Letter of compliance | | | 1/3/2007 | | DONE |
|
|
|
Letter of Compliance issued 1-3-07.
|
BLD-Final | 12/29/2006 | 12/29/2006 | 1/2/2007 | P | PASS |
Tony Young
|
|
|
shell and core final along with Tenant Improvement guard rail is in place now
|
BLD-Final | 12/29/2006 | 12/29/2006 | 12/29/2006 | A | NR |
Tony Young
|
|
|
public works guard rail,, verify
|
BLD-Final | 12/27/2006 | 12/27/2006 | 12/29/2006 | P | NR |
Tony Young
|
|
|
need to verify the guard rail
|
BLD-Conference | 12/20/2006 | 12/27/2006 | 12/27/2006 | A | CANC |
Tony Young
|
|
|
check on guard rail
|
BLD-Final | 12/19/2006 | 12/20/2006 | 12/20/2006 | A | PART |
Tony Young
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles just needs guard rail by rear side walk,, less than 30" drop off
|
BLD-Final | 12/5/2006 | 12/5/2006 | 12/5/2006 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/5/2006 at 6:29:01 AM. Contact: ###-####. Need to do all work in body of permit. PW has signed off, but not finaled in computer.
|
FIRE-Final Inspection | 11/28/2006 | 11/28/2006 | 11/28/2006 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
Code Occupancy Approval | 11/28/2006 | 11/28/2006 | 11/28/2006 | P | PASS |
Michael Garner
|
|
|
site inspection complete - officer completed a review of approved conditions and found that compliance has been met - case closed
|
Code Occupancy Approval | 11/28/2006 | 11/28/2006 | 11/28/2006 | P | PASS |
Michael Garner
|
|
|
|
FIRE-Final Inspection | 11/16/2006 | 11/17/2006 | 11/17/2006 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. No inspection performed.
|
Telephone call | | | 11/15/2006 | | DONE |
|
|
|
lft vm with joe stoy ###-#### that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 11/15/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 11/15/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 11/15/2006 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/15/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/15/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 10/30/2006 | 10/30/2006 | 11/14/2006 | | PASS |
|
|
|
11/14/2006 08:45:46 JCM - activity updated through activity BLDA022 from case BLD06-00658.
|
Routing - PUBLIC WORKS | 11/1/2006 | | 11/14/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/14/2006 | | 11/14/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/14/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 11/14/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/14/2006 | | DONE |
|
|
|
|
Routing - PLANNING | 10/30/2006 | | 11/1/2006 | | PASS |
|
|
|
Plans approved per DRH05-00463 MOD #1 and CUP04-00073.
|
Plan Reviewer's activity | | | 10/30/2006 | | PASS |
|
|
|
Reviewed and approved plan modification. JCM
|
Plan Modification Accepted | | | 10/27/2006 | | |
|
|
|
Plan modification accepted in response to Carl Westfall's plan review comments for the MoneyTree TI (BLd06-02350), we have added a new exterior (exit) door at the west elevation. The existing exterior door at the south elevation will serve a public restroom, which in turn will require continuous public acciss to the front of the building. We have added additional sidewalk and guard (railing) (due to the 30"+/- drop adjacent to the retention pond). Please refer to all the following sheets for revised plans and additional details: SD-1 (Arch. Site Plan), A-1 (Floor Plan), A-3 (Elevations, L-1.00 (Landscape Plan), E-2.0 (Electrical Plan). Also recieved 3 copies of 8pg. structural calculations. Routed to John Menard
|
PubWorks Occupancy Approval | 9/26/2006 | 9/26/2006 | 9/26/2006 | | DONE |
|
|
|
Reviewed, ready for acceptance after paving by R. Rokovitz. 09/19/06
|
Override - Parcel Holds | | | 9/26/2006 | | |
|
|
|
|
Plan Modification Accepted | | | 9/14/2006 | | |
|
|
|
Plan modification accepted to create an "exterior area of recue assistance" at the south exit door from the employee work area. We are enlarging the exterior concrete landing to accomodate (1) wheelchair, added signage & shifted plant materials to comply with IBC sections 1007.2, exception No. 1, sections 1007.8, 1007.6.1 & 1023.6 (per John Menard waive $500 fee); routed to John Menard
|
BLD-Energy code compliance | 8/28/2006 | 8/29/2006 | 8/29/2006 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/28/2006 at 1:13:15 PM. Contact: ###-####.
|
FIRE-Conference | 7/31/2006 | 8/1/2006 | 8/1/2006 | A | DONE |
Forrest France
|
|
|
Confrence with GC to discuss building addressing (number size, location), core and shell life safety requirements, and fire lane marking.
|
BLD-Framing/Rough-in | 7/26/2006 | 7/26/2006 | 7/26/2006 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 7/25/2006 | 7/26/2006 | 7/26/2006 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/25/2006 at 11:26:32 AM. Contact: ###-####. out of time,, rescheduled for pm
|
BLD-Foundation | 7/13/2006 | 7/14/2006 | 7/14/2006 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/13/2006 at 9:24:59 AM. Contact: ###-####. masonary on trash enclosure
|
BLD-Framing/Rough-in | 6/16/2006 | 6/19/2006 | 6/19/2006 | A | PART |
Tony Young
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley exterior ok to cover
|
BLD-Foundation | 5/12/2006 | 5/15/2006 | 5/15/2006 | A | PART |
Tony Young
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa pending s. i. report,, also need ok on redi-rod for hold downs .vs. simpson hold down bolts
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 5/12/2006 | | |
|
|
|
|
BLD-Footing | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok pending s. i. report
|
(F) Reprint permit | | | 4/24/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/21/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/17/2006 | | 4/6/2006 | | PASS |
|
|
|
4/6/2006 08:28:15 JCM - activity updated through activity BLDA022 from case BLD06-00658.
|
Routing - PLAN CHECK | 4/4/2006 | | 4/6/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/6/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 4/6/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/6/2006 | | DONE |
|
|
|
called ###-#### and left voicemessage for Doug Racine that permit is ready, fees, need GC, RCE, RP, ACHD
|
Routing - FIRE | 4/1/2006 | | 4/4/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed review comments to architect.
|
1st review completed | | | 4/4/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/1/2006 | | PASS |
|
|
|
Reviewed and approved as submiited with red lined notes. This review is for structural and nonstructural building requirements. JCM
|
Routing - PLAN CHECK | 3/30/2006 | | 4/1/2006 | | PASS |
|
|
|
John M.
|
Routing - PLANNING | 3/30/2006 | | 3/30/2006 | | PASS |
|
|
|
Approved.
|
Routing - PLANNING | 3/28/2006 | | 3/30/2006 | | PASS |
|
|
|
(Plans placed in office during vacation despite informational signage...)
cup04-00073 Angela W.
|
Routing - PLUMBING | 3/23/2006 | | 3/28/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 3/23/2006 | | 3/23/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 3/20/2006 | | 3/23/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 3/17/2006 | | 3/20/2006 | | PASS |
|
|
|
property is a platted lot.
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/17/2006 | | |
|
|
|
|
Application received | | | 3/17/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/17/2006 | | |
|
|
|
|
Fee Review-notes | 3/17/2006 | 3/17/2006 | | | |
|
|
|
|