Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD06-00531
StatusFinaled
Name WESTERN CONSTRUCTION SERVICES INC
Site Address 3809 W STATE ST
Project NameSTARBUCKS
Customer Number 
ePlanReviewNo
Description
(LODMAN COMMERCIAL CONST RCE #311/4/25/06/MLS)* (STARBUCKS) New coffee shop tenant to occupy the entire existing 1,692 sq. ft. vacant shell building per approved plans on file and DRH05-00286. Shell building was done under BLD05-03475. Work to include a new exterior drive-up window with awning, new interior walls and doors, interior finish, new soffit and suspended ceiling, two new accessible restrooms, counters/casework, new sinks, new mechanical, new plumbing, and new electrical work. Deferred Submittal information/engineering to be provided to the Building Inspector in the field for the new awning above the drive-up window. A Certificate of Occupancy is to be issued when done. NOTE: This building is not fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  5/17/2016 DONE
Telephone call  7/24/2007 DONE
lft vm with john Gain regarding the final cert of value that is needed at ASAP 12:25 pm
Telephone call  4/12/2007 DONE
call to karen w/ western construction, she stated she hadn't rcvd the notices, but would look into and get the fv out asap. faxed the notices and fv certs to her at her fax ###-####
Second Notice BLD9/25/20069/25/20061/8/2007 DONE
First Notice has not been responded to.
First Notice 7/27/20069/25/2006 DONE
Permanent occupancy  7/27/2006 DONE
Perm. Occ. Cert. # 11154 issued 7-27-06 to Starbuck's.
BLD-Final7/26/20067/26/20067/26/2006PPASS
DetailsTony Young
can be combined with Benchmark's shell insp- wasn't sure they would be ready for morning as we discussed. Thank you.; Phone #: ###-#### Internet Inspection Request from: John Lodman
Permanent Occupancy 7/26/20067/26/2006 DONE
Details
BLD-Conference7/24/20067/25/20067/25/2006APASS
DetailsTony Young
joint conference with benchmark const. thank you tony.; Phone #: ###-#### Internet Inspection Request from: John Lodman
conf. on final
FIRE-Final Inspection7/24/20067/24/20067/24/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection7/20/20067/21/20067/21/2006AFAIL
DetailsTroy Cobbley
Provide the correct sticker for the door, provide the additional exit sign and exit discharge lighting as noted on the approved plans
FIRE-Final Inspection7/19/20067/20/20067/20/2006ACANC
DetailsTroy Cobbley
Cancel per John Lodman
BLD-Other7/12/20067/13/20067/13/2006APASS
DetailsMike Jordan
Good morning, elect. passed, mech final this morning. Sorry about Wednesday, mech did not schedule as promised. Thank you.; Phone #: ###-#### Internet Inspection Request from: John Lodman. Ceiling grid ok.
BLD-Other7/12/20067/12/20067/12/2006ACANC
DetailsTony Young
Ceiling inspection. Requesting late morning if possible. Electrical and mech are scheduled for this morning also. Tight schedule.; Phone #: ###-#### Internet Inspection Request from: John Lodman
paving co. in the way,, can look at ceiling at final
Case Summary (BLD)  7/5/2006  
Case Summary (BLD)  7/5/2006  
FIRE-Conference6/6/20066/7/20066/7/2006ADONE
DetailsTroy Cobbley
I told John that I was not concerned about the open area of the ceiling and that it appears that the duct smoke detectors are not going to be required.
BLD-Wall cover6/5/20066/6/20066/6/2006PPART
DetailsTony Young
Exterior walls covered under shell building permit. Cover for interior partition framing and toilet room ceilings please.; Phone #: ###-#### Internet Inspection Request from: John Lodman
wip,, ok pending trades
Issue PAID IN FULL permit  4/26/2006  
Print Occupancy Form  4/13/2006 DONE
Telephone call  4/13/2006 DONE
lft vm with jeff ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  4/13/2006 DONE
1st review completed  4/12/2006 PASS
Routing - PLAN CHECK4/12/2006 4/12/2006 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/12/2006 PASS
Plan assigned to (JCB)3/16/2006 4/12/2006 PASS
4/12/2006 16:34:48 JCB - activity updated through activity BLDA022 from case BLD06-00531.
Routing - FIRE4/7/2006 4/12/2006 PASS
Attached review comments to plans. Faxed review comments to architect.
Telephone call  4/7/2006 DONE
Talked with architect representative to clarify a few issues. He requested that the new fabric covered/noncombustible framed awning (over drive-up window) manufacturer information/engineering be provided as a Deferrred Submittal to the Building Inspector in the field.
Routing - PLAN CHECK3/20/2006 4/7/2006 PEND
Plan review e-mailed and faxed to architect. No response required. Plans to route to Fire Dept. for review. When approved by Fire Dept. the permit can be issued.
Routing - PLUMBING3/20/2006 3/20/2006 PASS
r.p. required upstream of the filtered water equipment and the espresso mechine, verify thermol expantion tank sizing prior to installation, all water piping above the ceiling must be below the insulation.
Routing - PLANNING3/16/2006 3/20/2006 PASS
Sarah Schafer DRH05-00286

Approved per DRH05-00286.
Routing - PUBLIC WORKS3/16/2006 3/16/2006 PASS
Application received  3/7/2006  
Recd Pcfee & Taken To Pln CK  3/7/2006  
Plans ACCEPTED BY PLAN TECH  3/7/2006  
Third Notice BLD1/8/20071/8/2007   
Second Notice has not been responded to.
Fee Review-notes3/7/20063/7/2006