Third Notice BLD | 10/30/2007 | 10/30/2007 | 12/19/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 3/3/2006 | 3/3/2006 | 12/19/2007 | | DONE |
|
|
|
|
Second Notice BLD | 10/17/2007 | 10/17/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 9/21/2007 | 9/21/2007 | 10/17/2007 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 9/19/2007 | 9/20/2007 | 9/21/2007 | P | PASS |
Dave Hannah
|
|
|
scott Phone #: ###-####
|
DOC - Permit Finaled | 9/21/2007 | 9/21/2007 | 9/21/2007 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | PASS |
Forrest France
|
|
|
All noted items for correction have been completed, fire life safety inspection passed.
|
FIRE-Final Inspection | 9/18/2007 | 9/19/2007 | 9/20/2007 | A | FAIL |
Forrest France
|
|
|
See eight item correction notice for list of defficiencies, also need to final fire sprinkler permit prior to life safety final approval.
|
BLD-Final | 9/19/2007 | 9/19/2007 | 9/20/2007 | P | FAIL |
Dave Hannah
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Final | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | CANC |
Dave Hannah
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
PubWorks Occupancy Approval | 9/10/2007 | 9/10/2007 | 9/10/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/7/2007 | | |
|
|
|
|
Meeting | | | 9/6/2007 | | DONE |
|
|
|
Onsite meeting with Building and Fire department personnel to evaluate the current building protection status with respect to an occupancy event scheduled for noon today, discovered by the fire inspector at his initial check of the sprinkler hydro test this morning. No sprinkler contractor was on site, no sprinkler plans were available, but the system is currently shut off (isolated from the city supply, as a hydrostatic test is underway); sprinkler heads were noted missing in both basement stairways; it appears the wrong temperature heads may have been installed (high temperature heads were noted in the basement and first floor areas). The fire alarm system was out of service and the off-site monitoring phone connections were being installed at the time of this visit, several other deficiencies were noted including lack of the manual pull station, no monitoring point for the main sprinkler control valve. Exit signs and emergency lites were in service, exit hardware was satisfactory on the two 1st floor exit doors; signs were posted to indicate no public entry allowed to the basement and 2nd floor areas, although construction workers were intermittently in those areas; handrails on the front entrance were deficient. The building official required the front entry to be constantly manned with persons to assist as needed, as a temporary option for handrails. The fire marshal required a fire watch and an engine company to remain onsite during the event.
|
Code Occupancy Approval | | | 8/29/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/27/2007 | | |
|
|
|
|
BLD-Conference | 8/21/2007 | 8/22/2007 | 8/22/2007 | A | PASS |
Dave Hannah
|
|
|
scott Phone #: ###-####Note: please call 1/2 hr prior to conference
|
BLD-Framing/Rough-in | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | PART |
Dave Hannah
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang shaft ok
|
Telephone call | | | 5/17/2007 | | DONE |
|
|
|
left mess for scott sparks that plans are here & no fees due --to check & see if he wanted plans???
|
Telephone call | | | 2/8/2007 | | DONE |
|
|
|
left mess for scott sparks at ###-#### that revised plans are ready for pickup
|
BLD-Other | 1/29/2007 | 1/30/2007 | 1/30/2007 | P | PASS |
Dave Hannah
|
|
|
chris - hand rails; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
Telephone call | | | 12/19/2006 | | DONE |
|
|
|
left mess for scott sparks at ###-#### that permit is ready & need to pay achd
|
Plan Reviewer's activity | | | 11/14/2006 | | PASS |
|
|
|
The revised structural drawings, including the cable guard for stairways, was approved. CJW
|
Plan resubmittals received | | | 10/11/2006 | | |
|
|
|
Received transmittal sheet, 2 copies of 4pg. Cable Rail Calculations from AHJ Engineers, 2 copies of page S4.2; per Carl Westfall take in as resubmittals, taken to him
|
BLD-Aging Inspection | 9/8/2006 | 9/8/2006 | 9/11/2006 | | PASS |
Dave Hannah
|
|
|
|
Plan resubmittals received | | | 7/18/2006 | | DONE |
|
|
|
Per Marlene S. received 1 cover transmittal, copies 2 copies of revised staris at the linen building structural calcs, 2 copies of the following sheets-- S1.1, S2.1, S3.1, S3.2, S4.1, S4.2 and taken to Carl Westfall
|
Issue PAID IN FULL permit | | | 6/9/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/25/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2006 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up needs ACHD
|
Permit Ready to Issue | | | 5/25/2006 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/26/2006 | | 5/24/2006 | | PASS |
|
|
|
Called Action Couriers for pick up. The second structural review was completed on May 5, 2006. The review failed. The structural review was completed on May 23, 2006. No further review required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/4/2006 | | 5/24/2006 | | PASS |
|
|
|
(4-26-06) The resubmitted drawings were reviewed and approved with "red lines" except for structural. The structural drawings were sent to the consultant Engineer. Waiting for his review. (5-24-06) The structural review was completed on May 23, 2006. No further review required.
