PubWorks Occupancy Approval | 4/20/2009 | 4/20/2009 | 4/20/2009 | | DONE |
Terry Records
|
|
|
|
Permanent Occupancy | | | 1/9/2009 | | DONE |
|
|
|
|
Zoning Approval | 1/7/2009 | 1/7/2009 | 1/7/2009 | | PASS |
Susan Riggs
|
|
|
|
BLD-Final | 7/26/2007 | 7/27/2007 | 7/27/2007 | A | PASS |
Tom Arcoraci
|
|
|
KENNY Phone #: ###-####
|
Temporary Occupancy | 7/27/2007 | 10/25/2007 | 7/27/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/26/2007 | 7/26/2007 | 7/26/2007 | P | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
BLD-Energy code compliance | 6/1/2007 | 6/1/2007 | 6/1/2007 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 5/30/2007 | 5/31/2007 | 5/31/2007 | A | FAIL |
Mike Jordan
|
|
|
kenny; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 5/29/2007 | 5/30/2007 | 5/30/2007 | A | PASS |
Mike Jordan
|
|
|
kenny ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Other | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PASS |
Mike Jordan
|
|
|
Kenny shearing; Phone #: ###-#### Internet Inspection Request from: Andrea Whiteman
|
BLD-Foundation | 2/21/2007 | 2/21/2007 | 2/21/2007 | P | PASS |
Mike Jordan
|
|
|
ian - wall ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 2/16/2007 | 2/16/2007 | 2/16/2007 | P | PASS |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Footing | 2/15/2007 | 2/15/2007 | 2/15/2007 | P | CANC |
Mike Jordan
|
|
|
MATT; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Canc by contractor via phone call.
|
Issue PAID IN FULL permit | | | 2/9/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/6/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/4/2006 | | 12/5/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2006 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/5/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/5/2006 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/19/2006 | | 12/5/2006 | | PASS |
|
|
|
12/5/2006 16:00:18 M_P - activity updated through activity BLDA022 from case BLD06-00917.
|
Routing - PLUMBING | 4/26/2006 | | 12/5/2006 | | PASS |
|
|
|
|
Routing - FIRE | 11/29/2006 | | 12/4/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 11/14/2006 | | 11/29/2006 | | |
|
|
|
Routing to Fire.
|
Routing - PLANNING Land Div | 11/13/2006 | | 11/14/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/14/2006 | | 11/13/2006 | | |
|
|
|
Routing to Land Division.
|
Routing - PLANNING | 7/24/2006 | | 8/14/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/5/2006 | | 7/24/2006 | | |
|
|
|
Routing to Planning.
|
Routing - PLAN CHECK | 6/26/2006 | | 7/5/2006 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
1st review completed | | | 6/26/2006 | | FAIL |
|
|
|
Failed planning and fire.
|
Routing - FIRE | 6/21/2006 | | 6/26/2006 | | FAIL |
|
|
|
Lacking fire flow documentation.
|
Routing - PLAN CHECK | 5/16/2006 | | 6/21/2006 | | PEND |
|
|
|
Waiting for others to approve buildings 1,2,3,4,7,9,10,11,12,14,15,16 of block 2. Buildings 1,2,3,4,7,10,11,12,13 of block 3. Buildings 1,2,3,4, of block 4. Buildings 8,9,10,12,13,14,15,17,19 of block 5.
And plan review approval of buildings 5,8,13 of block 2. Buildings 6,8,9 of block 3. Buildings 11,16,19 of block 5.
|
Plan resubmittals received | | | 6/9/2006 | | |
|
|
|
Received 2 copys of sheet L1.00 taken to Mike P.
|
Routing - PLANNING | | | 5/15/2006 | | FAIL |
|
|
|
DRH05-00319- Sarah S CUP05-00009- Susan R
|
Routing - Erosion and Sediment | 4/26/2006 | | 4/26/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/21/2006 | | 4/26/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 4/19/2006 | | 4/21/2006 | | FAIL |
|
|
|
sub not recorded
|
Plans ACCEPTED BY PLAN TECH | | | 4/19/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/19/2006 | | |
|
|
|
|
Application received | | | 4/4/2006 | | |
|
|
|
|