Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00582
StatusFinaled
Name MTN WEST SENIOR HOUSING
Site Address 5850 N FIVE MILE RD
Project NameBONAVENTURE PLACE
Customer Number 
ePlanReviewNo
Description
(Bonaventure Place Retirement Community) This building is fully sprinklered for allowable area increase and requirements due to occupancy use group based on building stories & number of units. To construct a 1-hour fire-resistive, wood & steel, three story, 62 unit (23 over 800 sq. ft.) residential retirement facility with a two story common assembly area with kitchen. All fire resistive construction per listed assemblies on plans. There is a 1-hour fire barrier wall between the R2/A2 areas for fire area compliance. DRH05-00320 CUP05-00028 drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  11/28/2007  
Second Notice BLD10/17/200710/17/200710/30/2007 DONE
First Notice has not been responded to.
First Notice 10/3/200710/17/2007 DONE
FIRE-Final Inspection10/2/200710/2/200710/3/2007PPASS
DetailsTroy Cobbley
Life safety passed
Permanent Occupancy  10/3/2007 DONE
BLD-Final10/2/200710/2/200710/2/2007PPASS
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK for Perm Occ.
Code Occupancy Approval9/7/20079/7/20079/7/2007APASS
DetailsCarol Montgomery
Code Occupancy Approval Temp9/5/20079/5/20079/5/2007AFAIL
DetailsCarol Montgomery
Made inspection of site on 9-4-2007. Still have a small amount of hydroseeding to do and the remainder of the landscaping (incl. undergrd. sprinkle system) at the sw corner of the project. There is a $9,400.00 Bond in place so I am signing off on temporary(s)
Code Occupancy Approval9/5/20079/4/20079/5/2007PCANC
DetailsCarol Montgomery
BLD-Final8/31/20079/4/20079/4/2007PNR
DetailsJim Sly
Final for A and B wings. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Conference8/31/20079/4/20078/31/2007ACANC
DetailsJim Sly
Final in A and B wings! Phone #: ###-#### Internet Inspection Request from: Dale Shuart Inspection cancelled from web by: Dale Shuart
BLD-Energy code compliance8/24/20078/27/20078/27/2007APASS
DetailsJim Sly
Please inspect final attic insulation in A and B wings. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Other8/16/20078/17/20078/17/2007APART
DetailsJim Sly
Please inspect kitchen T-bar ceiling (B-wing). Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Above ceiling OK.......Need to re-inspect penitrations thru 2hr CMU wall in Kitchen area.
BLD-Other8/9/20078/10/20078/10/2007PPASS
DetailsJim Sly
Please inspect 2nd floor B-wing T-bar ceiling. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Other8/3/20078/7/20078/7/2007APASS
DetailsJim Sly
Please inspect B-wing 1st floor T-bar ceiling. Thanks you. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover7/6/20077/6/20077/6/2007PPASS
DetailsJim Sly
Please inspect 1st floor B-wing, sheetrock nailing in completed units. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover7/5/20077/5/20077/5/2007PPASS
DetailsJim Sly
Please inspect 1st layer sheetrock nailing on 1st floor of B-wing. Thanks Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover7/2/20077/3/20077/3/2007APASS
DetailsJim Sly
Please inspect 2nd floor B-wing completed units sheetrock. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Other6/28/20076/29/20076/29/2007PPASS
DetailsJim Sly
Please inspect 1st and 2nd floor A-wing T-bar ceiling. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Energy code compliance6/28/20076/29/20076/29/2007APASS
DetailsJim Sly
Please inspect 2nd floor B-wing insulation. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover6/28/20076/28/20076/28/2007PPASS
DetailsJim Sly
Please inspect 1st layer lids nailing on 2nd floor B-wing. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in6/25/20076/26/20076/26/2007APASS
DetailsJim Sly
Please inspect framing on all floors of B-wing - see Dale first. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in6/25/20076/25/20076/25/2007PCANC
DetailsJim Sly
Please inspect framing on all floors of B-wing - see Dale first. Thanks! Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover6/20/20076/20/20076/20/2007PPASS
DetailsJim Sly
2nd layer sheetrock nailing on 3rd floor B-wing. :) Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover6/19/20076/19/20076/19/2007PPASS
DetailsJim Sly
Please inspect 3rd floor B-wing 1st layer sheetrock nailing in completed units - early PM if possible. Thanks Jim. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Energy code compliance6/12/20076/12/20076/12/2007PPASS
DetailsJim Sly
Please inspect 3rd floor B-wing insulation. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Other6/5/20076/6/20076/6/2007ANR
DetailsJim Sly
Please inspect T-bar ceiling grid on all 3 floors of A-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Need to complete firestopping.
