Letter of compliance | | | 10/27/2006 | | DONE |
|
|
|
Letter of Compliance issued 10-27-06
|
BLD-Final | 10/24/2006 | 10/24/2006 | 10/24/2006 | P | PASS |
Mike Jordan
|
|
|
val; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Final ok.
|
FIRE-Final Inspection | 10/23/2006 | 10/24/2006 | 10/24/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Final | 10/9/2006 | 10/10/2006 | 10/10/2006 | A | NR |
Mike Jordan
|
|
|
Val, please call 1st; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Needs others to final first.
|
Inspection Record Card- Bld | | | 10/10/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2006 | | DONE |
|
|
|
|
BLD-Aging Inspection | 9/15/2006 | 9/15/2006 | 9/21/2006 | | PASS |
Mike Jordan
|
|
|
wip. should be ready for finals in next couple of weeks as per contractor.
|
Inspection Record Card- Bld | | | 7/14/2006 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 6/1/2006 | 6/2/2006 | 6/2/2006 | A | PASS |
Mike Jordan
|
|
|
val; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Inspection Record Card- Bld | | | 5/9/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/9/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/26/2006 | | 5/8/2006 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 3/16/2006 | | 5/8/2006 | | PASS |
|
|
|
5/8/2006 13:54:54 RMH - activity updated through activity BLDA022 from case BLD06-00536.
|
Plan resubmittals received | | | 5/4/2006 | | |
|
|
|
Received 3 copies of the follwing: A1, A2, P2, P3 taken to Ron H.
|
Routing - FIRE | 4/24/2006 | | 4/26/2006 | | PASS |
|
|
|
Attached review comments to plans. Did not fax comments to architect because no fax number is provided on application.
|
Routing - PLAN CHECK | 3/28/2006 | | 4/24/2006 | | FAIL |
|
|
|
Mailed requirements to architect and routed plans to fire. 4/24/06
|
Plan resubmittals received | | | 4/14/2006 | | |
|
|
|
Recieved 3 copies of the following forms E2, E3, E4, E5, M1, M2, M3, P3, P5, P1, P4, P2, A1, A2 and taken to Ron Hill
|
Routing - FIRE | 3/27/2006 | | 3/28/2006 | | FAIL |
|
|
|
Attached resubmittal requirements to plans.
|
1st review completed | | | 3/28/2006 | | FAIL |
|
|
|
Failed Plan Check and Fire.
|
Routing - PLAN CHECK | 3/16/2006 | | 3/27/2006 | | FAIL |
|
|
|
Mailed requirements to the architect 3/27/06 routed plans to fire
|
Case Summary (BLD) | | | 3/27/2006 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2006 | | 3/16/2006 | | PASS |
|
|
|
|
Application received | | | 3/7/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/7/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/7/2006 | | |
|
|
|
|
Fee Review-notes | 3/7/2006 | 3/7/2006 | | | |
|
|
|
|