Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00996
StatusFinaled
Name ROOSEVELT STREET HOMES
Site Address 305 S ROOSEVELT ST
Project NameSenior Housing Office/Laundry
Customer Number 
ePlanReviewNo
Description
Office / Laundry Building - To construct a new 660 square feet, single story, office area with laundry facilities and restrooms for the associated apartment buildings. NOTE: Buildings "A, B and the office building are being constructed per Section 704.3, EXCEPTION, the aggregate area of the buildings are within the allowable area of one buildings. All construction shall be per the approved plans and attached comment list. MJP CUP 05-00132 DRH 05-00388
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/11/200712/11/200712/27/2007 DONE
Second Notice has not been responded to.
Fee Review-notes4/7/20064/7/200612/27/2007 DONE
Second Notice BLD11/13/200711/13/200712/11/2007 DONE
First Notice has not been responded to.
First Notice 10/30/200711/13/2007 DONE
Permanent Occupancy  10/30/2007 DONE
FIRE-Final Inspection10/22/200710/23/200710/23/2007APASS
DetailsTroy Cobbley
Life safety passed
Code Occupancy Approval9/28/20079/28/20079/28/2007PPASS
DetailsDena Gambrel
BLD-Aging Inspection8/21/20078/21/20078/21/2007 DONE
DetailsTom Arcoraci
BLD-Aging Inspection5/11/20075/11/20075/11/2007 PASS
DetailsTom Arcoraci
ok or final
BLD-Final2/5/20072/6/20072/6/2007PPASS
DetailsTom Arcoraci
chuck; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Code Occupancy Approval Temp2/6/20072/6/20072/6/2007PPASS
DetailsDena Gambrel
2-6-07 Temp. Occupancy Signed.
FIRE-Final Inspection2/5/20072/6/20072/6/2007APART
DetailsTroy Cobbley
Temp only. Life safety will be ok to final when fire alarm permit for building B is complete.
BLD-Aging Inspection1/23/20071/23/20071/23/2007 PASS
DetailsTom Arcoraci
BLD-Wall cover11/16/200611/17/200611/17/2006APASS
DetailsTom Arcoraci
chuck ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in11/14/200611/15/200611/15/2006APASS
DetailsTom Arcoraci
chuck ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Footing9/19/20069/20/20069/20/2006APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 9/19/2006 at 12:58:35 PM. Contact: ###-####.
BLD-Footing9/18/20069/19/20069/19/2006PPART
DetailsTom Arcoraci
chuck; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
(F) Reprint permit  9/7/2006  
Issue PAID IN FULL permit  9/6/2006 DONE
Print Occupancy Form  9/5/2006  
Routing - PLAN CHECK8/14/2006 9/1/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/1/2006 DONE
Plan assigned to (M_P)4/12/2006 9/1/2006 PASS
9/1/2006 14:06:03 M_P - activity updated through activity BLDA022 from case BLD06-00996.
Routing - PLAN CHECK7/25/2006 8/14/2006 FAIL
Second review failed, sent correction report to architect requesting additional information to be submitted for further review prior to issuing permit.
Plan resubmittals received  7/28/2006  
Received 1 pg response and 2 copies of the follwing pages: G, A1, A3, A4, A5, A6, M-1, M-2; taken to Mike Phillips
Routing Off Site - STRUCTURAL7/18/2006 7/26/2006 FAIL
Second review failed. Followup review will be finished by plan reviewer.
Called Action Couriers for pick up
Routing - PLAN CHECK5/19/2006 7/25/2006 FAIL
Called and left message for architect. Need to review assumed property line issues.
Plan resubmittals received  6/26/2006  
received (10) pages from performance engineers, (3) sets of each structural calculations for roosevelt st. homes bld type A, B, & C -plans taken to mike phillips for review
Plan resubmittals received  6/9/2006  
Received 1 copy of plan review response to BLD06-00993, BLD06-00994, BLD06-00995, BLD06-00996, 1 copy of plan review report from Kartchner Engineering, 1 copy of plan review response from B & A Engineers, 1 page from Key Beam, 3 copy of the following sheets- G, C-1, C-2, C-3, C-4, C-5, C-6, C-7, C-8, A1, A2, A3, A3.1, A4, A5, A6, A7, A8, A9, A10, SO OF 9, S1 OF 9, S2 OF 9, S3 OF 9, S4 OF 9, S5 OF 9, S6 OF 9, S7 OF 9, S8 OF 9, M-1, M-2, M-3, P-1, P-2, P-3, MP-1, E-1, E-2, SE-1and taken to Mike Phillips
Routing - PLANNING6/7/2006 6/7/2006 PASS
PASS - per Hal Simmons-- see memo in file.
Routing - FIRE5/18/2006 5/19/2006 PASS
Attached review comments to plans.
1st review completed  5/19/2006 FAIL
Failed Plan Check.
Routing - PLAN CHECK4/21/2006 5/18/2006 FAIL
Routing Off Site - STRUCTURAL4/12/2006 4/28/2006 FAIL
Called Action Courier for pick up @ 2:09 to AHJ///4/12/06 BAS
Routing - PLANNING4/21/2006 4/21/2006 FAIL
Per CUP conditions of approval 3 (elevations), 4 (Shifitng strucutres A and B to obrserve required setbacks), and 5 (indicating floor plan details within common room). Spoke with Chuck (Developer)
Routing - PLANNING4/20/2006 4/21/2006 FAIL
DRH05-00388 - Pass - Andrea Tuning for DR
CUP05-00132 Angela W.
Routing - PLUMBING4/19/2006 4/20/2006 PASS
PER PLANS AND 2003 UPC
Routing - Erosion and Sediment4/17/2006 4/19/2006 PASS
ESC plan approved with attached conditions. Refer to ESC06-00605 as master ESC plan for project.
Routing - PUBLIC WORKS4/13/2006 4/17/2006 PASS
Routing - PLANNING Land Div4/12/2006 4/13/2006 PASS
Property has been combined under one parcel number.
Plans ACCEPTED BY PLAN TECH  4/12/2006 DONE
Plan routing begun/NEW & ADDTN  4/12/2006  
Application received  4/7/2006  
Recd Pcfee & Taken To Pln CK  4/7/2006