BLD-Wall cover5/21/20075/21/20075/21/2007PPASS
DetailsJim Sly
Please inspect 3rd floor A-wing sheetrock nailing. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover5/15/20075/16/20075/16/2007APASS
DetailsJim Sly
Please inspect 3rd floor A-wing 1st layer of sheetrock. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover5/15/20075/15/20075/15/2007PCANC
DetailsJim Sly
Please inspect 3rd floor A-wing 1st layer sheetrock nailing. Thanks! Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in5/1/20075/1/20075/1/2007PPASS
DetailsJim Sly
Please inspect framing in B-wing kitchen. Thanks Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Energy code compliance4/26/20074/26/20074/26/2007PPASS
DetailsJim Sly
Please inspect A-wing 3rd floor insulation. Thanks! Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in4/16/20074/17/20074/17/2007APASS
DetailsJim Sly
Please inspect 3rd floor framing in A-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Wall cover4/12/20074/12/20074/12/2007PPASS
DetailsJim Sly
Please inspect nailing on 2nd floor of A-wing in completed units. Anytime today is fine. Thanks. Phone #: ###-####
BLD-Wall cover4/4/20074/4/20074/4/2007PPASS
DetailsJim Sly
Please inspect 1st layer sheetrock nailing in ceiling on 2nd floor of A-wing. Thanks. Phone #: ###-####
BLD-Wall cover4/2/20074/2/20074/2/2007PPASS
DetailsJim Sly
Please inspect sheetrock nailing in completed units on 1st floor of A-wing. Thanks. Phone #: ###-####
BLD-Framing/Rough-in3/23/20073/26/20073/26/2007APART
DetailsJim Sly
Please inspect B-wing elevator framing. Thanks. Phone #: ###-####
OK
BLD-Wall cover3/23/20073/26/20073/26/2007APART
DetailsJim Sly
Please inspect 1st layer sheetrock nailing on 1st floor of A-wing. Thanks. Phone #: ###-#### OK
BLD-Framing/Rough-in3/20/20073/21/20073/21/2007PCANC
DetailsJim Sly
Please inspect 2nd floor A-wing. Thanks. Phone #: ###-####
2nd floor OK to insulate.
BLD-Framing/Rough-in3/19/20073/20/20073/20/2007PPART
DetailsJim Sly
Please inspect 1st and 2nd floor at A-wing. Thanks. Phone #: ###-####
1st floor OK to cover
BLD-Framing/Rough-in3/16/20073/19/20073/19/2007APART
DetailsJim Sly
Please inspect A-wing framing. Thanks. Phone #: ###-####
BLD-Framing/Rough-in3/16/20073/16/20073/16/2007PPART
DetailsJim Sly
Please inspect 2nd and 3rd flooring framing at A-wing. Phone #: ###-####
Partial......recall for insp.
BLD-Other3/14/20073/15/20073/15/2007PPART
DetailsJim Sly
Please inspect all floors framing in A-wing. Phone #: ###-####
Part
BLD-Framing/Rough-in3/14/20073/15/20073/15/2007PPART
DetailsJim Sly
Please inspect B-wing sheer. Phone #: ###-####
Part
BLD-Other3/13/20073/15/20073/14/2007PCANC
DetailsJim Sly
Please inspect all floors framing in A-wing. Thanks. Phone #: ###-####
BLD-Framing/Rough-in3/12/20073/15/20073/14/2007PCANC
DetailsJim Sly
Please inspect B-wing sheer. Thanks. Phone #: ###-####
BLD-Framing/Rough-in2/26/20072/27/20072/27/2007APART
DetailsJim Sly
Please inspect roof nailing at B-wing. Thanks. Phone #: ###-####
Roof OK
Plan resubmittals received  1/26/2007  
ok to log in as resubmittals per Dan Stuart; The following received for building A: 1 copy of pg 1 of 1 Roof Truss Layout, 2 copies of truss drawing packages from Idaho Truss; The following received for building B: 3 transmittal sheets, 3 copies of pg 1 of 1 roof truss layout, 3 copies of truss drawing packages from Idaho Truss; taken to Dan Stuart
BLD-Framing/Rough-in1/23/20071/23/20071/23/2007PPART
DetailsJim Sly
Please inspect framing of A-wing elevator (will also need C-wing elevator inspected - I''ll request seperately through C-wing permit). Thanks. Phone #: ###-####
BLD-Framing/Rough-in12/27/200612/28/200612/28/2006APART
DetailsJim Sly
Please inspect A-wing roof nailing (partial). Anytime AM or PM.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Roof nailing OK
BLD-Framing/Rough-in12/14/200612/15/200612/15/2006APASS
DetailsJim Sly
Please inspect partial A-wing shear nailing Friday AM sometime. Thanks :); Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK pending special insp (MTI) .
