BLD-Final | 1/25/2007 | 1/26/2007 | 1/26/2007 | P | PASS |
Jim Sly
|
|
|
Recheck on tempered windows....windows will be done before noon with tempered tint and switch out windows as needed....please, please, please get
inspection done early afternoon for funding today. Thanks,Kole Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 1/26/2007 | 1/26/2007 | 1/26/2007 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 1/25/2007 | 1/26/2007 | 1/25/2007 | A | CANC |
Dave Hannah
|
|
|
Inspection cancelled from web by: Kole Mogel
|
BLD-Final | 1/24/2007 | 1/24/2007 | 1/25/2007 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-####
|
BLD-Final | 1/25/2007 | 1/29/2007 | 1/25/2007 | P | CANC |
Tony Young
|
|
|
Cole, please call 1st for access (bond on file with Cathy); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Grading Inspection | 1/25/2007 | 1/25/2007 | 1/25/2007 | | BOND |
|
|
|
The rough grading and drainage has been completed at the above mentioned address. However, the driveway pavement, installation of the downspouts, and the construction of a small landscape wall adjacent to the patio at the rear of the house have not been completed. For this the engineer has recommended a bond of $5,000.00. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Framing/Rough-in | 8/23/2006 | 8/23/2006 | 8/25/2006 | P | PART |
Tony Young
|
|
|
Recheck stairs for final on framing.; Phone #: ###-#### Internet Inspection Request from: Kole Mogel ok in rough,, need to meet code w/ finished product
|
BLD-Energy code compliance | 8/22/2006 | 8/22/2006 | 8/22/2006 | P | PASS |
Tony Young
|
|
|
Energy Code Check, and rounded Stair Reinspection; Phone #: ###-#### Internet Inspection Request from: Kole Mogel
|
BLD-Framing/Rough-in | 8/16/2006 | 8/16/2006 | 8/16/2006 | P | PART |
Dave Hannah
|
|
|
All Corrections Complete, Stairs Will be done depending on time of inspection...stair inspection may be held over to energy per Tony. Thanks, Kole; Phone #: ###-#### still working on stairs and fire blocking ok to insulate Internet Inspection Request from: Kole Mogel
|
BLD-Conference | 8/14/2006 | 8/15/2006 | 8/15/2006 | A | PART |
Tony Young
|
|
|
If possible can we please do this late morning in order to have my framer make the conference. Thanks, Kole; Phone #: ###-#### Internet Inspection Request from: Kole Mogel conf only,, met w/ framer,, contractor,, will take care of some frame issues then call for a complete frame inspection,, stairs may have to be inspected later
|
BLD-Framing/Rough-in | 8/14/2006 | 8/14/2006 | 8/14/2006 | P | FAIL |
Tony Young
|
|
|
Framing Inspection Requested for PM on 8/14/06; Phone #: ###-#### Internet Inspection Request from: Kole Mogel walk through only,, need to meet on site to go over stairs,,,etc
|
BLD-Foundation | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/9/2006 at 8:46:37 PM. Contact: ###-####.
|
BLD-Footing | 5/8/2006 | 5/8/2006 | 5/8/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/8/2006 at 7:40:45 AM. Contact: ###-####.
|
PubWorks Subgrade Approval | 5/4/2006 | 5/4/2006 | 5/4/2006 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 4/24/2006 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 4/5/2006 | 4/5/2006 | 4/6/2006 | | PASS |
|
|
|
4/6/2006 15:36:40 SRZ - activity updated through activity BLDA022 from case BLD06-00637.
|
Case Summary (BLD) | | | 4/6/2006 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/6/2006 | | PASS |
|
|
|
Pending information from Engineer. (SRZ)
|
Plan Reviewer's activity | | | 4/6/2006 | | DONE |
|
|
|
Recieved information from Engineer. (SRZ)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/6/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/6/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/6/2006 | | DONE |
|
|
|
called ###-#### (Paramount Homes) and left voicemessage that permit is ready and fee
|
Routing - PLAN CHECK | | | 4/6/2006 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 3/15/2006 | 3/15/2006 | 4/5/2006 | | DONE |
|
|
|
|
Routing - FIRE | 3/21/2006 | | 3/22/2006 | | PASS |
|
|
|
No fire sprinklers required (Arrowhead Ridge sub)
|
Routing - Erosion and Sediment | 3/21/2006 | | 3/21/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 3/16/2006 | | 3/20/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 3/15/2006 | | 3/16/2006 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS | 3/16/2006 | | 3/16/2006 | | PASS |
|
|
|
|
Application received | | | 3/15/2006 | | |
|
|
|
|