Case Summary (BLD) | | | 7/2/2013 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 8/12/2011 | | DONE |
|
|
|
|
Second Notice BLD | 4/18/2007 | 4/18/2007 | 4/20/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 4/6/2007 | 4/6/2007 | 4/18/2007 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 4/6/2007 | 4/6/2007 | 4/6/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/6/2007 at 10:14:11 AM. Contact: ###-####.
|
DOC - Permit Finaled | 4/6/2007 | 4/6/2007 | 4/6/2007 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 4/3/2007 | 4/3/2007 | 4/4/2007 | P | PASS |
Dave Hannah
|
|
|
steven - first thing in the moring - if not please call ; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
FIRE-Final Inspection | 4/3/2007 | 4/3/2007 | 4/3/2007 | A | PASS |
Troy Cobbley
|
|
|
Correction notice items completed. Life safety passed
|
FIRE-Final Inspection | 3/29/2007 | 3/30/2007 | 3/29/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/29/2007 at 12:13:29 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Mar 29 2007 4:15PM.
|
BLD-Framing/Rough-in | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/8/2007 at 8:17:54 AM. Contact: ###-####. ceiling grid ok
|
BLD-Conference | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 10:01:11 AM. Contact: ###-####. ada counter top and conflect with door openning
|
BLD-Conference | 2/27/2007 | 2/27/2007 | 2/28/2007 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 10:01:11 AM. Contact: ###-####.
|
BLD-Conference | 2/27/2007 | 2/27/2007 | 2/28/2007 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 10:01:11 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/7/2006 | 11/7/2006 | 11/8/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 9:56:36 AM. Contact: ###-####.
|
Plan resubmittals received | | | 9/5/2006 | | |
|
|
|
Received 2 copies of pages P0.0, P0.1, P1.0; taken to Lee Rice
|
BLD-Aging Inspection | 9/1/2006 | 9/1/2006 | 9/1/2006 | | PASS |
Dave Hannah
|
|
|
|
Plan resubmittals received | | | 8/29/2006 | | |
|
|
|
received document transmittal letter from elkhorn & "2" sheets of PO.O, PO.1, & P1.O-plans taken to lee rice
|
Routing - PLUMBING | 8/29/2006 | | 8/29/2006 | | FAIL |
|
|
|
sumps require dual pump system in commercial use
require info on pump sizing
|
Issue PAID IN FULL permit | | | 6/2/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/18/2006 | | |
|
|
|
|
Telephone call | | | 5/18/2006 | | DONE |
|
|
|
called ###-#### and told Cory Nelson that permit is ready and fee, need GC & RCE
|
1st review completed | | | 5/17/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - PLAN CHECK | 5/17/2006 | | 5/17/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/8/2006 | | 5/17/2006 | | PASS |
|
|
|
5/17/2006 14:50:51 CJW - activity updated through activity BLDA022 from case BLD06-01263.
|
Routing - FIRE | 5/12/2006 | | 5/17/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan resubmittals received | | | 5/16/2006 | | |
|
|
|
Received cover transmittal and plan review comments response letter and 2 copies of A5.0 and taken to Carl W.
|
Routing - PLAN CHECK | 5/8/2006 | | 5/12/2006 | | FAIL |
|
|
|
The IBC plan review was started on May 10, 2006 and was finished on May 12, 2006. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 5/8/2006 | | 5/8/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2006 | | |
|
|
|
|
Application received | | | 5/2/2006 | | |
|
|
|
|