Information based on query as of Thursday, July 25, 2024.
Permit Information
Permit NumberBLD06-01451
StatusFinaled
Name CM INVESTMENTS LLC
Site Address 323 W JEFFERSON ST
Project NameTHE JEFFERSON BLDG
Customer Number 
ePlanReviewNo
Description
(THE JEFFERSON BUILDING RESIDENTIAL UNITS) (Unit 602 will be left in vanilla finish status and TI permit will need to be pulled to get occupancy for that unit only per Dave Hannah 7-23-09) To construct a new 44,487 sq.ft., 5 story, type III-A, 40 unit residential/condominium building, located above a three hour horizontal fire assembly per Section 508.2 with an approved alternate letter dated 9/27/2006, to allow for three residential units to be located on the first floor, for a total of 43 units. This permit includes the interior tenant improvements for the 3 residential units and the parking garage which are located below the three-hour horizontal fire assembly in the type I-A portion of this building. NOTE: This building is required to be fire sprinklered per NFPA 13 and is used for story increase. Refer to BLD06-01450 for the construction of the type I-A parking garage. All construction shall be per the approved plans and attached comment list. (12 units are less than 800 sq.ft./31 units are greater than 800 sq.ft.) MJP DRH 05-00396 CUP 05-00150
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  4/22/2010  
BLD-Final7/22/20097/23/20097/23/2009APASS
DetailsDave Hannah
Dave, I guess we do want to final the building. Zoning will be signed off this afternoon. Thanks, Zac. Phone #: ###-#### Internet Inspection Request from: bob austin ok for perm occ
Zoning Approval7/23/20097/23/20097/23/2009 DONE
DetailsSarah Schafer
Meets requirements of the Design Review and Conditional Use.
Permanent Occupancy  7/23/2009 DONE
BLD-Final7/22/20097/22/20097/22/2009PCANC
DetailsDave Hannah
Dave We are ready for final. Zac. Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Final7/16/20097/20/20097/22/2009PCANC
DetailsDave Hannah
Final for 602 and rest if the building. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Final7/20/20097/21/20097/22/2009ANR
DetailsDave Hannah
Everthing is signed off. We are ready for final. Thanks. Zac Phone #: ###-#### Internet Inspection Request from: bob austin
PubWorks Occupancy Approval7/21/20097/21/20097/21/2009 DONE
DetailsTiffany Lowery
Final Public Works Occupancy Inspection 02/11/09.
Inspection Record Card- Bld  7/21/2009 DONE
FIRE-Final Inspection7/17/20097/20/20097/20/2009APASS
DetailsForrest France
Fire life safety final inspection completed acceptable with the exception of one missing fire extinguisher at the storage mezzanine level 2nd floor-contractor to provide today as agreed.
FIRE-Final Inspection7/16/20097/17/20097/17/2009ACANC
DetailsTroy Cobbley
Rescheduled for monday as per Zac
FIRE-Final Inspection7/16/20097/20/20097/16/2009ACANC
DetailsForrest France
I need fire life safety for unit 602. Zac Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Conference5/21/20095/21/20095/21/2009PPASS
DetailsDave Hannah
Dave, I have a letter for you to sign. One for the lender to verify that 604 is ok to occupy. Also I have a question on some fire caulking issues in our mechanical room. Thank you, Zac. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Final4/8/20094/9/20094/9/2009APART
DetailsDave Hannah
Dave, I need my final inspection for unit 604. I believe everything else is signed off. By the way this is not Bob. This is Zac Mathews. Call me with any questions. Phone #: ###-#### Internet Inspection Request from: bob austin ok to move into 604
FIRE-Final Inspection4/3/20094/6/20094/7/2009APART
DetailsForrest France
FIRE-Conference3/20/20093/23/20093/23/2009ADONE
DetailsForrest France
On site conference regarding correction notice issued 1/30/09 and FIR permit activity note 1/22/09 addressing obstructions to sprinkler discharge such as surface mounted light fixtures. Discussed NFPA 13D 8.2.5 criteria.
FIRE-Conference3/20/20093/23/20093/23/2009ADONE
DetailsForrest France
On site conference regarding correction notice issued 1/30/09 and FIR permit activity note 1/22/09 addressing obstructions to sprinkler discharge such as surface mounted light fixtures. Discussed NFPA 13D 8.2.5 criteria.
