Permit Information
Permit NumberBLD06-01192
StatusFinaled
Name OVERLAND PARK ONE LLC
Site Address 6883 W OVERLAND RD
Project NameOVERLAND PARK SHOP CNTR
Customer Number 
ePlanReviewNo
Description
(PRIMARY CONSTRUCTION RCE #3372 - EXTERIOR REMODEL) 6883-3919 & 6945 W. Overland. To remodel the entire front facade and canopy of strip mall per approved plans and CZC06-00048. Note: This building is divided by 3 separate buildings with "area separation" walls previously constructed. Area separation ration walls are to extend through concealed area of new canopy. This building is fully fire sprinkelred any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department. Rmh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  3/15/2007 DONE
Issued letter of compliance on 3-15-07
BLD-Final3/13/20073/14/20073/14/2007APASS
DetailsTom Arcoraci
Gary ###-#### nothing to do with fire
FIRE-Final Inspection3/13/20073/13/20073/13/2007PPASS
DetailsTroy Cobbley
Life safety passed.
Override - Condition Holds  3/13/2007  
BLD-Aging Inspection1/10/20071/10/20071/10/2007 PASS
DetailsTom Arcoraci
BLD-Aging Inspection10/25/200610/25/200610/25/2006 PASS
DetailsTom Arcoraci
BLD-Framing/Rough-in8/23/20068/24/20068/24/2006APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 8/23/2006 at 9:00:12 AM. Contact: ###-####. ok but check 2 hour walls in canopy
BLD-Footing7/26/20067/27/20067/27/2006APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/26/2006 at 2:01:23 PM. Contact: ###-####.
Issue PAID IN FULL permit  6/16/2006 DONE
Plan assigned to (R_H)5/1/2006 6/15/2006 PASS
6/15/2006 07:33:32 RMH - activity updated through activity BLDA022 from case BLD06-01192.
Routing - PLAN CHECK5/22/2006 6/15/2006 PASS
Case Summary (BLD)  6/15/2006 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/15/2006 DONE
Routing - Erosion and Sediment6/15/2006 6/15/2006 PASS
ESC waiver request approved with attached conditions.
Inspection Record Card- Bld  6/15/2006 DONE
Permit Ready to Issue  6/15/2006 DONE
Telephone call  6/15/2006 DONE
TLK TO co that pemit and fees are ready to be picked up
Plan resubmittals received  6/6/2006  
Recieved transmittal sheet, 2 pg. memo, 2 copies of A1.1 & A5.2, taken to Ron H.
1st review completed  5/22/2006 FAIL
Failed Plan Check.
Routing - FIRE5/18/2006 5/22/2006 PASS
Attached review comments to plans.
Routing - PLAN CHECK5/2/2006 5/18/2006 FAIL
Faxed and mailed requirements to the architect 5/18/06, Routed plans to fire same day.
Plan resubmittals received  5/8/2006 DONE
received erosion app & waiver request letter and routed to ron hill
Routing - PLANNING5/2/2006 5/2/2006 PASS
Andrea Tuning CZC06-00048
Routing - Erosion and Sediment5/1/2006 5/2/2006 FAIL
No waiver request or ESC plan included with submittal. Notified applicant.
Routing - PUBLIC WORKS5/1/2006 5/1/2006 PASS
Plans ACCEPTED BY PLAN TECH  4/26/2006 FAIL
5/1/2006-Started routing by Marlene even though ESC had not been applied for on this date.
Recd Pcfee & Taken To Pln CK  4/26/2006  
Application received  4/25/2006