Second Notice BLD | 9/25/2006 | 9/25/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/1/2006 | 8/1/2006 | 9/25/2006 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 7/27/2006 | 8/1/2006 | 8/1/2006 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rob Puckett
|
DOC - Permit Finaled | 8/1/2006 | 8/1/2006 | 8/1/2006 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/18/2006 | 7/20/2006 | 7/20/2006 | A | PASS |
Forrest France
|
|
|
Noted items from previous confrence needing correction including door hardware at two double doors has been completed, inspection passed.
|
Plan resubmittals received | | | 5/18/2006 | | PASS |
|
|
|
5/17/06- Fire received email of Haz Mat Code Analysis from Bobbie Smith MTI, dated 5/16/06. Analysis accepted; project passed by Fire. Will sign off plans at next site visit.
6/14/2006 - Plans signed off at Micron site visit.
|
Plan assigned to (JCM) | 4/21/2006 | | 5/17/2006 | | PASS |
|
|
|
5/17/2006 13:41:17 JCM - activity updated through activity BLDA022 from case BLD06-00835.
|
Plan Reviewer's activity | | | 5/17/2006 | | PASS |
|
|
|
This permit is being issued prior to receiving the required chemical quantities to verify limits within control areas. The issue status is only to allow trades to pull necessary permits. Full approval after verification of chemical quantities. JCM
|
Routing - PLAN CHECK | 4/27/2006 | | 5/17/2006 | | PASS |
|
|
|
This permit is being issued prior to receiving the required chemical quantities to verify limits within control areas. The issue status is only to allow trades to pull necessary permits. Full approval after verification of chemical quantities. JCM
|
Issue & PRINT to be Invoiced | | | 5/17/2006 | | DONE |
|
|
|
Paul has Haz mat information he is sending to Sam. Ok to issue per Rita and John M.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2006 | | DONE |
|
|
|
|
Routing - FIRE | 4/21/2006 | | 4/21/2006 | | FAIL |
|
|
|
Not reviewed; need Haz Mat information to be provided.
|
Plan Reviewer's activity | | | 4/21/2006 | | FAIL |
|
|
|
Plan can be approved after confirmation of the chemical quantities within the control area. JCM
|
1st review completed | | | 4/21/2006 | | FAIL |
John Menard
|
|
|
|
Application received | | | 3/30/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | | | |
|
|
|
Second Notice has not been responded to.
|
Plan assigned from Web | 3/30/2006 | 4/9/2006 | | | |
|
|
|
|