Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00528
StatusFinaled
Name MURPHY ASPHALT & CONSTRUCTION
Site Address 8300 W OVERLAND RD
Project NameWAL-MART
Customer Number 
ePlanReviewNo
Description
(Murphy Asphalt & Construction RCE-1527) (WAL-MART)(GENERAL STORE REMODEL) Some new interior remodel work in an existing 230,935 sq. ft. retail building per approved plans. Most of the work includes interior finish changes. The vision center, pharmacy, and photo lab will be remodeled and a dairy cooler will be expanded. A temporary pharmacy will be constructed per plans while the actual pharmacy area is remodeled. Work to include some new interior walls and doors, interior finish, some new service counters, some new sinks and counters, replacing all fixtures and stalls in restrooms, a new accessible restroom in pharmacy, new shade cloth at garden center, fire sprinkler work, mechanical work, plumbing work, and electrical work. This is a Scope of Work Permit. A Letter of Completion is to be issued when done. NOTE: This building is fully fire sprinklered and has 60' minimum setbacks for unlimited area. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes3/6/20063/6/20063/14/2007 DONE
Third Notice BLD1/8/20071/8/20073/1/2007 DONE
Second Notice has not been responded to.
Second Notice BLD12/27/200612/27/20061/8/2007 DONE
First Notice has not been responded to.
First Notice10/3/200610/3/200612/27/2006 DONE
DetailsMike Jordan
BLD-Final10/2/200610/3/200610/3/2006APASS
DetailsMike Jordan
steve payne mgr/Ken Rosewell asst mgr; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
DOC - Permit Finaled10/3/200610/3/200610/3/2006PPASS
DetailsMike Jordan
All issues have been resolved.
FIRE-Final Inspection10/2/200610/2/200610/2/2006PPASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection9/11/20069/11/20069/11/2006PFAIL
DetailsTroy Cobbley
Fire extinguisher in the optical center needs lowered and the sprinkler canopy in the RX restroom needs installed correctly.
BLD-Final9/11/20069/11/20069/11/2006ACANC
DetailsTroy Cobbley
BLD-Final9/8/20069/11/20069/11/2006AFAIL
DetailsMike Jordan
dennis; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. HC sign required on door to restroom at Rx. Locks need to be switched out at rear restrooms. Also needs mech final. Sub contractor has not paid tthe reqiured fees.
BLD-Conference9/8/20069/8/20069/8/2006PPASS
DetailsMike Jordan
Spoke to contractor on phone regarding what sign offs were left for finals.
BLD-Framing/Rough-in6/16/20066/16/20066/16/2006PPASS
DetailsJim Sly
tom - bathroom walls in pharmacy area; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Framing/Rough-in6/14/20066/14/20066/14/2006PPASS
DetailsMike Jordan
tom - pharmacy area; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. Interior framing for new pharmacy wall and verified additional door on cooler expansion.
Issue PAID IN FULL permit  5/4/2006 DONE
Routing - PLAN CHECK4/7/2006 4/25/2006 PASS
Permit and plans approved and taken to front desk.
Plan assigned to (JCB)3/9/2006 4/25/2006 PASS
4/25/2006 11:22:56 JCB - activity updated through activity BLDA022 from case BLD06-00528.
Routing - PLANNING4/25/2006 4/25/2006 PASS
The applicant submitted a letter requesting the exterior painting not be included with this permit. Only the interior work is approved by Planning.
PLANS/APPL TAKEN TO FRONT DESK  4/25/2006 PASS
Inspection Record Card- Bld  4/25/2006 DONE
Telephone call  4/25/2006 DONE
tlk to teresa jones ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  4/25/2006 DONE
Plan resubmittals received  4/21/2006 DONE
Received 1 transmittal letter,1 review report, wood frame specifications,1 mechanical compliance, 1 lighting compliance & 3 copys of sheets C1,A1.1,A2.1,A3,PH1,TC1,GA1,GA2,M2,MPH1,GP1,GR1,E1.1,E2.4,E4.1,E4.2 EPH,GEI,EC1 taken to Jason B.
Routing - FIRE4/6/2006 4/7/2006 PASS
Attached reveiw comments to plans.
1st review completed  4/7/2006 FAIL
Failed Planning and Plan Check.
Routing - PLANNING4/5/2006 4/6/2006 FAIL
To Sarah Schafer. A note on sheet A1 indicates the exterior of the building will be painted. Sarah indicated that a Zoning Certificate would be required. spoke with applicant regarding the zoning certificate. They should be submitting soon.
Then route plans to Sam Rogers in Fire.
Plan resubmittals requested  4/5/2006 DONE
Plan resubmittals and written response required for further review.
Routing - PLAN CHECK3/13/2006 4/5/2006 FAIL
Plan review e-mailed and faxed to architect. Plan resubmittals and written response required for further review. Plans to Planning and then to the Fire Department for review.
Routing - PLUMBING3/13/2006 3/13/2006 PASS
additional cross connection protection may be required at the pharmacy sink. 120 deg. max hot water to all public lavs.
Routing - PUBLIC WORKS3/10/2006 3/13/2006 PASS
Pending Assignment by MYS3/6/2006 3/9/2006 DONE
3/9/2006 17:41:32 MYS - activity updated through activity BLDA184 from case BLD06-00528.
Recd Pcfee & Taken To Pln CK  3/6/2006  
Plans ACCEPTED BY PLAN TECH  3/6/2006  
Application received  3/6/2006