FIRE-Final Inspection | 8/21/2006 | 8/21/2006 | 8/21/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Footing | 6/2/2006 | 6/5/2006 | 6/5/2006 | P | DEFR |
Mike Jordan
|
|
|
kevin Note: as close 1:00 pm; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. work inspected by special insp.
|
BLD-Concrete | 6/1/2006 | 6/2/2006 | 6/2/2006 | P | DONE |
Mike Jordan
|
|
|
collumn insp///request 1pm//kevin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Placement completed when on site. rebar and conc. had special insp.
|
BLD-Footing | 5/26/2006 | 5/31/2006 | 5/31/2006 | P | PART |
Mike Jordan
|
|
|
dwayne; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Column pad footings, north side of bldg. Needs to clean bottom of footings.
|
BLD-Footing | 5/26/2006 | 5/30/2006 | 5/30/2006 | P | PASS |
Mike Jordan
|
|
|
dwayne; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Exterior column pad footings North side of bldg.
|
BLD-Footing | 5/23/2006 | 5/24/2006 | 5/24/2006 | A | PART |
Mike Jordan
|
|
|
dwayne Note: pouring at 3:00; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. wip. Bottom of footings were compacted vand tested. requested scope of work letter from special insp.
|
BLD-Footing | 5/19/2006 | 5/19/2006 | 5/19/2006 | P | NR |
Mike Jordan
|
|
|
dwayne; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Called in for interior column pad footings. rebar was not yet in place. Contractor needs to get geo-tech engineer to verify 3000psf soil bearing pressure of in place material. Special insp. for concrete is also required.
|
Issue PAID IN FULL permit | | | 5/5/2006 | | |
|
|
|
|
Telephone call | | | 5/1/2006 | | DONE |
|
|
|
called ###-#### and left message for Jeff Miller w/receptionist that permit is ready and fee and need RCE#
|
Permit Ready to Issue | | | 5/1/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/28/2006 | | 4/28/2006 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Routing - PLAN CHECK | 4/28/2006 | | 4/28/2006 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/26/2006 | | 4/28/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2006 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 3/15/2006 | | 4/28/2006 | | PASS |
|
|
|
4/28/2006 11:47:44 RMH - activity updated through activity BLDA022 from case BLD06-00632.
|
Case Summary (BLD) | | | 4/27/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/25/2006 | | |
|
|
|
Received via fax a 2 page response letter to Plan review comments and taken to Ron Hill
|
Routing Off Site - STRUCTURAL | 4/20/2006 | | 4/25/2006 | | FAIL |
|
|
|
Received 1 cover transmittal letter, 1 copy of response comments, 1 copy of plan review comments, 1 packet of structural calcs, 3 copies of S-3.01, 3 copies of S-4.01 and Sent by Action Courrier to AHJ. Called Action Courriers @12:30pm BAS /
SECOND REVIEW FAILED. Faxed comments to the architect Brian Haines and engineer Kenneth Bell on 4/25/06. Written comment required.
|
Routing - PLANNING | 4/20/2006 | | 4/20/2006 | | PASS |
|
|
|
Compliance with conditions of approval met.
|
Plan resubmittals received | | | 4/20/2006 | | |
|
|
|
Received 1 cover transmittal letter, 1 copy of response comments, 1 copy of plan review comments, 1 packet of structural calcs, 3 copies of S-3.01, 3 copies of S-4.01 and taken to Ron Hill
|
Routing - PLANNING | 4/17/2006 | | 4/18/2006 | | FAIL |
|
|
|
Received a letter in response to design review approval/ failed building permit. Faxed the applicant a letter outlining necessary changes for approval of bld. CER
|
Telephone call | | | 4/12/2006 | | |
|
|
|
Spoke with Brian Haines Architect. Related to him that I have not received any resubmitted plans from my request that I had sent on the 3rd of april. He said he would look into it.
|
Routing - PLAN CHECK | 3/23/2006 | | 4/3/2006 | | FAIL |
|
|
|
Faxed and mailed requirements to Architect Brain Haines on 4/03/06
|
Routing Off Site - STRUCTURAL | 3/20/2006 | | 4/3/2006 | | FAIL |
|
|
|
Called Action Courrier for pick up @ 3:05on 3/21/06 BAS
|
Plan resubmittals received | | | 3/30/2006 | | DONE |
|
|
|
Received 2 copys of sheet 1 of 5 ( from Sara S. ) taken to Ron H
|
1st review completed | | | 3/23/2006 | | FAIL |
|
|
|
Faile Planning and ESC.
|
Routing - FIRE | 3/22/2006 | | 3/23/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed review comments to architect.
|
Routing - PLAN CHECK | 3/17/2006 | | 3/22/2006 | | PEND |
|
|
|
Routed to off site engineering review,
|
Routing - Erosion and Sediment | 3/16/2006 | | 3/17/2006 | | FAIL |
|
|
|
ESC plan waiver will be approved but rp is not listed on application and contractor is called out. Informed rp to secure certification.
|
Routing - PLANNING | 3/17/2006 | | 3/17/2006 | | FAIL |
|
|
|
Sarah Schafer DRH06-00057 Conditions of approval for the DR have not been addressed. Applicant has not supplied any documentation re: lights or mechanical screens. Applicant has not worked with staff on an appropriate solution to breaking up the wall planes. Nothing in building documents address these issues.
|
Routing - PUBLIC WORKS | 3/15/2006 | | 3/16/2006 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 3/15/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2006 | | |
|
|
|
|
Application received | | | 3/15/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 3/15/2006 | | FAIL |
|
|
|
Faxed requirements to Brian Haines, and mailed structural plan review to Brian on 4/03/06
|
Recd Pcfee & Taken To Pln CK | | | 3/15/2006 | | |
|
|
|
|
Fee Review-notes | 3/15/2006 | 3/15/2006 | | | |
|
|
|
|