Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/13/2006 | 12/27/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/13/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11292 issued 11-13-06 to Micron Technology.
|
BLD-Final | 10/3/2006 | 10/10/2006 | 10/10/2006 | A | PASS |
Jim Storey
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Permanent Occupancy | | 10/10/2006 | 10/10/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/4/2006 | 10/9/2006 | 10/9/2006 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
FIRE-Final Inspection | 10/3/2006 | 10/4/2006 | 10/4/2006 | P | FAIL |
Troy Cobbley
|
|
|
Need fire alarm permit finaled and one emergency light provided that was not installled as per the plans and one existing exit sign has a burnt out buld. These items are marked on the city approved plans.
|
FIRE-Final Inspection | 9/29/2006 | 10/3/2006 | 10/3/2006 | A | DEFR |
Forrest France
|
|
|
rob Note: life safety; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection rescheduled per contractor
|
BLD-Final | 9/29/2006 | 10/4/2006 | 10/3/2006 | A | DEFR |
Jim Storey
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 9/29/2006 | 10/3/2006 | 10/3/2006 | A | DEFR |
Forrest France
|
|
|
Duplicate inspection request already called in.
|
FIRE-Final Inspection | 9/29/2006 | 9/29/2006 | 9/29/2006 | P | CANC |
Forrest France
|
|
|
Not ready per conversation with contractor, inspection mistakenly scheduled.
|
BLD-Other | 9/27/2006 | 9/29/2006 | 9/29/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/27/2006 at 12:24:38 PM. Contact: ###-####.
|
BLD-Other | 9/27/2006 | 9/28/2006 | 9/28/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/27/2006 at 12:24:03 PM. Contact: ###-####.
|
BLD-Other | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | PASS |
Jim Storey
|
|
|
ceiling grid; Phone #: ###-#### Internet Inspection Request from: Rob Puckett
|
BLD-Framing/Rough-in | 8/22/2006 | 8/22/2006 | 8/23/2006 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rob Puckett pending ele
|
BLD-Other | 8/8/2006 | 8/10/2006 | 8/10/2006 | A | PART |
Jim Storey
|
|
|
ceiling grid; Phone #: ###-#### Internet Inspection Request from: Rob Puckett ok pending others before cover.
|
BLD-Wall cover | 7/27/2006 | 8/1/2006 | 8/1/2006 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rob Puckett
|
BLD-Foundation | 7/6/2006 | 7/10/2006 | 7/10/2006 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2006 at 10:58:07 AM. Contact: ###-####.pwsi
|
BLD-Foundation | 7/6/2006 | 7/7/2006 | 7/7/2006 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2006 at 10:57:35 AM. Contact: ###-####.si reports corections achived and on track.
|
BLD-Energy code compliance | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2006 at 10:57:35 AM. Contact: ###-####.
|
BLD-Footing | 7/6/2006 | 7/6/2006 | 7/6/2006 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2006 at 10:56:56 AM. Contact: ###-####.cmu grout placment placed with si pending reports.
|
BLD-Footing | 6/21/2006 | 6/23/2006 | 6/23/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/21/2006 at 10:42:05 AM. Contact: ###-####.
|
BLD-Footing | 6/21/2006 | 6/21/2006 | 6/21/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/21/2006 at 10:41:37 AM. Contact: ###-####.
|
BLD-Footing | 6/15/2006 | 6/19/2006 | 6/19/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/15/2006 at 3:20:37 PM. Contact: ###-####. placed w/si
|
BLD-Footing | 6/6/2006 | 6/9/2006 | 6/9/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/6/2006 at 12:26:01 PM. Contact: ###-####.
|
BLD-Footing | 6/6/2006 | 6/8/2006 | 6/8/2006 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/6/2006 at 12:25:29 PM. Contact: ###-####.wip
|
BLD-Footing | 6/6/2006 | 6/7/2006 | 6/7/2006 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/6/2006 at 12:24:48 PM. Contact: ###-####.
|
Telephone call | | | 5/31/2006 | | DONE |
|
|
|
called ###-#### and told Paul Marcolina that permit is ready and need GC
|
Permit Ready to Issue | | | 5/31/2006 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 5/31/2006 | | |
|
|
|
|
(F) Reprint permit | | | 5/31/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/29/2006 | 3/29/2006 | 5/30/2006 | | PASS |
|
|
|
5/30/2006 10:50:49 JCM - activity updated through activity BLDA022 from case BLD06-00830.
|
Routing - PLAN CHECK | 4/10/2006 | | 5/30/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/30/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/25/2006 | | |
|
|
|
Received 1 copy of cover transmittal letter, 1 copy of 2 page Plan corrections letter, 1 copy of partition bracing detail,m 1 copy of suspended ceiling detail, 1 copy of suspended seismic provisions, 3 copies of A8.1, 3 copies of A9.1.1 and taken to John Menard
|
Routing - FIRE | 4/3/2006 | | 4/10/2006 | | PASS |
|
|
|
Inserted reveiw comments into plans. Faxed review comments to architect.
|
1st review completed | | | 4/10/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - PLUMBING | 4/1/2006 | | 4/3/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Plan resubmittals requested | | | 4/1/2006 | | DONE |
|
|
|
E-mailed the architect with a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 3/31/2006 | | 4/1/2006 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 3/30/2006 | | 3/31/2006 | | PASS |
|
|
|
|
Application received | | | 3/29/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/29/2006 | | |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | | | |
|
|
|
Second Notice has not been responded to.
|