PubWorks Occupancy Approval | 1/8/2007 | 1/8/2007 | 1/8/2007 | | DONE |
|
|
|
Engineer spoke with B. Murphy, project signed off by R. Anderson 01/02/2007.
|
BLD-Final | 12/29/2006 | 12/29/2006 | 12/29/2006 | P | PART |
Jim Sly
|
|
|
Shane; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett Temp Occ OK to Perm ...when P/W perms.
|
BLD-Final | 12/22/2006 | 12/26/2006 | 12/26/2006 | A | NR |
Jim Sly
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Need all req signatures...
|
FIRE-Final Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need to provide the building address
|
BLD-Final | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | CANC |
Jim Sly
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs fire final
|
BLD-Final | 12/15/2006 | 12/15/2006 | 12/15/2006 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/15/2006 at 8:42:15 AM. Contact: ###-####. Need all req signatures
|
BLD-Framing/Rough-in | 9/28/2006 | 9/29/2006 | 9/29/2006 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/28/2006 at 11:08:38 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/6/2006 | 9/6/2006 | 9/6/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/6/2006 at 6:59:35 AM. Contact: ###-####. Roof nailing and strapping at roof/wall OK
|
BLD-Foundation | 6/26/2006 | 6/28/2006 | 6/28/2006 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/26/2006 at 3:09:13 PM. Contact: ###-####.
|
BLD-Foundation | 6/23/2006 | 6/26/2006 | 6/26/2006 | A | PART |
Jim Sly
|
|
|
brian - late morning; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley Footing OK.......2500PSI No special insp req on concrete.
|
(F) Reprint permit | | | 6/8/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/4/2006 | | DONE |
|
|
|
lft vm with andrew davis - ###-#### that permit and fees are ready to picked up needs GC, ACHD and RP
|
Permit Ready to Issue | | | 5/4/2006 | | DONE |
|
|
|
|
Routing - PLUMBING | 4/27/2006 | | 5/3/2006 | | PASS |
Lee Rice
|
|
|
approved per plan and 2003 UPC
|
Routing - PLAN CHECK | 5/3/2006 | | 5/3/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2006 | | |
|
|
|
|
Plan assigned to (JCM) | 3/24/2006 | | 5/3/2006 | | PASS |
|
|
|
5/3/2006 11:55:14 JCM - activity updated through activity BLDA022 from case BLD06-00752.
|
Routing - PUBLIC WORKS | 4/26/2006 | | 4/27/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/12/2006 | | 4/26/2006 | | |
|
|
|
|
Plan resubmittals received | | | 4/26/2006 | | |
|
|
|
Received 1 copy of cover transmittal letter, 1 copy of Geotechnical Engineering Evaluation, 5 copies of C1.0, 5 copies of C1.1 and taken to John Menard
|
1st review completed | | | 4/12/2006 | | PASS |
|
|
|
|
Routing - FIRE | 4/7/2006 | | 4/12/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 4/6/2006 | | 4/7/2006 | | PASS |
|
|
|
John M.
|
Plan Reviewer's activity | | | 4/7/2006 | | PASS |
|
|
|
Plans reviewed and approved as submitted. JCM
|
Routing - PLANNING | 4/3/2006 | | 4/6/2006 | | PASS |
|
|
|
CUP05-00157 Carl M. Revised elevations to reflect required window treatment.
|
Routing Off Site - STRUCTURAL | 3/24/2006 | | 4/6/2006 | | PASS |
|
|
|
Called Action Couriers for pick up. - Received a faxed letter from the cosulting structural engineer approving the original plans and calculations. JCM
|
Routing - PLUMBING | 3/30/2006 | | 4/3/2006 | | FAIL |
|
|
|
need a civil plan showing the rain water system from the building to the site system.
|
Routing - Erosion and Sediment | 3/29/2006 | | 3/30/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 3/27/2006 | | 3/29/2006 | | FAIL |
|
|
|
Requires drainage plans: Contact Brian Murphy ###-####
|
Routing - PLANNING Land Div | 3/24/2006 | | 3/27/2006 | | PASS |
|
|
|
property was created by a Record of Survey (ROS02-00056).
|
Plan routing begun/NEW & ADDTN | | | 3/24/2006 | | |
|
|
|
|
Application received | | | 3/24/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/24/2006 | | |
|
|
|
|
Fee Review-notes | 3/24/2006 | 3/24/2006 | | | |
|
|
|
|