Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 7/17/2006 | 7/17/2006 | 8/2/2006 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | PASS |
Dave Hannah
|
|
|
mitch; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
DOC - Permit Finaled | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/14/2006 | 7/17/2006 | 7/17/2006 | A | DEFR |
Dave Hannah
|
|
|
mitch; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley will do after 2 pm
|
FIRE-Final Inspection | 7/14/2006 | 7/14/2006 | 7/14/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled.
|
BLD-Conference | 6/6/2006 | 6/7/2006 | 6/7/2006 | A | PASS |
Jim Storey
|
|
|
Jim, This inspection is for wall framing,ceiling grid and fire proofing of structural members. We can meet at the 17C lobby if that works for you? THX Troy; Phone #: ###-#### Internet Inspection Request from: Troy Mechsner
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2006 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 4/26/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 4/21/2006 | | 4/26/2006 | | PASS |
|
|
|
4/26/2006 11:15:06 JCM - activity updated through activity BLDA022 from case BLD06-01117.
|
Routing - FIRE | 4/21/2006 | | 4/21/2006 | | PASS |
|
|
|
Approved subject to fire inspector evaluation of FE placement within maximum 75' travel distance (hnot shown on plans).
|
Plan Reviewer's activity | | | 4/21/2006 | | PASS |
|
|
|
Plans reviewed and approved as submitted. JCM
|
1st review completed | | | 4/21/2006 | | PASS |
John Menard
|
|
|
|
Application received | | | 4/19/2006 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Third Notice BLD | 8/18/2006 | 8/18/2006 | | | |
|
|
|
Second Notice has not been responded to.
|
Plan assigned from Web | 4/19/2006 | 4/29/2006 | | | |
|
|
|
|