Second Notice | | 7/22/2009 | 8/3/2009 | | DONE |
|
|
|
|
First Notice | 7/1/2009 | 7/1/2009 | 7/22/2009 | | DONE |
Dave Hannah
|
|
|
|
BLD-Conference | 7/1/2009 | 7/1/2009 | 7/1/2009 | A | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 7/1/2009 | 7/1/2009 | 7/1/2009 | P | PASS |
Dave Hannah
|
|
|
|
Case Summary (BLD) | | | 5/16/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 5/15/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/26/2008 | | DONE |
|
|
|
|
BLD-Final | 12/11/2007 | 12/12/2007 | 12/12/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/11/2007 at 4:01:36 PM. Contact: ###-####.
|
(F) Reprint permit | | | 12/11/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/11/2007 | | DONE |
|
|
|
picked up and paid for plan mod
|
Telephone call | | | 10/31/2007 | | |
|
|
|
called ###-#### and left voicemessage for Larry Kalousek that permit is ready, & fee due
|
Ready Permit EXTENDED | | | 10/31/2007 | | |
|
|
|
|
Override - Parcel Holds | | | 9/18/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/18/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/18/2007 | | DONE |
|
|
|
tlk to martin hahle ###-#### that permit and fees are ready to picked up
|
Override - Parcel Holds | | | 9/18/2007 | | |
|
|
|
|
Permit Ready to Issue | | | 9/18/2007 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 9/7/2007 | 9/7/2007 | 9/17/2007 | | PASS |
|
|
|
9/17/2007 15:02:18 RMH - activity updated through activity BLDA022 from case BLD06-00628.
|
Routing - PLAN CHECK | 9/7/2007 | | 9/17/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2007 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 9/11/2007 | 9/11/2007 | 9/11/2007 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 9/11/2007 | | |
|
|
|
|
Plan Modification Accepted | | | 9/7/2007 | | |
|
|
|
Plan Modification accepted to re-design of removing the exit hardware on door 104A and replace with dead bolt lock. Construct exit access hallway through the bottom of stair "B" (Room #105) and routed to Ron Hill
|
BLD-Final | 8/22/2007 | 8/23/2007 | 8/24/2007 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/22/2007 at 7:44:50 AM. Contact: ###-####. ADA signs at restroom in wrong location
|
BLD-Conference | 7/11/2007 | 7/11/2007 | 7/12/2007 | P | CANC |
Dave Hannah
|
|
|
|
BLD-Final | 7/3/2007 | 7/5/2007 | 7/5/2007 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/3/2007 at 12:07:37 PM. Contact: (208) OK FOR TEMP
|
FIRE-Final Inspection | 7/2/2007 | 7/3/2007 | 7/3/2007 | A | PASS |
Forrest France
|
|
|
Corrections verified, shell fire life safety inspection passed.
|
FIRE-Final Inspection | 6/27/2007 | 6/28/2007 | 6/28/2007 | P | FAIL |
Forrest France
|
|
|
Missing exit signage at one location on each floor- see approved building plans, also discussed related life safety items.
