Telephone call | | | 5/2/2007 | | DONE |
|
|
|
call to mr. montoya at ###-####, he stated he would complete the fv cert and fax it back.
|
Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/12/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/28/2006 | 2/2/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/28/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # ``277 issued 12-28-06 to Vidal Montoya.
|
BLD-Final | 12/19/2006 | 12/19/2006 | 12/19/2006 | P | PASS |
Jim Sly
|
|
|
viela; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK for Perm Occ. :) Trades finaled.
|
FIRE-Final Inspection | 12/18/2006 | 12/18/2006 | 12/18/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled. Per Jason Blais the address has been changed to suite 211. I contacted April in addressing to let her know what is going on.
|
FIRE-Final Inspection | 12/15/2006 | 12/15/2006 | 12/18/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled. Per Jason Blais the address has been changed to suite 211. I contacted April in addressing to let her know what is going on.
|
BLD-Final | 12/15/2006 | 12/15/2006 | 12/15/2006 | P | NR |
Jim Sly
|
|
|
vidal ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Final | 12/7/2006 | 12/7/2006 | 12/7/2006 | P | NR |
Jim Sly
|
|
|
bidal ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith need fire final
|
FIRE-Final Inspection | 12/7/2006 | 12/7/2006 | 12/7/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide correct suite number, lower fire extinguisher and provide with annual inspection tag, provide door hardware that unlocks in a single motion, hi-light sticker as discussed and provide the missing fire dept. review comments.
|
BLD-Framing/Rough-in | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PASS |
Jim Sly
|
|
|
bibal montoya; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles F& E OK
|
BLD-Framing/Rough-in | 9/19/2006 | 9/20/2006 | 9/20/2006 | A | PASS |
Jim Sly
|
|
|
bidaf; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Frame and Energy OK.
|
BLD-Energy code compliance | 9/15/2006 | 9/18/2006 | 9/18/2006 | A | PART |
Tom Arcoraci
|
|
|
vedal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles correction notice item incomplete
|
BLD-Framing/Rough-in | 9/8/2006 | 9/8/2006 | 9/8/2006 | P | PART |
Jim Sly
|
|
|
vidal; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK to Insul.....Need paperwork from Architect for alternate method of wall bracing B 4 cover. (or do per plan)
|
BLD-Framing/Rough-in | 9/1/2006 | 9/1/2006 | 9/1/2006 | P | FAIL |
Tom Arcoraci
|
|
|
vidal ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley cn posted
|
Issue PAID IN FULL permit | | | 7/6/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/21/2006 | | 6/30/2006 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2006 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/30/2006 | | DONE |
|
|
|
|
Telephone call | | | 6/30/2006 | | DONE |
|
|
|
tlk to vidal montoya ###-#### that permit and fees are ready to be picked up but needs GC and RCE E
|
Permit Ready to Issue | | | 6/30/2006 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 5/16/2006 | | 6/30/2006 | | PASS |
|
|
|
6/30/2006 09:35:24 JCB - activity updated through activity BLDA022 from case BLD06-01376.
|
Plan resubmittals received | | | 6/29/2006 | | |
|
|
|
recieved 1 copy of 3pg. calculations; taken to Jason Blais
|
Routing - FIRE | 6/15/2006 | | 6/21/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 6/21/2006 | | FAIL |
|
|
|
Failed Plan check.
|
Plan resubmittals received | | | 6/15/2006 | | DONE |
|
|
|
Received fax showing location of service sink. Still need HVAC heating and cooling load calculations to be faxed.
|
Routing - PLAN CHECK | 5/19/2006 | | 6/15/2006 | | FAIL |
|
|
|
Called architect representative to let him know I still needed the HVAC heating and cooling load calculations. When received will attach to plans. Then will e-mail and fax final plan review. Plans to route to Fire Dept. for review.
|
Telephone call | | | 6/14/2006 | | DONE |
|
|
|
Called architect representative Josh Axthelm and talked about providing a service sink in the space and the need for the HVAC heating and cooling load calculations to be faxed over.
|
Routing - PUBLIC WORKS | 5/16/2006 | | 5/19/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/12/2006 | | DONE |
|
|
|
|
Application received | | | 5/11/2006 | | |
|
|
|
|
Third Notice BLD | 2/12/2007 | 2/12/2007 | | | |
|
|
|
Second Notice has not been responded to.
|