Permit Information
Permit NumberBLD06-00569
StatusFinaled
Name WELLER HOLDING
Site Address 8484 W VICTORY RD
Project NameWELLER PARTS
Customer Number 
ePlanReviewNo
Description
Weller Parts Store -RCE 1875 To construct a 11,921 sq. ft. one story Type III-B fully fire sprinkled storage\office building. Other work includes all site improvements, landscaping and paving per approved plans, DRH05-00431. Fire sprinklers used for area. Separate plans and permits are required prior to installing any racking systems greater than 8 feet.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD5/25/20075/25/200712/24/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Telephone call  10/4/2007  
tlk to adam 2:30 regarding the final values he said that he will being looking at bld05-02719, bld05-03054, bld06-00569 and bld05-2616 will be given to Ron Juhnke
Second Notice BLD5/9/20075/9/20075/25/2007 DONE
First Notice has not been responded to.
First Notice 4/20/20075/9/2007 DONE
Permanent occupancy  4/20/2007 DONE
Perm. Occ. Cert. # 11535 issued 4-20-07 to the Weller Parts Store.
Code Occupancy Approval4/17/20074/17/20074/18/2007PPASS
DetailsScott M.Brown
ALL IN WILL SIGN FINAL AT CITY HALL
Permanent Occupancy 4/18/20074/18/2007 DONE
Details
BLD-Final2/28/20072/28/20072/28/2007 DONE
Final approved for perm. occ.
PubWorks Occupancy Approval2/14/20072/14/20072/14/2007 DONE
Signed permanent occupancy 02/12/07 R. Rokovtiz.
FIRE-Final Inspection2/12/20072/12/20072/12/2007PPASS
DetailsTroy Cobbley
LIfe safety passed
FIRE-Final Inspection12/28/200612/29/200612/29/2006APART
DetailsTroy Cobbley
A temporary occupancy was given with dave hannimans permission until the sprinkler design/aisle widths are figured out. Also need curbing painted and the racking permit finaled.
BLD-Final12/28/200612/29/200612/29/2006PPART
DetailsMike Jordan
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. ok for temp occ. Needs fire to go perm and needs to add landing on exterior door and provide final aff. letter from special inspection agengcy.
BLD-Other12/15/200612/18/200612/18/2006PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/15/2006 at 4:22:17 PM. Contact: ###-####. grid ok
BLD-Framing/Rough-in11/14/200611/14/200611/14/2006PPASS
DetailsJim Sly
greg ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
Welding report .....OK
BLD-Framing/Rough-in11/10/200611/13/200611/13/2006ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/10/2006 at 1:27:19 PM. Contact: ###-####. Plumbing ri not completed.
BLD-Footing7/17/20067/17/20067/17/2006PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/17/2006 at 11:14:11 AM. Contact: ###-####.
BLD-Footing7/10/20067/11/20067/11/2006ADEFR
DetailsMike Jordan
craig - pouring concrete between 7 and 8 am; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. conc. placed prior to 8:00am
(F) Reprint permit  5/30/2006  
Issue PAID IN FULL permit  5/26/2006 DONE
Routing Off Site - STRUCTURAL4/18/2006 4/27/2006 PASS
Called Action Couriers for pick up
Routing - PLAN CHECK4/27/2006 4/27/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  4/27/2006 DONE
Print Occupancy Form  4/27/2006 DONE
Telephone call  4/27/2006 DONE
lft vm with wes that permit and fees are ready to be picked - needs CG RCE and ACHD
Permit Ready to Issue  4/27/2006 DONE
Plan assigned to (MLO)3/10/2006 4/27/2006 PASS
4/27/2006 10:40:53 MLO - activity updated through activity BLDA022 from case BLD06-00569.
Routing - Erosion and Sediment4/18/2006 4/19/2006 PASS
ESC plan approved with attached conditions.
Routing - PLAN CHECK4/19/2006 4/19/2006 PEND
Routing - PUBLIC WORKS4/17/2006 4/18/2006 PASS
Routing - PLAN CHECK4/18/2006 4/18/2006  
Routing - PLAN CHECK4/14/2006 4/14/2006 PEND
pending structural approval. MLO
Plan resubmittals received  4/13/2006  
recieved plan review comments, two copies of O, A-1, A-2, A-3, A-4, A-6, A-8. and three copies of S-4, S-0 taken to Mike O.
1st review completed  3/30/2006 FAIL
Failed ESC.
Routing - PLAN CHECK3/30/2006 3/30/2006 PEND
Routing - FIRE3/28/2006 3/30/2006 PASS
Attached review comments to plans. Faxed review comments to architect.
Routing - PLAN CHECK3/23/2006 3/28/2006 FAIL
corrections sent to architect MLO
Routing Off Site - STRUCTURAL3/10/2006 3/28/2006 FAIL
Corrections sent to architect. MLO
Plan resubmittals requested  3/28/2006 DONE
IBC corrections
Routing - PLANNING3/20/2006 3/22/2006 PASS
Julie A.
Routing - PLUMBING3/17/2006 3/20/2006 PASS
approved per plan,note and 2003 UPC THESE PLANS ARE NOT STAMPED APPROVED BY PLUMBING. MLO Plans stamped approved by L.Rice on 3/27/2006.
Routing - Erosion and Sediment3/16/2006 3/17/2006 FAIL
ESC application does not include the RP as required by BMC 8-17. BLD does call out the contractor so TBD is not acceptable.
Routing - PUBLIC WORKS4/13/2006 3/16/2006 FAIL
Drainage revisions required. Contact Brian Murphy ###-####
Routing - PLANNING Land Div3/10/2006 3/13/2006 PASS
Parcel is a platted lot.
Plans ACCEPTED BY PLAN TECH  3/10/2006  
Plan routing begun/NEW & ADDTN  3/10/2006  
Application received  3/9/2006  
Recd Pcfee & Taken To Pln CK  3/9/2006  
Fee Review-notes3/9/20063/9/2006