|
BLD-Final | 6/20/2007 | 6/21/2007 | 6/25/2007 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/20/2007 at 12:33:10 PM. Contact: ###-####. walked project with contractor still needs fire life saftey final
|
Code Occupancy Approval | | | 6/12/2007 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/3/2007 | 5/4/2007 | 5/4/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/3/2007 at 5:35:11 PM. Contact: ###-####. elev fronts and lobbys ok to cover
|
BLD-Framing/Rough-in | 4/27/2007 | 4/30/2007 | 5/1/2007 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/27/2007 at 11:03:17 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/30/2007 | 5/1/2007 | 5/1/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/27/2007 at 11:03:17 AM. Contact: ###-####. ok to cover front of elev 2nd thru 6th floors
|
BLD-Framing/Rough-in | 4/17/2007 | 4/18/2007 | 4/18/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/17/2007 at 1:04:15 PM. Contact: ###-####. second floor elev and stairtowers ok to cover third floor also ok
|
BLD-Framing/Rough-in | 3/28/2007 | 3/29/2007 | 3/29/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/28/2007 at 7:56:46 AM. Contact: ###-####. ok to cover beams around stairtowers and elev shaft 1-6
|
BLD-Framing/Rough-in | 3/20/2007 | 3/21/2007 | 3/21/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/20/2007 at 11:22:44 AM. Contact: ###-####. 2nd and 6th floor and stair towers and elev ok to cover ext
|
BLD-Framing/Rough-in | 3/14/2007 | 3/15/2007 | 3/15/2007 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/14/2007 at 11:28:59 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/5/2007 | 3/6/2007 | 3/6/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/5/2007 at 3:09:03 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/1/2007 at 9:47:26 AM. Contact: ###-####. 2hr perimeter floor fire safing appears OK at 2, 3, 4, and 5th floors.
|
BLD-Final | 2/28/2007 | 2/28/2007 | 2/28/2007 | P | PART |
Dave Hannah
|
|
|
evev shaft floors 1-5
|
BLD-Framing/Rough-in | 2/27/2007 | 2/27/2007 | 2/28/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/26/2007 at 2:32:18 PM. Contact: ###-####. elev shaft walls ok to cover outerlayer floors 1 thru 5
|
BLD-Framing/Rough-in | 2/26/2007 | 2/27/2007 | 2/28/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/26/2007 at 2:32:18 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/23/2007 | 2/26/2007 | 2/26/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/23/2007 at 12:43:35 PM. Contact: ###-####.ok to cover restroom on floors 2thru4
|
BLD-Framing/Rough-in | 2/20/2007 | 2/21/2007 | 2/22/2007 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/20/2007 at 2:47:28 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/21/2007 | 2/22/2007 | 2/22/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/20/2007 at 2:47:28 PM. Contact: ###-####. ok to finish fire proofing curtain wall at floor lines ok to start sheet rocking stair tower two outer layers stair tower one ok need to remove fire coulk from around fire dampers and frame around them in walls
|
BLD-Framing/Rough-in | 2/16/2007 | 2/20/2007 | 2/20/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/16/2007 at 11:01:02 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/20/2007 | 2/20/2007 | 2/20/2007 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/16/2007 at 11:01:02 AM. Contact: ###-####. curtain wall fire proofing not installed right ok to start covering out side walls
|
BLD-Framing/Rough-in | 2/7/2007 | 2/8/2007 | 2/8/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/7/2007 at 3:18:58 PM. Contact: ###-####. stair tower framing and sheet rock also elev shafts
|
BLD-Framing/Rough-in | 1/31/2007 | 2/5/2007 | 2/5/2007 | A | DEFR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/31/2007 at 8:19:44 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/5/2007 | 2/5/2007 | 2/5/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/31/2007 at 8:19:44 AM. Contact: ###-####. crew working on stair and elev shafts all looking go
|
BLD-Framing/Rough-in | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/29/2007 at 1:09:11 PM. Contact: ###-####. ok to start rocking stair towers
|
BLD-Framing/Rough-in | 1/22/2007 | 1/24/2007 | 1/24/2007 | A | PASS |
Dave Hannah
|
|
|
justin; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 1/18/2007 | 1/19/2007 | 1/22/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/18/2007 at 2:21:59 PM. Contact: ###-####.parapit ok
|
BLD-Framing/Rough-in | 1/16/2007 | 1/17/2007 | 1/18/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/16/2007 at 3:22:32 PM. Contact: ###-####. ext sheeting ok also parapit framing ok but needs to be reveiwed by arct
|
BLD-Framing/Rough-in | 1/12/2007 | 1/16/2007 | 1/16/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/12/2007 at 10:35:45 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/2/2007 | 1/3/2007 | 1/3/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/2/2007 at 3:59:32 PM. Contact: ###-####. ext curten wall framing 1st - 4th ok to cover
|
BLD-Framing/Rough-in | 12/21/2006 | 12/26/2006 | 12/27/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/21/2006 at 4:22:02 PM. Contact: ###-####. needs fix bracing and add screws
|
BLD-Framing/Rough-in | 12/7/2006 | 12/8/2006 | 12/11/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/7/2006 at 11:57:49 AM. Contact: ###-####.needs to fix framing on north face floors 1thru 3rd
|
BLD-Foundation | 8/9/2006 | 8/11/2006 | 8/11/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/9/2006 at 2:03:13 PM. Contact: ###-####.