BLD-Framing/Rough-in12/4/200612/4/200612/4/2006PPART
DetailsJim Sly
Please inspect shear nailing on 1st floor of A-wing this afternoon. Thanks!; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Shear at A wing 1st floor OK....MTI special insp and approval.
Additional plans submitted  12/1/2006 DONE
Received two copies of Sheets 1, 2, 3, 4, 5, 6, 7, 8 of 8 showing layout of structural floor framing & beams for second & third floor. These plans were prepared and stamped by an Idaho licensed engineer, Aaron M. Reed and have been reviewed and approved by Matthew Gralund, Project Structural Engineer. Copy of deferred submittal framing joists and beams included in original plans and copy to job site.
Additional plans submitted  10/20/2006 PASS
Resubmitted envelope energy code comcheck changing the wall insulation from R21 of original plans to R19. R19 is okay as compliance with IECC is maintained. Copy to inspector, Jim Sly.
BLD-Foundation10/17/200610/18/200610/18/2006APART
DetailsJim Sly
Please inspect B-wing rebar Wed. morning. Thanks!; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Footing10/3/200610/4/200610/4/2006APART
DetailsJim Sly
Please inspect elevator shaft in B-wing.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK pend MTI insp, tests and appr.
BLD-Footing10/2/200610/2/200610/2/2006PPART
DetailsJim Sly
Please inspect column footings at A-wing this afternoon.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Footing9/25/20069/27/20069/27/2006APART
DetailsJim Sly
Please inspect A-wing rebar in AM; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK pending MTI special insp, tests and approvals.
BLD-Footing9/21/20069/22/20069/22/2006APART
DetailsJim Sly
Please inspect 2-hour party wall footings tomorrow AM. Thanks.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK pending MTI special insp, tests and approvals.
BLD-Concrete9/12/20069/13/20069/13/2006APART
DetailsTony Young
Please inspect structural steel in A-wing elevator tomorrow morning. If at all possible, this afternoon would be best! Thank you.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
special inspector did this one,, ok pending report
BLD-Concrete9/8/20069/11/20069/11/2006APASS
DetailsJim Sly
Please inspection elevator structural steel around noon Monday if possible. Thanks; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Footing9/5/20069/6/20069/6/2006PPART
DetailsJim Sly
Please inspect around 2:30 or 3:00 if possible. Thanks.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Foot OK Pend special insp, tests and appr...
(F) Reprint permit  9/1/2006  
Plan assigned to (DRS)3/10/2006 8/31/2006 PASS
8/31/2006 10:59:16 MYS - activity updated through activity BLDA022 from case BLD06-00582.
Routing - PLAN CHECK8/18/2006 8/31/2006 PASS
Routing - PLUMBING8/31/2006 8/31/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/31/2006 DONE
Print Occupancy Form  8/31/2006 DONE
Permit Ready to Issue  8/31/2006 DONE
Issue PAID IN FULL permit  8/31/2006 DONE
Routing - FIRE8/15/2006 8/18/2006 PASS
Attached updated review comments to plans.
Telephone call  8/15/2006 DONE
Had phone conference call with Jason Tarkowsky, Ben Settecase and Larry with Bonaventure Plaza Assisted Living Complex to review each item of plan review conditions still needing to be addressed by design professionals. Jenifer Gilliland and Marlene Southard were with me.
Routing - PLANNING8/15/2006 8/15/2006 PASS
Approved per DRH05-00320 Modification #2.
Routing - PLANNING8/14/2006 8/15/2006 PASS
Susan Riggs ok, passed to Sara Schfer for review of DR
Routing - PLUMBING8/9/2006 8/14/2006 FAIL
see bld06 00579 for review comments.
Routing Off Site - STRUCTURAL8/2/2006 8/14/2006 PASS
8/2/06 Called Action Courier 8/2/06 @ 10:00am. BAS
8/14/06 - Received structural review approval for this permit.
Routing - PUBLIC WORKS8/9/2006 8/9/2006 PASS
Plan resubmittals requested  8/8/2006 DONE
E-mailed and faxed copy of plan review to Greg elmore.
Routing - PLAN CHECK5/22/2006 8/8/2006 FAIL
Resubmittals incomplete or incorrect for some of the original plan review comments. Copy of plan review items needing to be addressed were e-mailed and faxed to Greg Elmor. Routing to plumbing.
Plan Reviewer's activity  8/1/2006 DONE
Received copy of Matt Gralund engineering response to out outside structural engineers review dated 3/29/06. Routing copy of response, new plans and eng. calcs to Keith Jones. All to permit desk for routing.
