BLD-Final | 8/8/2007 | 8/9/2007 | 8/9/2007 | A | PASS |
Dave Hannah
|
|
|
troy Phone #: ###-####
|
DOC - Permit Finaled | 8/9/2007 | 8/9/2007 | 8/9/2007 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 8/7/2007 | 8/8/2007 | 8/8/2007 | A | NR |
Mike Jordan
|
|
|
troy - please call for access Phone #: ###-####. Needs public works final.
|
BLD-Grading Inspection | 8/8/2007 | 8/8/2007 | 8/8/2007 | | DONE |
|
|
|
Final grading and drainage approved.
|
BLD-Energy code compliance | 3/26/2007 | 3/27/2007 | 3/28/2007 | P | PASS |
Dave Hannah
|
|
|
Troy; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok to cover
|
BLD-Framing/Rough-in | 3/19/2007 | 3/19/2007 | 3/19/2007 | P | PASS |
Dave Hannah
|
|
|
Troy; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok to insulate after fire sprinkler oked
|
BLD-Conference | 3/14/2007 | 3/15/2007 | 3/15/2007 | A | DONE |
Mike Jordan
|
|
|
Troy,, wants a pre-frame conf. walk through; Phone #: ###-####. Walk thru only. Still needs framing insp after fire sprinkler has been instaslled. Could not verify ST22 strap on cantilever beam on main level balcony. Dave, I did note some welding, dont know if you are requiring insp? c/n posted.
|
BLD-Framing/Rough-in | 3/13/2007 | 3/14/2007 | 3/14/2007 | A | NR |
Tony Young
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Victoria Beall need trades 1st,, fire,, called left messege
|
BLD-Framing/Rough-in | 2/26/2007 | 2/26/2007 | 2/27/2007 | P | PART |
Dave Hannah
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 2/26/2007 | 2/27/2007 | 2/27/2007 | A | PART |
Dave Hannah
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok to cover ext shear ok
|
BLD-Framing/Rough-in | 2/23/2007 | 2/23/2007 | 2/23/2007 | P | FAIL |
Dave Hannah
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs fire sprinkler permit and fire sprinkler installed and inspected befor framing inspection can be done
|
BLD-Framing/Rough-in | 2/22/2007 | 2/23/2007 | 2/23/2007 | A | CANC |
Dave Hannah
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PART |
Dave Hannah
|
|
|
troy ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith basement shear walls ok to stand/cover
|
BLD-Footing | 11/7/2006 | 11/8/2006 | 11/8/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 3:19:58 PM. Contact: ###-####.
|
PubWorks Subgrade Approval | 11/8/2006 | 11/8/2006 | 11/8/2006 | | PART |
|
|
|
Footing subgrade for retaining walls on each side of the driveway approved by the geotechnical engineer.
|
BLD-Foundation | 10/12/2006 | 10/13/2006 | 10/13/2006 | A | PASS |
Dave Hannah
|
|
|
clint; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 10/4/2006 | 10/9/2006 | 10/9/2006 | P | PASS |
Dave Hannah
|
|
|
Clint; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
PubWorks Subgrade Approval | 10/5/2006 | 10/5/2006 | 10/5/2006 | | DONE |
|
|
|
Footing subgrade for midfloor section (foundation above basement) has been approved by the geotechnical engineer.
|
BLD-Foundation | 8/10/2006 | 8/10/2006 | 8/10/2006 | P | PART |
Dave Hannah
|
|
|
clint; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley basement walls ok to pour
|
BLD-Footing | 8/4/2006 | 8/7/2006 | 8/7/2006 | A | PART |
Dave Hannah
|
|
|
Clint; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt lower basement ftgs ok to pour
|
PubWorks Subgrade Approval | 8/4/2006 | 8/4/2006 | 8/4/2006 | | PASS |
|
|
|
Received letter from Geotec approving basement foundation footing subgrade. Okay to schedule basement footing inspection.
|
PubWorks Subgrade Approval | 8/4/2006 | 8/4/2006 | 8/4/2006 | | PASS |
|
|
|
Received basement footing subgrade approval letter from geotec. Okay to shchedule basement footing inspection.footin
|
Issue PAID IN FULL permit | | | 7/5/2006 | | |
|
|
|
|
Plan assigned to (SAM) | 5/11/2006 | 6/21/2006 | 6/29/2006 | | PASS |
|
|
|
6/29/2006 08:03:09 SAM - activity updated through activity BLDA022 from case BLD06-01371.
|
Routing - PLAN CHECK | | | 6/29/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 6/29/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/29/2006 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2006 | | DONE |
|
|
|
left vm for troy quick custom homes@###-####/told permit was ready and fees associated with it
|
Plan Reviewer's activity | | | 6/22/2006 | | DONE |
|
|
|
6/22/06 09:55 I called and left a message for Tim Johnson to call me. I have questions on the calculations and the plans. Plans are on hold. I also requested a new foundation plans from Mike Carroll on 6/21/06.
|
Routing - FIRE | 5/16/2006 | | 5/16/2006 | | PASS |
|
|
|
This house requires a fire sprinkler system in accordance with NFPA 13D. (Morningside Heights #2 sub)
|
Routing - Erosion and Sediment | 5/15/2006 | | 5/16/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 5/12/2006 | | 5/15/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/12/2006 | | 5/12/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 5/11/2006 | | 5/12/2006 | | PASS |
|
|
|
Approved as Category 1 by CFH06-00003
|
Application received | | | 5/11/2006 | | |
|
|
|
|