Voucher Form | | | 1/31/2007 | | DONE |
|
|
|
|
First Notice | 9/21/2006 | 9/21/2006 | 9/28/2006 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 9/20/2006 | 9/21/2006 | 9/21/2006 | A | PASS |
Mike Jordan
|
|
|
rance ###-####- call 1st before insp
|
DOC - Permit Finaled | 9/21/2006 | 9/21/2006 | 9/21/2006 | P | PASS |
Mike Jordan
|
|
|
|
(F) Reprint permit | | | 8/17/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/31/2006 | 8/1/2006 | 8/1/2006 | A | PASS |
Forrest France
|
|
|
Scope of work to install metal framing only for demising wall, existing smoke evac. system to be verified at future TI permit for occupancy inspections.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/31/2006 | | |
|
|
|
No tenant as this space
|
FIRE-Final Inspection | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | CANC |
Troy Cobbley
|
|
|
contractor was not ready
|
BLD-Framing/Rough-in | 7/19/2006 | 7/19/2006 | 7/19/2006 | P | PASS |
Mike Jordan
|
|
|
rance -call 1st for access -1/2 prior; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Inspected steel stud framing for 1hr. demising wall. Contractor noted that his scope was to erect the framming only, no sheetrock. Contractor wanted to final, but needs life/safety to inspect also.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/19/2006 | | |
|
|
|
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/19/2006 | | |
|
|
|
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/19/2006 | | |
|
|
|
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/19/2006 | | |
|
|
|
need fr insp
|
Override - Parcel Holds | | | 7/3/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/3/2006 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 5/17/2006 | 5/17/2006 | 5/18/2006 | | PASS |
|
|
|
5/18/2006 07:54:45 RMH - activity updated through activity BLDA022 from case BLD06-01422.
|
Routing - PLAN CHECK | 5/17/2006 | | 5/18/2006 | | PASS |
|
|
|
|
Routing - FIRE | 5/18/2006 | | 5/18/2006 | | PASS |
|
|
|
Minor remodel / Field Verify
|
Case Summary (BLD) | | | 5/18/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/18/2006 | | DONE |
|
|
|
|
1st review completed | | | 5/18/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/18/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/18/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/18/2006 | | DONE |
|
|
|
called ###-#### and told Paul Lawrence that permit is ready, fee and need GC and RCE
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2006 | | |
|
|
|
|
Application received | | | 5/17/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2006 | | |
|
|
|
|