|
BLD-Footing | 8/9/2006 | 8/11/2006 | 8/11/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/9/2006 at 2:02:29 PM. Contact: ###-####.
|
BLD-Foundation | 8/3/2006 | 8/7/2006 | 8/8/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2006 at 1:26:28 PM. Contact: ###-####.
|
BLD-Foundation | 7/31/2006 | 8/1/2006 | 8/1/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/31/2006 at 10:44:31 AM. Contact: ###-####.
|
BLD-Footing | 7/26/2006 | 7/28/2006 | 7/28/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/26/2006 at 1:18:22 PM. Contact: ###-####.
|
BLD-Foundation | 7/24/2006 | 7/25/2006 | 7/26/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/24/2006 at 11:16:57 AM. Contact: ###-####.
|
BLD-Foundation | 7/19/2006 | 7/21/2006 | 7/24/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/19/2006 at 12:03:11 PM. Contact: ###-####.
|
BLD-Foundation | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | DEFR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/19/2006 at 12:02:30 PM. Contact: ###-####. Doundation was inspected by special inspector.
|
BLD-Foundation | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/17/2006 at 12:36:46 PM. Contact: ###-####.
|
BLD-Foundation | 7/11/2006 | 7/13/2006 | 7/13/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/11/2006 at 10:42:43 AM. Contact: ###-####.
|
BLD-Footing | 7/11/2006 | 7/12/2006 | 7/13/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/11/2006 at 10:43:33 AM. Contact: ###-####.
|
BLD-Footing | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/5/2006 at 12:44:11 PM. Contact: ###-####.
|
BLD-Footing | 7/5/2006 | 7/7/2006 | 7/7/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/5/2006 at 12:44:11 PM. Contact: ###-####.ok to pour mti on site
|
BLD-Footing | 6/26/2006 | 6/27/2006 | 6/28/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/26/2006 at 3:59:04 PM. Contact: ###-####. mti on site talked with supper and spec inspector all going well
|
BLD-Footing | 6/22/2006 | 6/23/2006 | 6/27/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/22/2006 at 8:53:59 AM. Contact: ###-####.
|
BLD-Footing | 6/15/2006 | 6/19/2006 | 6/19/2006 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/15/2006 at 12:06:00 PM. Contact: ###-####.pwis mti
|
BLD-Footing | 6/12/2006 | 6/14/2006 | 6/15/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/12/2006 at 2:24:50 PM. Contact: ###-####.
|
(F) Reprint permit | | | 5/26/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/25/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/17/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2006 | | DONE |
|
|
|
called ###-#### and left voicemessage for Larry Kalousek that permit is ready, fee, and need ACHD
|
Plan assigned to (JCM) | 3/14/2006 | 3/14/2006 | 5/16/2006 | | PASS |
|
|
|
5/16/2006 16:01:10 JCM - activity updated through activity BLDA022 from case BLD06-00628.
