Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-01069
StatusFinaled
Name BONAVENTURE LLC
Site Address 5850 N FIVE MILE RD
Project NameBONAVENTURE PLACE
Customer Number 
ePlanReviewNo
Description
(Bonaventure Place Retirement Community) This building is fully sprinklered for allowable area increase & compliance with occupancy use group. To construct a 1-hour fire-resistive, three story, 69 unit (26 units > 800 sq. ft.), multi family residential facility, separated from adjacent 'A2' Dining/common use area by a 2-hour fire wall to allow review of this portion as a stand alone structure for area & construction type. All fire-resistive assemblies to be as called out on plans. DRH05-00320 CUP05-00028 drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD10/17/200710/17/200710/30/2007 DONE
First Notice has not been responded to.
First Notice 10/3/200710/17/2007 DONE
FIRE-Final Inspection10/2/200710/2/200710/3/2007PPASS
DetailsTroy Cobbley
Life safety passed
Permanent Occupancy  10/3/2007 DONE
BLD-Final10/2/200710/2/200710/2/2007PPASS
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK for Perm Occ.
BLD-Conference9/7/20079/10/20079/10/2007ADONE
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Walk thru.....1st Floor.......
BLD-Conference9/6/20079/7/20079/7/2007PDONE
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Dale
Walk thru 2nd floor ....all bldgs.
FIRE-Conference9/7/20079/7/20079/7/2007PCANC
DetailsTroy Cobbley
Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Code Occupancy Approval9/7/20079/7/20079/7/2007APASS
DetailsCarol Montgomery
Meets compliance with DRH05-00320/CUP05-00028 - PASS.
BLD-Conference9/7/20079/7/20079/7/2007ACANC
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Conference9/5/20079/6/20079/6/2007ADONE
DetailsJim Sly
Consulation with Troy - I will call you when he shows up or you can coordinate with him directly. Thanks, Katy Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Code Occupancy Approval Temp9/5/20079/5/20079/5/2007AFAIL
DetailsCarol Montgomery
Made inspection of site on 9-4-2007. Still have a small amount of hydroseeding to do and the remainder of the landscaping (incl. undergrd. sprinkle system) at the sw corner of the project. There is a $9,400.00 Bond in place so I am signing off on temporary(s)
BLD-Final8/31/20079/4/20079/4/2007PNR
DetailsJim Sly
Final for C wing. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Conference8/31/20079/4/20078/31/2007PCANC
DetailsJim Sly
Final in C wing! Phone #: ###-#### Internet Inspection Request from: Dale Shuart Inspection cancelled from web by: Dale Shuart
BLD-Conference8/29/20078/29/20078/29/2007PDONE
DetailsJim Sly
Final inspection questions - we can do this over the phone if that''s better for your schedule. Thanks, Katy. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Conference8/24/20078/27/20078/27/2007APASS
DetailsJim Sly
Please inspect final attic insulation in C-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Other6/13/20076/14/20076/14/2007APASS
DetailsJim Sly
Please inspect T-bar ceiling grid on 2nd floor of C-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Conference6/11/20076/11/20076/11/2007PPART
DetailsJim Sly
Please inspect T-bar ceiling grid on all 3 floors of C-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
1st floor only....OK
BLD-Other6/5/20076/6/20076/6/2007ANR
DetailsJim Sly
Please inspect T-bar ceiling grid on all 3 floors of C-wing. Thanks. Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Need to complete firestopping.
