Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/4/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/21/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 7/21/2006 | | DONE |
|
|
|
Perm. Occ. Cerr. # 11143 issued 7-21-06 to Pearle Vision.
|
BLD-Final | 7/19/2006 | 7/20/2006 | 7/20/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/19/2006 at 11:34:42 AM. Contact: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety passed.
|
FIRE-Alarm Testing | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | PASS |
Troy Cobbley
|
|
|
Alarm testing passed.
|
Permanent Occupancy | | 7/20/2006 | 7/20/2006 | | DONE |
|
|
|
|
BLD-Other | 7/10/2006 | 7/11/2006 | 7/11/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2006 at 12:19:33 PM. Contact: ###-####. ceiling grid ok.
|
BLD-Framing/Rough-in | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/24/2006 at 7:41:31 AM. Contact: ###-####. interior stud walls.
|
BLD-Framing/Rough-in | 5/22/2006 | 5/23/2006 | 5/23/2006 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/22/2006 at 3:33:49 PM. Contact: ###-####. Approved plans not on site.
|
Issue PAID IN FULL permit | | | 5/8/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 4/17/2006 | | 4/21/2006 | | PASS |
|
|
|
Inserted new plans. No further submittals required.
|
Received Certificate of Value | | | 4/21/2006 | | DONE |
|
|
|
Received new certificate of value from Russell Corporation adding in restrooms and new electrical panels to scope of work.
|
Telephone call | | | 4/21/2006 | | DONE |
|
|
|
Called Russell corp. to see if a new Certificate of Value was available. Mike said he would fax me a new one.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2006 | | PASS |
|
|
|
To permit desk.
|
Print Occupancy Form | | | 4/21/2006 | | DONE |
|
|
|
|
Telephone call | | | 4/21/2006 | | DONE |
|
|
|
lft vm with johnathan steeel ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 4/21/2006 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 4/6/2006 | | 4/21/2006 | | PASS |
|
|
|
4/21/2006 13:16:20 DRS - activity updated through activity BLDA022 from case BLD06-00889.
|
Plan resubmittals received | | | 4/20/2006 | | DONE |
|
|
|
Received 1 copy of cover transmittal letter, 1 copy of response letter to plan review, 2 copies of 2003 Lighting complainace, 1 copy of sheet 1 of 1(Cabinet cut sheet), 1 copy of sheet 1 of 3 (Cabinet cut sheet), 1 copy of sheet 2 of 3 (Cabinet cut sheet), 1 copy of sheet of 3 of 3 (Cabinet cut sheet), 2 copies of the following- M-1, E-2, EC-1, A-1, A-3, A-4.1, A-5, F-1 and taken to Dan Stuart
|
1st review completed | | | 4/17/2006 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - FIRE | 4/13/2006 | | 4/17/2006 | | PASS |
|
|
|
Attached review comments to plans. Faxed review comments to architect.
|
Plan resubmittals requested | | | 4/13/2006 | | DONE |
|
|
|
Faxed and e-mailed copy of plan review conditions to architect for his response. Routing plans to fire code analyst for review.
|
Routing - PLAN CHECK | 4/6/2006 | | 4/12/2006 | | FAIL |
|
|
|
E-mailed and faxed copy of plan review conditions needing addresed by architect to architect.
|
Routing - PUBLIC WORKS | 4/6/2006 | | 4/6/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 4/3/2006 | | 4/4/2006 | | DONE |
|
|
|
4/4/2006 15:13:42 B_S - activity updated through activity BLDA165 from case BLD06-00889.
|
Plans ACCEPTED BY PLAN TECH | | | 4/4/2006 | | |
|
|
|
|
Application received | | | 4/3/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/3/2006 | | DONE |
|
|
|
|
Fee Review-notes | 4/3/2006 | 4/3/2006 | | | |
|
|
|
|