Third Notice BLD | 2/12/2007 | 2/12/2007 | 3/20/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/12/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/10/2007 | 2/2/2007 | | DONE |
|
|
|
|
BLD-Final | 1/9/2007 | 1/10/2007 | 1/10/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/9/2007 at 12:37:05 PM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 1/10/2007 | 1/10/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/10/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/10/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11391 issued 1-10-07 to La Vie En Rose Restaurant on the 1st floor of the Idanha Bldg.
|
CHANGE STATUS TO (ISS) | | | 1/9/2007 | | DONE |
|
|
|
|
BLD-Final | 8/31/2006 | 9/1/2006 | 9/1/2006 | A | PART |
Dave Hannah
|
|
|
andy - call prior to meet there; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok for temp occ needs to remove bolt on door
|
FIRE-Final Inspection | 8/31/2006 | 8/31/2006 | 8/31/2006 | P | PASS |
Forrest France
|
|
|
Items on previous c/n have been verified for completion, inspeciton passed.
|
FIRE-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | FAIL |
Forrest France
|
|
|
Need to post max. occupant load sign per review comments, repair door leaf at the north entry/exit doors, install missing ceiling tile and sprinkler escutcheon at the dry storage room, provide one additional PFE for the back office and storage area as discussed.
|
BLD-Framing/Rough-in | 8/22/2006 | 8/22/2006 | 8/22/2006 | P | PASS |
Dave Hannah
|
|
|
andy - ceiling; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok to cover ceiling
|
BLD-Framing/Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | PART |
Dave Hannah
|
|
|
andy - call prior for access (ceiling grid insp); Phone #: ###-#### Internet Inspection Request from: Barbara Buckley grid ok but need to fix holes in ceiling
|
Routing - PLAN CHECK | 6/23/2006 | | 6/26/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/26/2006 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2006 | | DONE |
|
|
|
tlk to lori ###-#### that permit and fees are ready to be picked up
|
Issue PAID IN FULL permit | | | 6/26/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/22/2006 | | 6/26/2006 | | PASS |
|
|
|
6/26/2006 08:43:13 CJW - activity updated through activity BLDA022 from case BLD06-01416.
|
Routing - PLAN CHECK | 6/20/2006 | | 6/23/2006 | | PASS |
|
|
|
(6-21-06) Drawings approved after resubmittal review. (6-23-06) Drawings sent back to fire after the resubittal was received.
|
Routing - FIRE | 6/23/2006 | | 6/23/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan resubmittals received | | | 6/23/2006 | | |
|
|
|
recieved 3 copies of M1.1; taken to Carl Westfall
|
Plan resubmittals received | | | 6/21/2006 | | DONE |
|
|
|
Received 1 Project letter,1 Bar Store Restaurant Design & Supplies. taken to Carl W.
|
Routing - PLAN CHECK | 6/19/2006 | | 6/20/2006 | | |
|
|
|
Sent back to fire
|
Routing - FIRE | 6/20/2006 | | 6/20/2006 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Attached review comments to plans.
|
Telephone call | | | 6/20/2006 | | DONE |
|
|
|
Spoke with kitchen supplier. Described in detail what is necessary for the review to be completed regarding the product information of the type 1 hood assembly.
|
Routing - PLUMBING | 6/8/2006 | | 6/19/2006 | | PASS |
|
|
|
Big dipper now shown on plan, also Plumber to connect owner suppied kitchen equipment plumbing. Approved per plan and 2003 UPC
|
Plan resubmittals received | | | 6/13/2006 | | |
|
|
|
received "3" sheets of A2.1, "3" sheets of M1.1 with project letter, report etl testing inc cover letter & page 2 & 10, conclusion page c1, memorandum (3 pages)
|
Routing - PUBLIC WORKS | 6/7/2006 | | 6/8/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/7/2006 | | DONE |
|
|
|
Received 1 project letter, & 1 elevation of new opening in existing masonary wall. taken to Carl W.
|
Routing - FIRE | 6/2/2006 | | 6/7/2006 | | FAIL |
|
|
|
Faxed resubmittal requirements to architect. Attached review comment to plans.
|
1st review completed | | | 6/7/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/25/2006 | | 6/2/2006 | | FAIL |
|
|
|
The IBC plan review was started on May 31 and was finished on June 2. Revise drawings were required. See the plan review report.
|
Plan resubmittals received | | | 5/31/2006 | | DONE |
|
|
|
Received 1 transmittal & 3 copys of sheet P1.1 taken to Carl W.
|
Routing - PLUMBING | 5/23/2006 | | 5/25/2006 | | FAIL |
|
|
|
rerout to plumbing after public works pretreatment approval.
|
Routing - PUBLIC WORKS | 5/22/2006 | | 5/23/2006 | | FAIL |
|
|
|
Need to provide grease abatement information. Contact Mike Hunter at ###-####
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2006 | | |
|
|
|
|
Application received | | | 5/16/2006 | | |
|
|
|
|