BLD-Conference3/30/20074/2/20074/2/2007ADONE
DetailsJim Sly
Please meet Superintendent for overall job consultation. Phone #: ###-####
BLD-Wall cover3/12/20073/12/20073/12/2007PPASS
DetailsJim Sly
Please inspect sheetrock nailing in completed units on 3rd floor of C-wing. Thanks. Phone #: ###-####
OK
BLD-Wall cover3/8/20073/9/20073/9/2007APASS
DetailsJim Sly
Please inspect sheetrock nailing in completed units on 3rd floor of C-wing. Thanks Phone #: ###-####
BLD-Energy code compliance3/1/20073/2/20073/2/2007PPASS
DetailsJim Sly
Please inspect C-wing 3rd floor 1st layer sheetrock nailing - AM if possible. Thanks! Phone #: ###-####
BLD-Wall cover2/27/20072/27/20072/27/2007PPASS
DetailsJim Sly
Please inspect sheetrock nailing in C-wing (see John Coe). Thanks. Phone #: ###-####
BLD-Energy code compliance2/27/20072/27/20072/27/2007PPASS
DetailsJim Sly
Please inspect 3rd floor insulation of C-wing. Thanks. Phone #: ###-####
BLD-Energy code compliance2/21/20072/22/20072/22/2007APASS
DetailsJim Sly
Please inspect C-wing insulation. Thanks. Phone #: ###-####
BLD-Energy code compliance2/19/20072/20/20072/20/2007APASS
DetailsJim Sly
Please inspect C-wing 2nd floor insulation. AM or PM is fine. Thanks! Phone #: ###-####
BLD-Energy code compliance2/14/20072/15/20072/15/2007PPASS
DetailsJim Sly
Please inspect C-wing insulation. Thanks. Phone #: ###-####
BLD-Framing/Rough-in2/14/20072/15/20072/15/2007PPASS
DetailsJim Sly
Please inspect C-wing framing. Thanks. Phone #: ###-####
BLD-Energy code compliance2/12/20072/13/20072/13/2007APART
DetailsJim Sly
joe - - early am ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
1st floor OK
BLD-Framing/Rough-in2/8/20072/9/20072/9/2007PPART
DetailsJim Sly
Please inspect C-wing trusses. Thanks! Phone #: ###-####
BLD-Energy code compliance2/7/20072/9/20072/9/2007PPART
DetailsJim Sly
Please inspect C-wing insulation. Thanks. Phone #: ###-####
BLD-Framing/Rough-in2/7/20072/8/20072/8/2007PFAIL
DetailsJim Sly
Please inspect C-wing trusses. Thanks Phone #: ###-####
C/N on site
BLD-Framing/Rough-in2/5/20072/7/20072/7/2007PPART
DetailsJim Sly
Please inspect C-wing framing. Phone #: ###-####
3rd Floor
BLD-Framing/Rough-in2/5/20072/6/20072/6/2007PPART
DetailsJim Sly
Please inspect C-wing framing. Thanks. Phone #: ###-####
BLD-Framing/Rough-in2/2/20072/5/20072/5/2007PPART
DetailsJim Sly
Please inspect C-wing framing in PM. Phone #: ###-####
BLD-Framing/Rough-in2/2/20072/5/20072/5/2007APART
DetailsJim Sly
Please inspect C-wing framing in AM. Phone #: ###-####
BLD-Framing/Rough-in2/2/20072/2/20072/2/2007PPART
DetailsJim Sly
Please inspect framing in C-wing. Phone #: ###-####
BLD-Framing/Rough-in2/1/20072/1/20072/1/2007PPART
DetailsJim Sly
Please inspect framing in C-wing. Phone #: ###-####
BLD-Framing/Rough-in1/31/20071/31/20072/1/2007PNR
DetailsJim Sly
Framing C-wing Phone #: ###-####
BLD-Framing/Rough-in1/30/20071/31/20071/31/2007ANR
DetailsJim Sly
Please inspect structural framing, 1st floor of C-wing. Thanks! Phone #: ###-####
Plan resubmittals received  1/26/2007  
ok to log in as resubmittals per Dan Stuart; Received pg 1 of 1 Roof Truss Layout and 2 truss drawing packages from Idaho Truss; taken to Dan Stuart
BLD-Framing/Rough-in1/23/20071/23/20071/23/2007PPART
DetailsJim Sly
Please inspect C-wing elevator framing (also requested A-wing elevator inspection as well). Thanks. Phone #: ###-####
Additional plans submitted  12/1/2006 DONE
Received two copies of floor framing plans (deferred submittal, from Architect for project. Sheet 2 of 9 & 5 of 9. Plans were prepared and stamped by and Idaho licensed engineer, Aaron M Reed. Plans have been reviewed and approved by Project structural engineer, Matthew Gralund. Copy in original plans and copy to job site.
BLD-Framing/Rough-in11/30/200611/30/200611/30/2006APART
DetailsJim Sly
Please inspect roof nailing this morning. ; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Areas that I could inspect were OK.....(icy)
BLD-Framing/Rough-in11/27/200611/27/200611/27/2006PPART
DetailsJim Sly
Please inspect C-wing roof nails. Anytime today is fine. Thanks!; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Partial insp......Icy.
BLD-Framing/Rough-in11/15/200611/15/200611/15/2006PPART
DetailsJim Sly
Please inspect structural framing of C-wing between 1:00 and 2:00 if possible. See Joe Lamke when here; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Energy code compliance10/20/200610/20/200610/20/2006PPASS
DetailsTom Arcoraci
Please inspect shear walls for C-wing this afternoon. Thanks!; Phone #: ###-#### Internet Inspection Request from: Dale Shuart mti on site
Additional plans submitted  10/20/2006 PASS
Architect submitted new envelope compliance certificate changing the wall insulation R value from R21 to R19 which still shows compliance with energy code requirements. Copy given to inspector, Jim Sly.