BLD-Final3/6/20093/6/20093/7/2009APART
DetailsDave Hannah
Dave; We were needing electrical sign-off for final on the remaining units on the 4th and 5th floors,which we now have. We had a couple units signed off for final, but not all the units. Could we get those signed off by you this morning,please? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin 4th and 5th floors are ok to occ
BLD-Conference2/27/20092/27/20093/2/2009ADONE
DetailsDave Hannah
BLD-Final2/26/20092/26/20092/26/2009APART
DetailsDave Hannah
Dave; We have all our sign offs for this permit. Can we get the Temp.Oc. today?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin. Ok for occupancy of units #101, 102, 403, 404, 505 & 508 final occ.after all unit are completed
BLD-Final2/23/20092/24/20092/26/2009PPART
DetailsDave Hannah
Dave; We should have our Life/Safety signed off tomorrow morning.We got the punchlist items done on your first walk-thru. Were you able to get satifactory explanation on the stair door question you had? If so,can we get our Temp.Oc.?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
FIRE-Final Inspection2/25/20092/26/20092/26/2009APART
DetailsTroy Cobbley
A temporary occupancy was given until the project related fire alarm permit is finaled. Life safety items will be ok to pass at that time.
FIRE-Final Inspection2/23/20092/24/20092/25/2009AFAIL
DetailsTroy Cobbley
Life safety items are ok. Just waiting for the fire alarm resubmittals which were required due to changes/additional devices.
FIRE-Final Inspection2/24/20092/24/20092/24/2009APASS
DetailsScott Arellano
Emergency egress lighting satisfactory. Emergency generator satisfactory.
FIRE-Final Inspection2/20/20092/23/20092/23/2009AFAIL
DetailsTroy Cobbley
All life safety items except the exit signs, emergency lights and exit discharge lights appear to be ok. The exit signs, emergency lights and exit discharge lights will be tested tomorrow. The project related fire alarm permit still has two issues that need to be addressed prior to a final occupancy.
FIRE-Final Inspection2/19/20092/20/20092/20/2009ADEFR
DetailsForrest France
Discussed project related fire alarm and sprinkler permit work for finals and scheduling for life safety inspection.

BLD-Final2/18/20092/19/20092/20/2009ANR
DetailsDave Hannah
Dave; Our fire inspector,Forrest France, is trying to get us through our Life/Safety by Friday. Would it be possible to have you do your inspection tomorrow,Thurs., so IF there was a problem, we had a day to get it resolved? We are trying to get the Temp.Oc. by Friday, if possible. Let me know.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin I walked project with bob made a small punch list
FIRE-Conference2/18/20092/19/20092/19/2009ADONE
DetailsForrest France
Forrest; Can we get our "Life/Safety" done, or at least started, Thursday am? If you have a check-off list, I will be glad to use it to make sure I have not missed something. Let me know.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
Zoning Approval2/19/20092/19/20092/19/2009 PASS
DetailsCody Riddle
FIRE-Conference2/3/20092/4/20092/4/2009ADONE
DetailsForrest France
Site visit to verify new light fixtures at residential units do not create obstructions for adjacent sprinkler heads.
FIRE-Conference1/26/20091/26/20091/26/2009PCANC
DetailsForrest France
Forrest; I sent you an e-mail; we need to set up a meeting with the owner''s rep to discuss the sprinkler head location issues brought up Friday. What time today would be good with you? I will call, also.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Other1/26/20091/27/20091/26/2009ACANC
DetailsDave Hannah
Dave; Could you reinspect our grid ceiling areas on L3-L7 and the garage elevator lobby grids? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Other1/22/20091/23/20091/23/2009AFAIL
DetailsDave Hannah
Dave; Could we get a ceiling grid inspection for the corridors? Elect. and fire have Oked their end.needs to fire caulk

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
FIRE-Conference1/16/20091/16/20091/16/2009PDONE
DetailsForrest France
Forest; Could you stop by and discuss what is needed for each fire inspection? I want to be sure I do not miss something.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
FIRE-Conference1/15/20091/15/20091/16/2009ADONE
DetailsForrest France
Regarding fire code review notes on areas of refuge.
FIRE-Conference1/15/20091/15/20091/15/2009PDONE
DetailsForrest France
Duplicate request
FIRE-Conference1/8/20091/9/20091/9/2009ADONE
DetailsForrest France
Regarding pin up insulation at the garage levels adjacent to sprinkler uprights.
BLD-Conference1/6/20091/7/20091/7/2009PPASS
DetailsDave Hannah
Dave; Could you get me,or tell me who to contact, to find out what signage is needed to get a C.of O. Also,if we could talk about what is needed for a C.of O.in the building,itself. We all have a general idea,but would like your input.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Energy code compliance12/30/200812/31/200812/31/2008PPART
DetailsDave Hannah
Dave; Could we get a drop inspection for L7?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover drop hard lids on L7
BLD-Energy code compliance12/23/200812/23/200812/23/2008PPART
DetailsDave Hannah
Dave; Could we get a drop inspection on L3?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover drop ceilings on L3
BLD-Conference12/15/200812/15/200812/15/2008PPASS
DetailsDave Hannah
Dave; My drywall forman would like you to look at the 2hr system at the ceiling area of the center stair well.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Energy code compliance12/11/200812/11/200812/11/2008PPART
DetailsDave Hannah
Dave; Could we get a drop inspection on L4?
