Patricia Smith handrail exterior stair 34/38 with min 1 1/2 clearance to wall.
|
BLD-Other | 7/14/2006 | 7/14/2006 | 7/14/2006 | P | PART |
Dave Hannah
|
|
|
matt Note: basement water seal ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles only able to see area around window wells
|
BLD-Framing/Rough-in | 7/13/2006 | 7/13/2006 | 7/13/2006 | P | PASS |
Dave Hannah
|
|
|
TROY; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Energy code compliance | 7/13/2006 | 7/13/2006 | 7/13/2006 | P | PASS |
Dave Hannah
|
|
|
TROY NOTE: PLEASE CALL 1 HR PRIOR TO INSPECTION; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 7/10/2006 | 7/10/2006 | 7/10/2006 | P | PART |
Jim Storey
|
|
|
troy ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley need truss engineering to repesent bearing of truss above furn noted on engineering.16#&17.
|
BLD-Footing | 5/1/2006 | 5/2/2006 | 5/2/2006 | A | PASS |
Jim Storey
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ft on garge.
|
BLD-Other | 4/21/2006 | 4/24/2006 | 4/24/2006 | P | PART |
Jim Storey
|
|
|
MATT NOTE: BASEMENT REBAR; Phone #: ###-#### Internet Inspection Request from: Cathy Chilespwoi
|
BLD-Footing | 4/19/2006 | 4/19/2006 | 4/19/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/19/2006 at 7:11:49 AM. Contact: ###-####. scheduling mix up crew had concrete on site unable to get to project crew will place at own risk will chech at stem wall insection
|
BLD-Footing | 4/17/2006 | 4/18/2006 | 4/18/2006 | P | FAIL |
Jim Storey
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong no plans no rebar.
|
Issue PAID IN FULL permit | | | 4/3/2006 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 4/3/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 3/20/2006 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2006 | | DONE |
|
|
|
lft vm with prestige homes ###-#### that permit and fees are ready to be picked up
|
Plan assigned to (DJO) | 3/13/2006 | | 3/17/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/17/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/7/2006 | | 3/17/2006 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 3/1/2006 | 3/1/2006 | 3/13/2006 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/7/2006 | | 3/7/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 3/1/2006 | | 3/2/2006 | | PASS |
Tom Curren
|
|
|
Eave on north side of garage extends 3 ft into required side yard setback. Maximum extension allowed is 2 ft. Site plan scale is not correct. Street name not shown on site plan. Driveway paving is not indicated. TAC
Contacted Prestige homes 3/2/2006. Scott Zierler will be back in office on 3/6. He will contact me then. Revised site plan reviewed and approved 3/7/2006 TAC
|
Application received | | | 3/1/2006 | | |
|
|
|
|