Plan resubmittals received  7/31/2006  
Received 3 copies of the following sheets--A1.1B, A1.1C, A1.2, A1.3, A2.1, A2.1A, A2.1B, A2.1DF, A2.2, A2.2A, A2.2B, A2.2D, A2.3, A2.3A, A2.3B, A2.3D, A2.4, A3.1, A3.2, A3.3, A4.1, A4.2, A4.3, A5.1, A6.1, A6.2, A6.3, A7.1, A8.1, A8.2, A8.3, A9.1, A9.2, S0.1, S1.1A, S1.1B, S1.1C, S1.1D, S2.1A, S2.1B, S2.1C, S2.1D, S2.2A, S2.2B, S2.2C, S2.2D, S2.3A, S2.3B, S2.3C, S2.3D, S2.4, S3.1, S3.2, S5.1, S5.2, S6.1, S7.1, S7.2, S8.1, S8.2, S8.3, S8.4, S8.5, S9.1, M2.1, M2.1A, M2.1B, M2.1C, M2.2, M2.2A, M2.2B, M2.2C, M2.3, M2.3A, M2.3B, M2.3C, M2.4, M2.4A, M2.4B, M2.4C, M3.1, M3.2, M4.1, M4.2, M5.1, M5.2, P1.0, P1.1, P1.3, P1.4, P2.1, P2.2, P2.3, P2.4, P3.1, P3.2, P3.3, P3.4, P4.1, P4.2, P4.3, P4.4, P5.1, P6.1, P6.2, HOOD PERMIT DRAWING,1 set of revised structure calcs, 2 copies of Plan review response letter and taken to Dan stuart
Plan resubmittals received  6/23/2006 DONE
Received 1 transmittal , & 2 copys of sheets C1,C2,L2.1,L2.3 taken to Dan S.
1st review completed  5/22/2006 FAIL
Failed Plan Check and Fire
Routing - FIRE5/11/2006 5/22/2006 FAIL
Faxed resubmittal items to architec. Attached review comment to plans.
Routing - PLAN CHECK4/12/2006 5/8/2006 FAIL
Dan Stuart Copy of plan review report e-mailed and faxed to architect, Greg Elmore. Will route to fire code analyst when BLD06-01069 plan review is completed. there are three permits with this et of plans. Also BLD06-00579 & BLD06-00582.
Plan resubmittals requested  5/8/2006 DONE
Copy of plan review items sent to architect.
Routing - PLANNING Land Div4/14/2006 4/14/2006 PASS
Plat has been recorded.
Routing - PLANNING4/11/2006 4/12/2006 FAIL
Marty S. DRH05-00320 - The landscape plans need to be reworked and additional information submitted regarding the fencing. The parking lot islands need to contain shrubs, the evergreen trees, esp. the Austrian Pines, need to be spaced approx. 15'-20' at a minimum.

Susan R. CUP05-00028
Routing - PLUMBING3/27/2006 4/11/2006 FAIL
Routing Off Site - STRUCTURAL3/10/2006 3/29/2006 FAIL
Called Action Corrier for pick up @ 2:20
#/29/06 - Received copy of structural plan review for this project from third party under contract with city. Correction and resubmittals required. Faxed copy of review report with cover letter to architect of record, Greg Elmore, for his response.
Routing - Erosion and Sediment3/22/2006 3/27/2006 PASS
3/27/06 Refer to ESC06-00325 as master plan for project, RP must be determined before permit is issued. adh.
Routing - PUBLIC WORKS3/15/2006 3/22/2006 FAIL
Eliminate disposer(s) in kitchen. 3100 gallon grease interceptor/a typical volume/potentially to large; Need to show UPC sizing calculation; If volume prescription is correct, install two 1500 gallon interceptors; an interceptor this size will require odor control assessment. Contact Mike Hunter ###-####
Routing - PLANNING Land Div3/10/2006 3/15/2006 PEND
Do not issue the Building Permit until the Final Plat has been recorded at the County. The City Engineer signed the Final Plat in Dec. 2005.
Plans ACCEPTED BY PLAN TECH  3/10/2006  
Plan routing begun/NEW & ADDTN  3/10/2006  
Application received  3/10/2006  
Recd Pcfee & Taken To Pln CK  3/10/2006  
Routing - PLANNING6/20/2006 2/20/2006 FAIL
failed for lack of landscape plan, overall site plan of entire development and x-access agreement.
Third Notice BLD10/30/200710/30/2007   
Second Notice has not been responded to.
Fee Review-notes3/10/20063/10/2006