Third Notice BLD | 12/11/2007 | 12/11/2007 | 12/27/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 4/7/2006 | 4/7/2006 | 12/27/2007 | | DONE |
|
|
|
|
Second Notice BLD | 11/13/2007 | 11/13/2007 | 12/11/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/30/2007 | 11/13/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/30/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | 9/28/2007 | 9/28/2007 | 9/28/2007 | P | PASS |
Dena Gambrel
|
|
|
|
BLD-Aging Inspection | 8/21/2007 | 8/21/2007 | 8/21/2007 | | DONE |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 5/8/2007 | 5/8/2007 | 5/8/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 2/6/2007 | 2/6/2007 | 2/9/2007 | P | DEFR |
Jim Storey
|
|
|
per tom done
|
BLD-Final | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
Code Occupancy Approval Temp | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | PASS |
Dena Gambrel
|
|
|
2-6-07 Temp. Occupancy Signed.
|
FIRE-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Wall cover | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | PASS |
Tom Arcoraci
|
|
|
chuck; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 12/14/2006 | 12/14/2006 | 12/14/2006 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 12/13/2006 | 12/14/2006 | 12/14/2006 | A | NR |
Tom Arcoraci
|
|
|
Chuck; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett
|
BLD-Foundation | 9/12/2006 | 9/13/2006 | 9/13/2006 | A | PASS |
Tom Arcoraci
|
|
|
jared; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | PASS |
Tom Arcoraci
|
|
|
jerod; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Issue PAID IN FULL permit | | | 9/6/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/5/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 8/14/2006 | | 9/1/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/2006 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/12/2006 | | 9/1/2006 | | PASS |
|
|
|
9/1/2006 14:04:28 M_P - activity updated through activity BLDA022 from case BLD06-00995.
|
Routing - PLAN CHECK | 7/25/2006 | | 8/14/2006 | | FAIL |
|
|
|
2nd review failed, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 7/28/2006 | | |
|
|
|
Received 1 pg response and 2 copies of the follwing pages: G, A1, A3, A4, A5, A6, M-1, M-2; taken to Mike Phillips
|
Routing Off Site - STRUCTURAL | 7/18/2006 | | 7/26/2006 | | FAIL |
|
|
|
Second review failed. Followup review will be finished by plan reviewer.
Called Action Couriers for pick up
|
Routing - PLAN CHECK | 6/16/2006 | | 7/25/2006 | | FAIL |
|
|
|
Called and left message for architect. Need to review assumed property line issues.
|
Plan resubmittals received | | | 6/26/2006 | | |
|
|
|
received (10) pages from performance engineers, (3) sets of each structural calculations for roosevelt st. homes bld type A, B, & C -plans taken to mike phillips for review
|
Routing - PLAN CHECK | 5/19/2006 | | 6/16/2006 | | FAIL |
|
|
|
Need copy of responce letter from structural engineer, prior to sending plans to outside engineering firm for follow-up review. Left message for James Gipson to call me.
|
Plan resubmittals received | | | 6/9/2006 | | |
|
|
|
Received 1 copy of plan review response to BLD06-00993, BLD06-00994, BLD06-00995, BLD06-00996, 1 copy of plan review report from Kartchner Engineering, 1 copy of plan review response from B & A Engineers, 1 page from Key Beam, 3 copy of the following sheets- G, C-1, C-2, C-3, C-4, C-5, C-6, C-7, C-8, A1, A2, A3, A3.1, A4, A5, A6, A7, A8, A9, A10, SO OF 9, S1 OF 9, S2 OF 9, S3 OF 9, S4 OF 9, S5 OF 9, S6 OF 9, S7 OF 9, S8 OF 9, M-1, M-2, M-3, P-1, P-2, P-3, MP-1, E-1, E-2, SE-1and taken to Mike Phillips
|
Routing - PLANNING | 6/7/2006 | | 6/7/2006 | | PASS |
|
|
|
PASS - per Hal Simmons see memo in file
|
1st review completed | | | 5/19/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - FIRE | 5/18/2006 | | 5/19/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | | | 5/18/2006 | | FAIL |
|
|
|
Plan review completed, sent correction report to the architect requesting additional informaiton be submitted for further review prior to issuing permit.
|
Case Summary (BLD) | | | 5/18/2006 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/12/2006 | | 4/28/2006 | | FAIL |
|
|
|
Called Action Courier for pick up @ 2:09 to AHJ///4/12/06 BAS
|
Routing - PLANNING | 4/21/2006 | | 4/21/2006 | | FAIL |
|
|
|
Per CUP conditions of approval 3 (elevations), 4 (Shifitng strucutres A and B to obrserve required setbacks), and 5 (indicating floor plan details within common room). Spoke with Chuck (Developer)
|
Routing - PLANNING | 4/20/2006 | | 4/21/2006 | | FAIL |
|
|
|
DRH05-00388 - Pass - Andrea Tuning for DR
CUP05-00132 Angela W.
|
Routing - PLUMBING | 4/19/2006 | | 4/20/2006 | | PASS |
|
|
|
PER PLANS AND 2003 UPC
|
Routing - Erosion and Sediment | 4/17/2006 | | 4/18/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 4/13/2006 | | 4/17/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 4/12/2006 | | 4/13/2006 | | PASS |
|
|
|
Property has been combined under one parcel number.
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/12/2006 | | |
|
|
|
|
Application received | | | 4/7/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/7/2006 | | |
|
|
|
|