BLD-Final | 1/25/2008 | 1/28/2008 | 1/28/2008 | A | PASS |
Tony Young
|
|
|
Michael Phone #: ###-####
|
DOC - Permit Finaled | 1/28/2008 | 1/28/2008 | 1/28/2008 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 1/11/2008 | 1/11/2008 | 1/11/2008 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Final | 12/31/2007 | 1/2/2008 | 1/2/2008 | A | NR |
Tony Young
|
|
|
mike Phone #: ###-#### need hillside 1st
|
BLD-Conference | 11/15/2007 | 11/16/2007 | 11/16/2007 | A | PART |
Tony Young
|
|
|
mike Phone #: ###-#### final conf,, still work to do, mainly need fire sprinklers
|
BLD-Conference | 11/6/2007 | 11/8/2007 | 11/8/2007 | P | PART |
Tony Young
|
|
|
please call 30min prior to meet//Mike ###-#### conf on final
|
BLD-Energy code compliance | 3/13/2007 | 3/14/2007 | 3/14/2007 | A | PASS |
Tony Young
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 3/1/2007 | 3/1/2007 | 3/2/2007 | P | PART |
Tony Young
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles will need to see int shear and fire blocks w/ energy code inspection
|
BLD-Framing/Rough-in | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PASS |
Tony Young
|
|
|
Bob, call 1st; Phone #: ###-####
|
BLD-Framing/Rough-in | 2/22/2007 | 2/23/2007 | 2/23/2007 | A | FAIL |
Tony Young
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles need trades,, walk through frame conf w/ framer and owner,, need seal package also
|
BLD-Other | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PART |
Tony Young
|
|
|
bob -- wall inspection ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith exterior shear
|
BLD-Other | 11/16/2006 | 11/16/2006 | 11/16/2006 | P | CANC |
Tony Young
|
|
|
bob - note: wall inspection ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Inspection cancelled from web by: Patricia Smith
|
BLD-Wall cover | 11/13/2006 | 11/15/2006 | 11/15/2006 | A | FAIL |
Tony Young
|
|
|
bob ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith staples ok per eng. follow up sheet,, need to staple per engineering,, conf. only
|
BLD-Other | 10/31/2006 | 11/1/2006 | 11/1/2006 | P | NR |
Mike Jordan
|
|
|
bob Note: wall inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs to complete shear nailing at S2 areas and get spacing for staples in leiu of 8d nails from engineer.
|
PubWorks Subgrade Approval | 7/14/2006 | 7/14/2006 | 7/14/2006 | | DONE |
|
|
|
Upper level footings approved by the geotechnical engineer
|
BLD-Foundation | 7/12/2006 | 7/13/2006 | 7/13/2006 | A | PART |
Mike Jordan
|
|
|
logan,, pouring at 10am; Phone #: ###-####. Met contractor on site and recieved gfeo-tech report for footings at remainder of house. A copy has been given to Terry Records, but is in vacation. Ok to place conc.
|
BLD-Foundation | 7/12/2006 | 7/12/2006 | 7/12/2006 | P | NR |
Tony Young
|
|
|
Logan,, pour at 10am; Phone #: ###-####
|
BLD-Framing/Rough-in | 7/12/2006 | 7/12/2006 | 7/12/2006 | P | CANC |
Tony Young
|
|
|
logan - stemwall; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 7/11/2006 | 7/11/2006 | 7/12/2006 | P | PART |
Tony Young
|
|
|
logan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles house ftgs ok
|
BLD-Footing | 7/10/2006 | 7/10/2006 | 7/10/2006 | P | NR |
Tony Young
|
|
|
LOGAN; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Foundation | 6/14/2006 | 6/15/2006 | 6/15/2006 | A | PART |
Tony Young
|
|
|
logan - stem wall insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley wip on basement walls
|
BLD-Footing | 6/9/2006 | 6/9/2006 | 6/9/2006 | P | PART |
Tony Young
|
|
|
logan ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley \basement area ftgs ok
|
PubWorks Subgrade Approval | 6/1/2006 | 6/1/2006 | 6/1/2006 | | PART |
|
|
|
Footing subgrade for basement has been approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 5/31/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/31/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 4/18/2006 | 5/18/2006 | 5/30/2006 | | PASS |
|
|
|
5/30/2006 15:16:54 SAM - activity updated through activity BLDA022 from case BLD06-01090.
|
Routing - PLAN CHECK | 4/28/2006 | | 5/30/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 5/30/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/26/2006 | | 4/27/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 4/27/2006 | | 4/27/2006 | | PASS |
|
|
|
Fire sprinklers are required. This house shall be fitted with a NFPA 13D system modified by the installation of a single row of dry sidewall sprinklers installed in the garage(s) along the common walls between the garage(s) and the heated living spaces, spaced sideways according to their listing.
|
Routing - PLANNING | 4/20/2006 | | 4/26/2006 | | PASS |
|
|
|
Failed-Driveway too wide within the front setback. Applicant will come in monday. resubmitted 4/26. driveway redlined to conform.
|
Routing - PUBLIC WORKS GRADING | 4/18/2006 | | 4/20/2006 | | PASS |
|
|
|
Approved as Category 1 by CFH06-00010
|
Routing - PUBLIC WORKS | 4/20/2006 | | 4/20/2006 | | PASS |
|
|
|
|
Application received | | | 4/18/2006 | | |
|
|
|
|