Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-01376
StatusFinaled
Name VIDAL MONTOYA
Site Address 10074 W FAIRVIEW AVE Unit: 211
Project NameFairview Office Park Bldg #2
Customer Number 
ePlanReviewNo
Description
(NO CONTRACTOR REGISTRATION PROVIDED) (VIDAL MONTOYA) (FAIRVIEW OFFICE PARK BLDG #2-STE 160) New 1,260 sq. ft. office tenant in a portion of a vacant shell building that was done under BLD04-01640 per approved plans. Work to include completing the concrete slab on the interior of the space, new interior walls and doors, interior finish, a new suspended ceiling, counter with sink, a new accessible restroom, new mechanical including a new HVAC rooftop unit and associated ducting, new plumbing, and new electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is not fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  5/2/2007 DONE
call to mr. montoya at ###-####, he stated he would complete the fv cert and fax it back.
Second Notice BLD2/2/20072/2/20072/12/2007 DONE
First Notice has not been responded to.
First Notice 12/28/20062/2/2007 DONE
Permanent occupancy  12/28/2006 DONE
Perm. Occ. Cert. # ``277 issued 12-28-06 to Vidal Montoya.
BLD-Final12/19/200612/19/200612/19/2006PPASS
DetailsJim Sly
viela; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
OK for Perm Occ. :) Trades finaled.
FIRE-Final Inspection12/18/200612/18/200612/18/2006PPASS
DetailsTroy Cobbley
Life safety finaled. Per Jason Blais the address has been changed to suite 211. I contacted April in addressing to let her know what is going on.
FIRE-Final Inspection12/15/200612/15/200612/18/2006PPASS
DetailsTroy Cobbley
Life safety finaled. Per Jason Blais the address has been changed to suite 211. I contacted April in addressing to let her know what is going on.
BLD-Final12/15/200612/15/200612/15/2006PNR
DetailsJim Sly
vidal ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Final12/7/200612/7/200612/7/2006PNR
DetailsJim Sly
bidal ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
need fire final
FIRE-Final Inspection12/7/200612/7/200612/7/2006PFAIL
DetailsTroy Cobbley
Provide correct suite number, lower fire extinguisher and provide with annual inspection tag, provide door hardware that unlocks in a single motion, hi-light sticker as discussed and provide the missing fire dept. review comments.
BLD-Framing/Rough-in11/17/200611/17/200611/17/2006PPASS
DetailsJim Sly
bibal montoya; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
F& E OK
BLD-Framing/Rough-in9/19/20069/20/20069/20/2006APASS
DetailsJim Sly
bidaf; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Frame and Energy OK.
BLD-Energy code compliance9/15/20069/18/20069/18/2006APART
DetailsTom Arcoraci
vedal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles correction notice item incomplete
BLD-Framing/Rough-in9/8/20069/8/20069/8/2006PPART
DetailsJim Sly
vidal; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
OK to Insul.....Need paperwork from Architect for alternate method of wall bracing B 4 cover. (or do per plan)
BLD-Framing/Rough-in9/1/20069/1/20069/1/2006PFAIL
DetailsTom Arcoraci
vidal ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley cn posted
Issue PAID IN FULL permit  7/6/2006 DONE
Routing - PLAN CHECK6/21/2006 6/30/2006 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  6/30/2006 PASS
Print Occupancy Form  6/30/2006 DONE
Telephone call  6/30/2006 DONE
tlk to vidal montoya ###-#### that permit and fees are ready to be picked up but needs GC and RCE E
Permit Ready to Issue  6/30/2006 DONE
Plan assigned to (JCB)5/16/2006 6/30/2006 PASS
6/30/2006 09:35:24 JCB - activity updated through activity BLDA022 from case BLD06-01376.
Plan resubmittals received  6/29/2006  
recieved 1 copy of 3pg. calculations; taken to Jason Blais
Routing - FIRE6/15/2006 6/21/2006 PASS
Attached review comments to plans.
1st review completed  6/21/2006 FAIL
Failed Plan check.
Plan resubmittals received  6/15/2006 DONE
Received fax showing location of service sink. Still need HVAC heating and cooling load calculations to be faxed.
Routing - PLAN CHECK5/19/2006 6/15/2006 FAIL
Called architect representative to let him know I still needed the HVAC heating and cooling load calculations. When received will attach to plans. Then will e-mail and fax final plan review. Plans to route to Fire Dept. for review.
Telephone call  6/14/2006 DONE
Called architect representative Josh Axthelm and talked about providing a service sink in the space and the need for the HVAC heating and cooling load calculations to be faxed over.
Routing - PUBLIC WORKS5/16/2006 5/19/2006 PASS
Recd Pcfee & Taken To Pln CK  5/12/2006 DONE
Application received  5/11/2006  
Third Notice BLD2/12/20072/12/2007   
Second Notice has not been responded to.