Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD06-00730
StatusFinaled
Name THORNTON-OLIVER KELLER
Site Address 600 E RIVERPARK LN
Project NameRIVER RUN BLDG D
Customer Number 
ePlanReviewNo
Description
(HC Company RCE-793) (RIVER RUN CENTER BLDG D)(RESTROOMS UPGRADE) Interior remodel to upgrade the building core restrooms on the first and second floor of an existing two story building per approved plans. Work to include some miscellaneous interior demolition work, some new one-hour rated corridor walls, some new 20 minute rated corridor doors, other new interior walls, interior finish, some minor suspended ceiling and soffit work, plumbing work, and electrical work. This permit is attached to the same set of plans along with another permit for work being done under BLD06-00731 in an adjacent building on the site. This is a Scope of Work Permit. A Letter of Completion is to be issued when done. NOTE: This building is not fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  9/23/2014 DONE
Case Summary (BLD)  11/15/2012 DONE
(F) Reprint permit  7/18/2007  
Print Statement  7/18/2007 DONE
Third Notice BLD1/8/20071/8/20073/1/2007 DONE
Second Notice has not been responded to.
Second Notice BLD12/27/200612/27/20061/8/2007 DONE
First Notice has not been responded to.
First Notice10/13/200610/13/200612/27/2006 DONE
DetailsJim Storey
BLD-Final10/12/200610/13/200610/13/2006APASS
DetailsJim Storey
darren; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
DOC - Permit Finaled10/13/200610/13/200610/13/2006PPASS
DetailsJim Storey
BLD-Final10/6/200610/9/200610/10/2006PNR
DetailsJim Storey
darin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection10/2/200610/3/200610/3/2006APASS
DetailsForrest France
Life safety passed inspection.
BLD-Framing/Rough-in8/7/20068/8/20068/8/2006APASS
DetailsJim Storey
darin - call 1/2 hr for access; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Framing/Rough-in6/5/20066/5/20066/5/2006PPASS
DetailsJim Storey
daren - ceiling insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Framing/Rough-in6/2/20066/2/20066/2/2006PFAIL
DetailsJim Storey
daren - ceiling insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Framing/Rough-in5/24/20065/24/20065/24/2006PPART
DetailsJim Storey
darren; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Issue PAID IN FULL permit  5/19/2006  
Inspection Record Card- Bld  5/18/2006 DONE
Telephone call  5/18/2006 DONE
called ###-#### and left voicemessage for Matt Rhees that permit is ready, fee and need GC & RCE
Permit Ready to Issue  5/18/2006 DONE
Routing - PLAN CHECK5/1/2006 5/17/2006 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  5/17/2006 PASS
Print Pending Permit.LaserJet4  5/17/2006  
Case Summary (BLD)  5/17/2006  
Case Summary (BLD)  5/17/2006  
Plan assigned to (JCB)3/24/2006 5/17/2006 PASS
5/17/2006 16:13:17 JCB - activity updated through activity BLDA022 from case BLD06-00730.
Plan resubmittals received  5/15/2006  
Received 1 pg response letter for Bld06-00731, 1 pg response letter for Bld06-00730, 2 copies of the following; 8 pg. structural calcs, A1.0, A2.0, A4.0, taken to Jason B.
Routing - FIRE4/28/2006 5/1/2006 PASS
Faxed review comments to architect. Inserted comments into plans.
1st review completed  5/1/2006 FAIL
Failed Plan Check.
Plan resubmittals requested  4/28/2006 DONE
Plan resubmittals and written response required for further review.
Routing - PLAN CHECK3/24/2006 4/28/2006 FAIL
Plan review e-mailed to architect. One item to address. Plans will next route to the Fire Dept. for review.
Routing - PUBLIC WORKS3/24/2006 3/24/2006 PASS
Application received  3/22/2006  
Recd Pcfee & Taken To Pln CK  3/22/2006  
Plans ACCEPTED BY PLAN TECH  3/22/2006  
Fee Review-notes3/22/20063/22/2006