Permit EXPIRED | | | 11/27/2007 | | DONE |
|
|
|
Per Mike J permit expired and needs to resubmit plans
|
BLD-Conference | 10/8/2007 | 10/8/2007 | 10/11/2007 | A | CANC |
Mike Jordan
|
|
|
per mike jordan
|
DOC - Permit Expired | 10/11/2007 | 10/11/2007 | 10/11/2007 | P | DONE |
Mike Jordan
|
|
|
per mike jordan. Noted no work has been done on this permit. Attempted to contact Mr. Blazer several times and left messages on cell phone. No return calls. Permit has expired. Will have to resubmit plans.
|
(F) Reprint permit | | | 10/8/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/26/2006 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 4/17/2006 | 4/17/2006 | 4/21/2006 | | PASS |
|
|
|
4/21/2006 11:54:13 SRZ - activity updated through activity BLDA022 from case BLD06-00838.
|
Routing - PLAN CHECK | 4/6/2006 | | 4/21/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 4/21/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/21/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/21/2006 | | DONE |
|
|
|
left mess that permit is ready
|
Permit Ready to Issue | | | 4/21/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 3/30/2006 | 3/30/2006 | 4/17/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 4/17/2006 | | PASS |
|
|
|
Plan Review Pending Truss Engineering, Roof Framing Plan and 2nd Floor Framing Plan. (SRZ)
|
Routing - PUBLIC WORKS | 4/6/2006 | | 4/6/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 3/30/2006 | | 4/3/2006 | | PASS |
|
|
|
Pepperwood Estates # 8 requires 5 ft. per story side yard setbacks. Site plan shows 5 ft. setback on west-side side yard at garage location. This is a two story building and setback must be 10 ft. Contacted Brian Blaser 4/3/2006. Revised site plans submitted 4/5/2006. New site plan approved. TAC
|
Application received | | | 3/30/2006 | | PASS |
|
|
|
|