BLD-Wall cover10/3/200610/3/200610/3/2006PDONE
DetailsJim Sly
Please inspect partial drywall on 1st floor of C-wing this afternoon. Thanks!; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in10/2/200610/2/200610/2/2006PPART
DetailsJim Sly
Please inspect 2nd floor corridor walls in C-wing this afternoon.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK
BLD-Framing/Rough-in9/20/20069/20/20069/20/2006PCANC
DetailsJim Sly
Please inspect parial framed hallway at C-wing.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Framing/Rough-in9/19/20069/20/20069/20/2006APART
DetailsJim Sly
Please inspect C-wing framed hallways in AM. Internet Inspection Request from: Dale Shuart
C wing halls OK to pre rock partial ceiling.
BLD-Footing8/14/20068/15/20068/14/2006PPART
DetailsJim Sly
Please inspect the interior footings underslab of the 2nd leg of the C-wing.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Footing8/10/20068/10/20068/10/2006APART
DetailsJim Sly
Please inspect patio post footings as soon as possible today. Dale will call this morning.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
Footings for columns at entrys OK pend appr's
BLD-Foundation8/4/20068/7/20068/7/2006PPART
DetailsJim Sly
We need to inspect interior bearing footing rebar and the reabar "mat" for the slab. Late in the day would be good for us (3:30 or so ) if possable.; Phone #: ###-####
Rebar mat and thickened slab appears OK pending MTI special insp, tests and approvals.

Internet Inspection Request from: Dale Shuart
BLD-Foundation7/31/20068/1/20068/1/2006PPART
DetailsJim Sly
We would like the rebar in the raised stem walls of Elevator "C" Inspected shortly after lunch, if possible. (would like to pour around 3:00pm).; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
OK pending MTI special insp tests and appr
BLD-Foundation7/28/20067/31/20067/31/2006APASS
DetailsMike Jordan
Please inspect "C" wing elevator floor and sidewalls.; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
BLD-Footing7/24/20067/25/20067/25/2006APART
DetailsJim Sly
Please do a partial inspection on section "C"; Phone #: ###-#### Internet Inspection Request from: Dale Shuart
MTI special inspector on site.......Section C ... footing and found wall mono pour OK pending special insp, tests and approvals.
Permit Ready to Issue  7/20/2006 DONE
Telephone call  7/20/2006 DONE
Left voice message for Ben that permit is ready & fees///7/20/06 @ 11:25am BAS
Issue PAID IN FULL permit  7/20/2006 DONE
Routing - FIRE7/13/2006 7/18/2006 PASS
Attached review comments to plans
Routing - PLAN CHECK7/18/2006 7/18/2006 PASS
To permit desk to issue.
PLANS/APPL TAKEN TO FRONT DESK  7/18/2006 PASS
Print Occupancy Form  7/18/2006 DONE
Plan assigned to (DRS)3/10/2006 7/18/2006 PASS
7/18/2006 11:48:42 DRS - activity updated through activity BLDA022 from case BLD06-01069.
Routing - PLAN CHECK6/30/2006 7/13/2006 PEND
Inserted resubmitted plans & documents reveived on 7/12/06 into original plans. No further submittals required. Routing to fire code analyst for re-review.
Routing Off Site - STRUCTURAL7/12/2006 7/12/2006 PASS
Called Action Couriers for pick up. Received letter approving structural plan review for this permit, BLD06-01069 from Kieth Jones. Copy attached to plans.
Plan resubmittals received  7/12/2006 DONE
Received 2 structural calcs,2 united water plans,1 response, & 2 copys of sheets A1.1A,A2.1C,A2.2C,A2.3C,A3.2,S2.1C,S8.3,S8.5,M2.1,M2.18,M2.2B,M2.3B,M2.4B,M3.1,M3.2,M4.1,M4.2,M5.1,M5.2 taken to Dan S.
Meeting  7/11/2006 DONE
Met with Greg Elmore, Ben Settecase, Dale Shuart and contrtactor to review proposed resubmittals. Resubs accepted and taken to permit desk to be checked in and to route one set to outside structural engineering re-review.
Routing - PLANNING7/11/2006 7/11/2006 PASS
Planning approval for Building 'C' only, as specified on drawings.
Routing - FIRE6/29/2006 6/30/2006 FAIL
Faxed resubmittal items to architect. Attached review comments to plans.
Routing - PLAN CHECK6/22/2006 6/29/2006 FAIL
Resubmittals incomplete. Items remaining needing to be addressed were e-mailed and faxed to architect for response. Plans routed to fire code analyst for review.
Plan resubmittals requested  6/29/2006 DONE
faxed and e-mailed to Greg Elmore.
Routing - PUBLIC WORKS6/23/2006 6/23/2006 PASS
Plan resubmittals received  6/23/2006 DONE
Received 1 transmittal , & 2 copys of sheets C1,C2,L2.1,L2.3 taken to Dan S.
