Permit Information
Permit NumberBLD06-01126
StatusFinaled
Name BRIAN REED
Site Address 5300 W MORRIS HILL RD
Project NameJohn Browning 4-plex
Customer Number 
ePlanReviewNo
Description
(RCE-1 - Jerry Nemec) Four-Plex Apartment - To construct a new 3,586 square feet, two story, four plex. Each unit is two story and over 800 square feet each. Two units are one bedroom, one and one half baths and two units are two bedrooms, one and one half baths. All construction is per the approved plans and attached comment list. MJP DRH05-00377
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  7/26/2007 DONE
Code Occupancy Approval  7/26/2007 FAIL
DetailsDena Gambrel
7-26-07 10:47 Site inspection shows that the paving has not been striped for this 4 plex. No one on location to look at stamp plans from the City. CE not passing occupancy.
BLD-Aging Inspection5/31/20075/31/20075/31/2007 DONE
DetailsTom Arcoraci
called jeff
BLD-Final3/28/20073/29/20073/29/2007APASS
DetailsTom Arcoraci
jeff ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Final1/25/20071/26/20071/26/2007PPART
DetailsDave Hannah
Jeff; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok for temp occ need to fix hand rail and do fine grading
FIRE-Final Inspection1/24/20071/25/20071/25/2007PPASS
DetailsTroy Cobbley
life safety finaled
BLD-Framing/Rough-in12/5/200612/5/200612/5/2006PPASS
DetailsTom Arcoraci
fire stop
BLD-Energy code compliance12/5/200612/5/200612/5/2006PPASS
DetailsTom Arcoraci
fire stop
BLD-Framing/Rough-in12/4/200612/5/200612/5/2006ANR
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/4/2006 at 3:21:22 PM.
BLD-Other11/27/200611/28/200611/28/2006AFAIL
DetailsTom Arcoraci
jeff Note: to cover; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles cn posted
BLD-Other11/21/200611/22/200611/22/2006APART
DetailsJim Sly
jeff Note: cover; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Fire caulk and reinspect for nailing pattern (1HR wall) Because....couldn't get ahold of bldr...and no appr plan
BLD-Framing/Rough-in11/14/200611/15/200611/15/2006APART
DetailsTom Arcoraci
jeff ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to side and cover fire wall
BLD-Other11/9/200611/13/200611/13/2006AFAIL
DetailsTom Arcoraci
jeff - shear nailing and wire wall ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith no plans on site ext covered
BLD-Aging Inspection10/17/200610/17/200610/17/2006 PASS
DetailsTom Arcoraci
BLD-Footing8/15/20068/16/20068/16/2006APASS
DetailsTom Arcoraci
jeff - expecting pour around 11a.m.; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Issue PAID IN FULL permit  7/26/2006  
Telephone call  7/14/2006 DONE
tlk to gerald teal ###-#### that permit and fees are ready to be picked up but needs ACHD and R/P
Permit Ready to Issue  7/14/2006  
Routing - PLAN CHECK6/21/2006 7/13/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  7/13/2006 DONE
Print Pending Permit.LaserJet4  7/13/2006 DONE
Case Summary (BLD)  7/13/2006 DONE
Print Occupancy Form  7/13/2006 DONE
Plan assigned to (M_P)4/24/2006 7/13/2006 PASS
7/13/2006 10:30:09 M_P - activity updated through activity BLDA022 from case BLD06-01126.
Routing - PLUMBING6/9/2006 6/21/2006 PASS
Received revised plumbing plans. already done
Plan resubmittals received  6/19/2006  
Received 1 cover letter to Mike Phillips from Teal Architects regarding Plan review comments, 2 copies of the following--Shear wall calculations, Walls & interior partitions, wood framed, A2-0, A2-1, A2-2, A2-4, A2-5, A4-1, A4-2, A4-3, A4-4, A4-5, A7-2, A7-3, A7-4 and taken to Mike Phillips
Routing - PLAN CHECK6/5/2006 6/9/2006  
Routing to Plumbing.
1st review completed  6/5/2006 FAIL
Failed Plan check.
Routing - FIRE6/1/2006 6/5/2006 PASS
Attached review comments to plans.
Case Summary (BLD)  6/1/2006  
Routing - PLAN CHECK5/9/2006 6/1/2006 FAIL
Plan review completed, sent correction report to the architect requesting additional information be submitted for further review.
Routing - PLUMBING5/23/2006 5/23/2006 PASS
per plans and 2003 upc
Plan resubmittals received  5/12/2006  
Received transmittal letter, 3 copies of the following: C1.0, P-1, P-2, taken to Mike P.
Routing - PLANNING5/9/2006 5/9/2006 PASS
Approved per DRH01-225 & 05-377- Sarah S
Routing - PLUMBING5/2/2006 5/9/2006 FAIL
1" min. water service to each unit. provide a civil plan showing sewer and water services- size and location- from building to connection to mains.
Routing - Erosion and Sediment5/2/2006 5/2/2006 PASS
ESC plan approved with initial subdivision submittal on 9/23/05.
Routing - PUBLIC WORKS4/28/2006 5/2/2006 PASS
Routing - PLANNING Land Div4/25/2006 4/28/2006 PASS
Plans ACCEPTED BY PLAN TECH  4/21/2006  
Plan routing begun/NEW & ADDTN  4/21/2006  
Application received  4/20/2006