|
Plan assigned to (CJW) | 3/6/2006 | | 5/24/2006 | | PASS |
|
|
|
5/24/2006 13:52:47 CJW - activity updated through activity BLDA022 from case BLD06-00500.
|
Plan resubmittals received | | | 4/26/2006 | | |
|
|
|
Received 1 copy of cover transmittal letter, 1 copy of structural responses to plan review comments, 1 copy of supplemtental structural calcs, 1 copy of ACHD comments from Lochsa Engineering, 1 copy of C1.01, A1.1, A1.2, A2.1, A4.1, A4.2, A4.3, S1.1, S2.1, S2.2, S3.1, S3.2, S4.1, S4.2 and taken to Carl W.
|
Plan resubmittals received | | | 4/21/2006 | | |
|
|
|
Received 1 copy of transmittal letter; 2 copies of each of the following-ACHD License agreement; engineering response letter; AHJ engineers response & sealed calculations; C1.01; A0.0; A1.1; A1.2; A2.1; A4.1; A4.2, A4.3; S1.1; S2.1; S2.2; S3.1; S3.2; S4.1; S4.2 and taken to Carl W.
|
Meeting | | | 4/17/2006 | | DONE |
|
|
|
Onsite visit to verify non-accessible and non-cumbustible space in basement. Verified that the space is infact non accessible and the floor above is slab concrete surrounded by concrete walls floor to ceiling. The space will not require fire protection.
|
Routing - FIRE | 3/31/2006 | | 4/4/2006 | | PASS |
|
|
|
Review complete. Sam Rogers responding to letter from architect requesting not to sprinkler inaccessible crawl space.
|
1st review completed | | | 4/4/2006 | | FAIL |
|
|
|
failed plan check.
|
Routing - PLAN CHECK | 3/17/2006 | | 3/31/2006 | | FAIL |
|
|
|
(3-23-06) Finished the IBC plan review except for the structural review by the consultant. Waiting for comments from the Consultant Structural Engineer. Sent back to Addressing for another address. (3-31-03) Incorporated the Consultant Structural Engineer's comments into the plan review report.
|
Routing Off Site - STRUCTURAL | 3/6/2006 | | 3/30/2006 | | FAIL |
|
|
|
Called Action Couriers for pick up
|
Routing - PUBLIC WORKS | 3/23/2006 | | 3/24/2006 | | PASS |
|
|
|
Sent back to addressing for another address.
|
Routing - PLANNING | 3/15/2006 | | 3/17/2006 | | PASS |
|
|
|
Sarah Schafer DRH06-00039
Approved per DRH06-00039.
|
Routing - PLUMBING | 3/15/2006 | | 3/15/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 3/14/2006 | | 3/15/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 3/7/2006 | | 3/14/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/14/2006 | | DONE |
|
|
|
Received 1 Erosion & Sediment application,1 trasnmittal,2 Erosion & Sediment Control Plans & 3 copys of sheet 2 of 2 taken and inserted into main plans./// DLD
|
Plan resubmittals received | | | 3/9/2006 | | |
|
|
|
Recieved 1 cover transmittal letter and 3 copies of C1.01 and taken to Brian Murphy
|
Routing - PLANNING Land Div | 3/6/2006 | | 3/7/2006 | | PASS |
|
|
|
Single parcel with one Tax Parcel # merged from Lots 5 and 6, Block 111 of Boise City Original Townsite.
|
Plans ACCEPTED BY PLAN TECH | | | 3/3/2006 | | |
|
|
|
|
Application received | | | 3/3/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/3/2006 | | |
|
|
|
|