LAYTON CONST RCE #6233//(CABELA'S)(FRANKLIN TOWNE PLAZA) To construct a new exterior canopy on the exterior of an existing builidng, install exterior doors, any related site work per approved plans and DRH06-00057. No occupancy of interior tenant space allowed under this permit. A separate permit will be issued for the tenant improvement to the interior of space. This building is fully fire sprinklered for allowed area. All alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. SEE ATTACHED LIST FOR SPECIAL INSPECTION REQUIREMENTS (RMH)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/21/20068/21/20068/21/2006PPASS
DetailsTroy Cobbley
Life safety finaled
BLD-Footing6/2/20066/5/20066/5/2006PDEFR
DetailsMike Jordan
kevin Note: as close 1:00 pm; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. work inspected by special insp.
BLD-Concrete6/1/20066/2/20066/2/2006PDONE
DetailsMike Jordan
collumn insp///request 1pm//kevin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Placement completed when on site. rebar and conc. had special insp.
BLD-Footing5/26/20065/31/20065/31/2006PPART
DetailsMike Jordan
dwayne; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Column pad footings, north side of bldg. Needs to clean bottom of footings.
BLD-Footing5/26/20065/30/20065/30/2006PPASS
DetailsMike Jordan
dwayne; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Exterior column pad footings North side of bldg.
BLD-Footing5/23/20065/24/20065/24/2006APART
DetailsMike Jordan
dwayne Note: pouring at 3:00; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. wip. Bottom of footings were compacted vand tested. requested scope of work letter from special insp.
BLD-Footing5/19/20065/19/20065/19/2006PNR
DetailsMike Jordan
dwayne; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Called in for interior column pad footings. rebar was not yet in place. Contractor needs to get geo-tech engineer to verify 3000psf soil bearing pressure of in place material. Special insp. for concrete is also required.
Issue PAID IN FULL permit  5/5/2006  
Telephone call  5/1/2006 DONE
called ###-#### and left message for Jeff Miller w/receptionist that permit is ready and fee and need RCE#
Permit Ready to Issue  5/1/2006 DONE
Routing - Erosion and Sediment4/28/2006 4/28/2006 PASS
ESC waiver request approved with attached conditions.
Routing - PLAN CHECK4/28/2006 4/28/2006 PASS
Routing Off Site - STRUCTURAL4/26/2006 4/28/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  4/28/2006 DONE
Inspection Record Card- Bld  4/28/2006 DONE
Plan assigned to (R_H)3/15/2006 4/28/2006 PASS
4/28/2006 11:47:44 RMH - activity updated through activity BLDA022 from case BLD06-00632.
Case Summary (BLD)  4/27/2006 DONE
Plan resubmittals received  4/25/2006  
Received via fax a 2 page response letter to Plan review comments and taken to Ron Hill
Routing Off Site - STRUCTURAL4/20/2006 4/25/2006 FAIL
Received 1 cover transmittal letter, 1 copy of response comments, 1 copy of plan review comments, 1 packet of structural calcs, 3 copies of S-3.01, 3 copies of S-4.01 and Sent by Action Courrier to AHJ. Called Action Courriers @12:30pm BAS /
SECOND REVIEW FAILED. Faxed comments to the architect Brian Haines and engineer Kenneth Bell on 4/25/06. Written comment required.
Routing - PLANNING4/20/2006 4/20/2006 PASS
Compliance with conditions of approval met.
Plan resubmittals received  4/20/2006  
Received 1 cover transmittal letter, 1 copy of response comments, 1 copy of plan review comments, 1 packet of structural calcs, 3 copies of S-3.01, 3 copies of S-4.01 and taken to Ron Hill
Routing - PLANNING4/17/2006 4/18/2006 FAIL
Received a letter in response to design review approval/ failed building permit. Faxed the applicant a letter outlining necessary changes for approval of bld. CER
Telephone call  4/12/2006  
Spoke with Brian Haines Architect. Related to him that I have not received any resubmitted plans from my request that I had sent on the 3rd of april. He said he would look into it.
Routing - PLAN CHECK3/23/2006 4/3/2006 FAIL
Faxed and mailed requirements to Architect Brain Haines on 4/03/06
Routing Off Site - STRUCTURAL3/20/2006 4/3/2006 FAIL
Called Action Courrier for pick up @ 3:05on 3/21/06 BAS
Plan resubmittals received  3/30/2006 DONE
Received 2 copys of sheet 1 of 5 ( from Sara S. ) taken to Ron H
1st review completed  3/23/2006 FAIL
Faile Planning and ESC.
Routing - FIRE3/22/2006 3/23/2006 PASS
Attached review comments to plans. Faxed review comments to architect.
Routing - PLAN CHECK3/17/2006 3/22/2006 PEND
Routed to off site engineering review,
Routing - Erosion and Sediment3/16/2006 3/17/2006 FAIL
ESC plan waiver will be approved but rp is not listed on application and contractor is called out. Informed rp to secure certification.
Routing - PLANNING3/17/2006 3/17/2006 FAIL
Sarah Schafer DRH06-00057 Conditions of approval for the DR have not been addressed. Applicant has not supplied any documentation re: lights or mechanical screens. Applicant has not worked with staff on an appropriate solution to breaking up the wall planes. Nothing in building documents address these issues.
Routing - PUBLIC WORKS3/15/2006 3/16/2006 PASS
Override - Parcel Holds  3/15/2006  
Plans ACCEPTED BY PLAN TECH  3/15/2006  
Application received  3/15/2006  
Override - Parcel Holds  3/15/2006 FAIL
Faxed requirements to Brian Haines, and mailed structural plan review to Brian on 4/03/06
Recd Pcfee & Taken To Pln CK  3/15/2006  
Fee Review-notes3/15/20063/15/2006