|
Plan resubmittals received | | | 5/16/2006 | | |
|
|
|
received lochsa engineering cover sheet including (7) pages of previous calcs, & four connection types A-D.D for loads less than 80k, "2" sets of s1.02, s1.03, s3.01, s3.02
|
Routing - PLAN CHECK | 4/18/2006 | | 5/16/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2006 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/15/2006 | | DONE |
|
|
|
Consulting structural engineer corresponded directly with the project engineer by e-mail to request additional resumittals. JCM
|
Routing Off Site - STRUCTURAL | 4/28/2006 | | 5/15/2006 | | PASS |
|
|
|
called action couriers for pick up
|
Plan resubmittals received | | | 5/12/2006 | | |
|
|
|
Received 1 transmittal cover, 1 plan check comments, 3 supplemental calcs, 2 of the following sheets S1.01, S1.02, S1.03, S3.01, S3.02 and taken to John Menard
|
Plan resubmittals requested | | | 5/10/2006 | | DONE |
|
|
|
Consulting structural engineer corresponded directly with the project engineer and discussed required resumittals. JCM
|
Plan Reviewer's activity | | | 5/3/2006 | | PASS |
|
|
|
Reviewed and approved resubmitted construction documents. JCM
|
Plan resubmittals received | | | 4/28/2006 | | |
|
|
|
Received 1 transmittal, 1 comments & 1 copy of sheets S0.1,S2.01,S3.01,S3.02 taken to John M
|
Plan resubmittals received | | | 4/28/2006 | | DONE |
|
|
|
Received 1transmittal letter, 3 plan check comments, & 2 copys of sheets S0.1,S2.01,S3.01,S3.02 taken to John M.
|
Plan resubmittals received | | | 4/27/2006 | | DONE |
|
|
|
Received 1 letter of transmittal, 1 (2pg.) response to plan review report from Martin Hahle, 1 (2pg) water cooler specifications, 2 copies of the following: G2.0, A1.1, A2.3, A3.1, A3.2, A4.3, A5.1, A6.1, A9.2, M1.1, M2.1, P1.1 and taken to John M.
|
1st review completed | | | 4/18/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - FIRE | 4/17/2006 | | 4/18/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - Erosion and Sediment | 4/14/2006 | | 4/17/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals requested | | | 4/14/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 4/4/2006 | | 4/14/2006 | | FAIL |
|
|
|
John M.
|
Routing Off Site - STRUCTURAL | 3/15/2006 | | 4/14/2006 | | FAIL |
|
|
|
Called Action Courier for Pick up at 2:30pm on 3/15/06 BAS - Received a comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 4/14/2006 | | DONE |
|
|
|
E-mailed the architect a copy of the plans review comment list requesting revisions. JCM
|
Plan resubmittals received | | | 4/6/2006 | | DONE |
|
|
|
Received 1 letter of transmittal,1 letter, 2 ESC Narratives & 1 copy of sheets C1 of 4,C2 of 4,C3 of 4, C4 of 4 taken to John M.
|
Routing - PLANNING | 3/27/2006 | | 4/3/2006 | | PASS |
|
|
|
Approved DRH03-00228 (3/30/06) - Marty S.
Routed to Carl M. for review per CUP05-00107.
|
Routing - PLUMBING | 3/22/2006 | | 3/27/2006 | | PASS |
|
|
|
80 psi max. on water system. 120 deg max. hot water to public lavs.
|
Routing - Erosion and Sediment | 3/22/2006 | | 3/22/2006 | | FAIL |
|
|
|
ESC plan does not meet requirements per BMC 8-17. Checklist completed and faxed to Plan Designer.
|
Routing - PUBLIC WORKS | 3/15/2006 | | 3/22/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 3/15/2006 | | 3/15/2006 | | PASS |
|
|
|
The property is a combination of contiguous existing platted lots.
|
Application received | | | 3/14/2006 | | |
|
|
|
|
Pending Assignment by MYS | 3/14/2006 | | 3/14/2006 | | DONE |
|
|
|
3/14/2006 16:57:30 B_S - activity updated through activity BLDA166 from case BLD06-00628.
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/14/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/14/2006 | | |
|
|
|
|
Fee Review-notes | 3/14/2006 | 3/14/2006 | | | |
|
|
|
|