Routing - PLANNING6/16/2006 6/20/2006 FAIL
I called Ron Sargent and asked for a landscape plan, a site plan of the entire development so that I could see traffic circulation and for the required cross access agreement/parking . I'll pass plans on to Cody (design review) today 6/20/06.
Routing - PUBLIC WORKS6/15/2006 6/16/2006 FAIL
Eliminate disposer(s) in kitchen. 3100 gallon grease inteceptor/atypical volume/potentially to large; Need to show UPC sizing calculation; If volume prescription is correct, install two 1500 gallon interceptors; an interceptor this size will require odor control assessment. Contact Mike Hunter ###-####.
Routing - PLAN CHECK5/22/2006 6/15/2006 PEND
Received complete two new complete sets of plans, application and CV for the purpose of breaking this permit out to be a stand alone plans and permit. BLD06-00579 & 582 are still needing the architects response and will be resubmitted in the near future. Plans & copies of original review data were organized and then the plans were sent to PW to begin the routing process for the resubmittals.
Plan resubmittals received  6/15/2006  
Received 1 copy of new application, new cert of value, 3 page plan review response page letter, 2 copies of the following sheets-- A1.1, A1.2, A1.3, A2.1, A2.1C, A2.2, A2.2C, A2.3, A2.4, A3.1, A3.2, A4.1, A4.2, A4.3, A5.1, A6.1, A6.2, A6.3, A7.1, A8.1, A8.2, A8.3, A9.1, A9.2, S0.1, S1.1C, S2.1C, S2.2C, S2.3C, S2.4, S3.1, S5.1, S8.1, S8.2, S8.3, S8.4, S8.4, S8.5, M2.1B, M2.2B, M2.3B, M2.4B, M3.1, M3.2, M4.1, M4.2, M5.1, M5.2, P1.0, P1.3, P2.3, P3.3, P4.3, P6.1, P6.2, E2.1, E2.5, E2.9, E2.13, E3.1, E3.5, E3.9, E3.13, E4.1, E4.2, E4.3, E4.4, E4.5, E6.1, E6.2, E6.3, E6.5, E6.5, E6.6, E6.7 and taken to Dan Sturat
Plan resubmittals received  6/15/2006 DONE
Received new plans for routing to all agencies that had reviewed and failed the first time around. The owner & architect broke this set of plans and corrections out to go through as separate plans.
1st review completed  5/22/2006 FAIL
Failed Plan check and Fire.
Routing - FIRE5/11/2006 5/22/2006 FAIL
Attached review comments to plans. Faxed resubmittal items to architect.
Routing - PLAN CHECK4/12/2006 5/11/2006 FAIL
Copy of review conditions e-mailed and faxed to Greg Elmore, architect. Routing to fire code analyst.
Plan resubmittals requested  5/11/2006 DONE
By e-mail & fax, copy of plan review report of items needing to be corrected or clarified on plans & specs.
Routing - PLANNING Land Div4/14/2006 4/14/2006 PASS
Plat has been recorded.
Routing - PLANNING4/11/2006 4/12/2006 FAIL
Marty S. DRH05-00320 Landscape plan needs reworked a little. There need to be shrubs added to the parking lot planters and the evergreen trees, especially the Austrian Pines along the Willowcliff need to have wider spacing approximately 15'-20'.

Susan R. CUP05-00028
Routing - PLUMBING3/27/2006 4/11/2006 FAIL
Several corrections requiring resubmittal ... faxed copy to architect.
Routing - Erosion and Sediment3/22/2006 3/27/2006 PASS
3/27/06 Refer to ESC06-00325 as master plan for project, RP must be determined before permit is issued.
Routing - PUBLIC WORKS3/15/2006 3/22/2006 FAIL
Eliminate disposer(s) in kitchen. 3100 gallon grease inteceptor/atypical volume/potentially to large; Need to show UPC sizing calculation; If volume prescription is correct, install two 1500 gallon interceptors; an interceptor this size will require odor control assessment. Contact Mike Hunter ###-####.
Routing Off Site - STRUCTURAL3/10/2006 3/22/2006 FAIL
Faxed copy of structural review comments needing addressed to Greg Elmore for response.
Routing - PLANNING Land Div3/10/2006 3/15/2006 PEND
Do not issue Building Permit until the Final Plat has been recorded at the County. the City Engineer signed the Final Plat in Dec. 2005.
Plans ACCEPTED BY PLAN TECH  3/10/2006 DONE
Plan routing begun/NEW & ADDTN  3/10/2006 DONE
Application received  3/10/2006 DONE
Routing - PLUMBING6/20/2006 6/22/2005 PASS
project has been phased. this is for area C only. elevator pit pumps must be oil exclusionary. note 7 page P1.0- 1% grade for waste lines 4" and larger.
Third Notice BLD10/30/200710/30/2007   
Second Notice has not been responded to.