Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-01295
StatusFinaled
Name PRIMARY CONSTRUCTION
Site Address 11678 W FRANKLIN RD
Project NameFranklin Building Supply
Customer Number 
ePlanReviewNo
Description
(FRANKLIN BUILDING SUPPLY - TRUCK WASH) To construct a 960 sq. ft. pre-manufactured canopy with equipment room for a truck wash on the south side of the existing building per approved plans and attachments and DRH06-00127. (MLO)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD2/7/20072/7/20072/21/2007 DONE
First Notice has not been responded to.
First Notice 1/26/20072/7/2007 DONE
Permanent occupancy UNPAID FEE  1/26/2007 DONE
Perm. Occ. Cert. # 11413 issued 1-26-06 to Franklin Building Supply for a truck wash.
BLD-Final1/25/20071/25/20071/25/2007PPASS
DetailsMike Jordan
Gary; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Final ok.
Code Occupancy Approval  1/25/2007 PASS
OK PER REQUIREMENTS FINAL SIGNED OFF
FIRE-Final Inspection1/23/20071/24/20071/24/2007APASS
DetailsForrest France
Door hardware corrections verified, fire life safety inspection passed.
Permanent Occupancy 1/24/20071/24/2007 DONE
Details
FIRE-Final Inspection1/18/20071/19/20071/19/2007AFAIL
DetailsTroy Cobbley
Need approved door hardware. Other items are ok.
BLD-Framing/Rough-in1/18/20071/18/20071/18/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 1/18/2007 at 5:35:59 AM. Contact: ###-####. Wanted final insp. Still needs finals from others. Also needs special insp. on high strength bolting.
BLD-Footing10/6/200610/6/200610/6/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/6/2006 at 5:26:43 AM. Contact: ###-####. Footings and column pad footings. Notified cntractor that conc. testing is required.
Issue PAID IN FULL permit  8/10/2006 DONE
Print Occupancy Form  8/8/2006 DONE
Telephone call  8/8/2006  
tlk to tim ###-#### because dana was on vacation that permit and fees are ready to be picked up but needs ACHD
Permit Ready to Issue  8/8/2006  
PLANS/APPL TAKEN TO FRONT DESK  8/7/2006 DONE
Plan assigned to (MLO)6/26/2006 8/7/2006 PASS
Routing - PLAN CHECK7/28/2006 8/4/2006 PASS
Plan resubmittals received  7/28/2006 DONE
Received United Water Fire Flow Documentation via fax.
Routing - FIRE7/28/2006 7/28/2006 PASS
Recieved fire flow documentation.
1st review completed  7/24/2006 FAIL
Failed Fire.
Routing - FIRE7/19/2006 7/24/2006 FAIL
Faxed resubmittal requirement to architec. Requested fire flow documentation. Inserted review comments into plans.
Routing - PLAN CHECK7/10/2006 7/19/2006 PEND
Mike Otto...
Building review approved. Routing to fire for review. Faxed copy of plan review to architect. pep
Routing - PLANNING7/7/2006 7/10/2006 PASS
Routing - PLUMBING7/6/2006 7/7/2006 PASS
use boise city approved flammable liquids interceptor detail, attached. install an R.P. on the water service upstream of the hose bib.
Routing - Erosion and Sediment7/5/2006 7/6/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS6/28/2006 7/5/2006 PASS
Routing - Addressing6/28/2006 6/28/2006 PASS
Routing - PLANNING Land Div6/26/2006 6/27/2006 PASS
parcel is greater than five acres in size.
Plans ACCEPTED BY PLAN TECH  6/26/2006  
Plan routing begun/NEW & ADDTN  6/26/2006  
Telephone call  5/9/2006  
Called Dana Kauffman told him i would not send palns on until i received eng calcs for the metal building 5-9-06 ///DLD
CHANGE STATUS TO (PND)  5/9/2006  
WAITING FOR METAL BUILDING CALCS ///DLD
Application received  5/4/2006