Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00696
StatusFinaled
Name RYAN WALKER
Site Address 1113 -1115 S PHILLIPPI ST
Project Name 
Customer Number 
ePlanReviewNo
Description
CONTRACTOR RYAN WALKER REGISTRATION # RCE-14320.1113 & 1115 Phillippi To construct a 2966sq.ft. Two story DUPLEX. Each unit has three bedrooms, two and a half bathrooms, 1483sq.ft. (623sq.ft. First floor / 860sq.ft. Second floor) with a 74sq.ft. Covered front porch, and a 389sq.ft. Attached garage per approved plans, all red-lining, and Plan review report. THIS STRUCTURE IS BEING BUILT TO ONLY MEET DUPLEX STANDARDS AND NOT TO BE SOLD AS INDIVIDUAL UNITS. CAA06-00040, R-1C zoning, and building setbacks as per Cody Riddle with Planning and Zoning. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Code Occupancy Approval  4/4/2007 PASS
4-2-07 Site inspection shows that the landscape and fence are installed. O.K. to release bond.
BLD-Final1/31/20072/1/20072/1/2007APASS
DetailsTom Arcoraci
PLease call prior to inspection for access--ryan; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
DOC - Permit Finaled2/1/20072/1/20072/1/2007PPASS
DetailsTom Arcoraci
co issued as duplex
Inspection Record Card- Bld  1/19/2007  
Code Occupancy Approval Temp1/18/20071/18/20071/18/2007PFAIL
DetailsDena Gambrel
1-18-07 Need to bond for $1,177.00 for sod and fence.
Code Occupancy Approval12/20/200612/20/200612/20/2006PFAIL
DetailsDena Gambrel
FAILED. Landscaping not in the back yard on either duplex. The landscaping in the front is not the same as the plans that were approved by the City. No bark, two existing trees that were required to be left have been taken out, shrubs in front not there.....I left a correction notice that an updated landscape plan needs to be approved and once that is completed bonding could be done.
BLD-Final12/18/200612/19/200612/19/2006ANR
DetailsTom Arcoraci
ryan - please call for access ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs zoning
BLD-Framing/Rough-in8/10/20068/10/20068/11/2006PPASS
DetailsTom Arcoraci
ryan ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Plan Reviewer's activity  8/2/2006 DONE
Field Inspection requested plan review to sign-off on cricket detail. Applicant brought in new detail. I Approved and signed. I also scanned the Approved detail. (SRZ)
BLD-Framing/Rough-in7/21/20067/24/20067/24/2006AFAIL
DetailsTom Arcoraci
ryan ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie cn posted 1 hr wall not per plan steel beam requires eng ect....
BLD-Framing/Rough-in7/13/20067/13/20067/13/2006PNR
DetailsTom Arcoraci
ryan; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley NO plans or truss eng on site
BLD-Footing5/8/20065/9/20065/9/2006APART
DetailsMike Jordan
tray; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Permit Ready to Issue  4/20/2006  
Telephone call  4/20/2006 DONE
left mess that permit is ready
Issue PAID IN FULL permit  4/20/2006 DONE
Plan assigned to (SRZ)4/11/20064/11/20064/19/2006 PASS
4/19/2006 13:40:46 SRZ - activity updated through activity BLDA022 from case BLD06-00696.
Routing - PLAN CHECK3/30/2006 4/19/2006 PASS
Plan Reviewer's activity  4/19/2006 PASS
Recieved Engineering for steel column, Floor framing beam, and Footing. (SRZ)
PLANS/APPL TAKEN TO FRONT DESK  4/19/2006 DONE
Inspection Record Card- Bld  4/19/2006 DONE
Plan Reviewer's activity  4/13/2006 PASS
Recieved Foundation and Roof Framing Plan as required to complete Plan Review. (SRZ)
Plan Reviewer's activity  4/13/2006 PEND
Plan review Pending Truss Engineering. Incomplete Floor framing/roof framing plan submitted. (SRZ)
Case Summary (BLD)  4/13/2006  
Plan resubmittals received  4/12/2006 DONE
Received 2 copies of Foundation plan and 2 copies of roof framing & truss layout and taken to Sam Z.
Plan assigned to (SAM)3/21/20063/21/20064/11/2006 DONE
Plan Reviewer's activity  4/11/2006 FAIL
Applicant needs to submit roof framing plan and a Foundation plan to complete plan review. (SRZ)
Telephone call  4/11/2006 DONE
I called applicant and requested a roof plan and Foundation plan.
(SRZ)
Routing - PLANNING3/30/2006 3/30/2006 PASS
Okay per revised site and landscape plans
Routing - PLANNING3/27/2006 3/28/2006 FAIL
Building permit submittal fails to comply with the conditions of approval for CAA06-00040. Contacted applicant, will discuss issues at 8:30 a.m. on 3/29. CER
Routing - PUBLIC WORKS3/27/2006 3/27/2006 PASS
Routing - PLANNING Land Div3/22/2006 3/27/2006 PASS
property created by ROS signed by the City Planning Director in 2004.
Application received  3/21/2006