Also, do you need to look at the trash chute before we do the closure walls?
ceiling L7 ok to cover
Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in12/11/200812/11/200812/11/2008PPART
DetailsDave Hannah
Dave; Could we get a drop inspection on L4?
Also, do you need to look at the trash chute before we do the closure walls?ok to cover dropped ceilings l4

Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference12/5/200812/5/200812/8/2008APART
DetailsDave Hannah
Dave; Chewie, or drywaller, has a question on 2hr. assembly at a mech. rm. Could you stop by please?

Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Energy code compliance12/2/200812/2/200812/2/2008PPASS
DetailsDave Hannah
Dave; While you were gone,we had Jim Story look at the drop areas on L5. In unit B1 west, there was a pipe that needed to be dropped,then the hole drywalled and firecaulked. This was about 12" long and has been repaired. Could you look at this please? ok to cover
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Energy code compliance11/26/200811/28/200811/28/2008APART
DetailsJim Storey
Could we get a drop ceiling inspection before cover?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin fith foloor ok all but ceilling in b1 west closet plm trap arm pvc void gyp ceilling protection.
BLD-Conference11/12/200811/13/200811/20/2008PCANC
DetailsDave Hannah
Dave; Could we get a framing inspection on the storage area (L2), and a "dry run" on L7 to find any pending problems?
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in11/19/200811/19/200811/20/2008PNR
DetailsDave Hannah
Dave; Could we do a "dry run" on L7. I have most,if not all, the info you needed.

Thanks,Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in11/20/200811/20/200811/20/2008AFAIL
DetailsDave Hannah
Dave; Could we do a "dry run" on L7. I have most,if not all, the info you needed.

Thanks,Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in11/6/200811/6/200811/6/2008PPART
DetailsDave Hannah
Dave; Could we get a framing inspection on the stairways and could you check the fire caulking at the tub/shower locations on L3 and L4? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin OK to cover ceilings ok to cover stairtowers ok to cover lobby and corradors on ground floor
BLD-Energy code compliance10/24/200810/24/200810/27/2008PPART
DetailsDave Hannah
Dave; Did you want to look at the fire collars for the tub connections at the sixth floor ceilings? If so, could you get here about 2:30 - 3pm. I will be off site early afternoon. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover 6th floor ceil tub and shower drains on 7th floor ok
BLD-Energy code compliance10/21/200810/21/200810/21/2008PPASS
DetailsDave Hannah
Dave; Could you inspect the insulation on L6?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover
BLD-Framing/Rough-in10/16/200810/20/200810/21/2008PPART
DetailsDave Hannah
Dave; Could we get a rough-in inspection for L6?
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to insulate
BLD-Framing/Rough-in10/15/200810/16/200810/17/2008PCANC
DetailsDave Hannah
Dave; Could we get a rough-in inspection on L6?
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference10/13/200810/14/200810/14/2008APART
DetailsDave Hannah
Dave; Drywaller needs you to OK his shaft work at the lobby area which was discussed last week with you and the HVAC.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover
BLD-Energy code compliance10/9/200810/10/200810/13/2008ACANC
DetailsDave Hannah
Dave; Could we get an insulation inspection for L5? Also, need to converse about drop ceiling situation. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover 5th
BLD-Framing/Rough-in10/7/200810/7/200810/7/2008PPART
DetailsDave Hannah
Dave; Could we get a rough-in inspec. for L5?
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to insulate the 5th floor and ok to cover 4th
BLD-Framing/Rough-in9/24/20089/24/20089/26/2008PPART
DetailsDave Hannah
Dave; Could we get a rough-in inspectionon
L4. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to insulate
BLD-Wall cover9/21/20089/22/20089/23/2008PPART
DetailsDave Hannah
Dave; Could we get an insulation inspection for L3.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover level 3
BLD-Wall cover9/22/20089/23/20089/23/2008APART
DetailsDave Hannah
Dave; All the exterior walls have been insulated on L3. Sorry about the re-inspection. Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover level 3
BLD-Framing/Rough-in9/19/20089/19/20089/20/2008PPART
DetailsDave Hannah
Dave; Could we get a rough-in re-inspection on level 3?
Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to insulate level 3
BLD-Framing/Rough-in9/16/20089/17/20089/17/2008PFAIL
DetailsDave Hannah
Dave; Could we get a framing inspection on L3? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin needs to install seal package draft stop fire caulk and fix over cut top plates
BLD-Conference9/13/20089/15/20089/15/2008APART
DetailsDave Hannah
Dave; The disposition you sent back to me,for Friday''s inspection,OKed the covering of soffits at roof,but made no reference to the OK to install dryer boxes and vent pipes in 1hr.party walls with 1hr.drywall system around box and vent pipe. Could you send me that OK for my records,please? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to install dryer ducts in sheetrocked chases in party walls
BLD-Framing/Rough-in9/12/20089/12/20089/12/2008APART
DetailsDave Hannah
Dave; Need to drywall soffits at roof.I have partial inspections from electrical and fire.Could you check this area?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover soffits
BLD-Framing/Rough-in9/11/20089/11/20089/12/2008PDEFR
DetailsDave Hannah
Dave; Need to drywall soffits at roof.I have partial inspections from electrical and fire.Could you check this area?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin rescheduled for 9/12 out of time
BLD-Conference8/29/20089/2/20089/2/2008APART
DetailsDave Hannah
Dave; We need to have a 10min. conference on
what the drywaller plans to do around the elevator doors.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in8/27/20088/27/20088/28/2008PPART
DetailsDave Hannah
Dave; Could we get framing inspection on shear walls so framer can complete those areas? Also, we should have the fire caulking engineered suggestions for the plumbers by the time you get here,with a little luck! Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover walls with no plumbing in them
BLD-Conference8/13/20088/14/20088/14/2008PDONE
DetailsDave Hannah
Dave; Could we set up a meeting at 2pm to go over the fire collars that you requested at the cast iron-PVC joints? The plumbing office crew will be here,also. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in7/22/20087/22/20087/23/2008PPART
DetailsDave Hannah
Dave; Could we get the holdowns inspected
so we can finish up the shear ply?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin checked hold dowms all in place ok to cover two sided shear walls also looked at roof sheeting nailing and straping ok
Plan resubmittals received  7/22/2008  
DetailsDan Stuart
Per Marlene take in as resubmittals: Received transmittal and three copies of sheets A223, M306, M307, M404, M604, E2.6P, E2.6S, E2.6L; taken to Dan Stuart
BLD-Wall cover7/11/20087/11/20087/14/2008PPART
DetailsDave Hannah
Dave; We are starting to drywall the interior of the elevator shaft. You said you wanted to check when it got going.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to keep going
BLD-Framing/Rough-in7/8/20087/8/20087/8/2008APART
DetailsDave Hannah
Dave; I need inspections on the exterior drywall for cover;the theater board sound insulation in the fluid cooler shaft; general look at the framing; some pre-drywall at the lower north units;and a conference on the elevator shaft drywall. Ext sheetrock ok ok to start per rock on soffits
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Framing/Rough-in7/8/20087/8/20087/8/2008ACANC
DetailsDave Hannah
Dave; I need inspections on the exterior drywall for cover;the theater board sound insulation in the fluid cooler shaft; general look at the framing; some pre-drywall at the lower north units;and a conference on the elevator shaft drywall.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Framing/Rough-in7/8/20087/8/20087/8/2008ACANC
DetailsDave Hannah
Dave; I need inspections on the exterior drywall for cover;the theater board sound insulation in the fluid cooler shaft; general look at the framing; some pre-drywall at the lower north units;and a conference on the elevator shaft drywall.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin Inspection cancelled from web by: bob austin
BLD-Wall cover6/14/20086/17/20086/17/2008APART
DetailsDave Hannah
Dave; If you need to,could you inspect the nailing on the exterior wall ply, from the middle of the 3rd level thru the 4th level? 8" and 12" is the nailing pattern. I will be out of town this week.Could you leave a message on my cell if there is a problem?
Otherwise, I will tell the drywaller to continue with the exterior drywall.
Thanks, Bob
Phone #: ###-#### Internet Inspection Request from: bob austin ok to start rocking ext walls
BLD-Conference6/10/20086/10/20086/11/2008PPART
DetailsDave Hannah
Dave; Can you,me,and my steel fabricator meet at the jobsite at 2pm +- to discuss the code concerning the bolts used in the steel decks?He has a couple questions. Let me know what time works. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin talked about connections of decks to bluiding will get engineer to reveiw
BLD-Conference6/9/20086/9/20086/10/2008PPASS
DetailsDave Hannah
Dave; Got a question on the bolts for the steel balcony decks. I will call you.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Wall cover5/29/20085/30/20085/30/2008APART
DetailsDave Hannah
Dave; Could you inspect the exterior ply nailing? You might need those binoculars you were talking about!! We would like to start installing both layers of drywall on the exterior walls this weekend,if that would be OK with you. Phone #: ###-#### Internet Inspection Request from: bob austin. Ext walls level 3-5 0k to cover with sheetrock
BLD-Wall cover5/20/20085/20/20085/20/2008PPART
DetailsDave Hannah
Dave; Could we get the north wall,street level, inspected for nailing? Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to sheetrock
FIRE-Conference5/14/20085/15/20085/15/2008PDONE
DetailsForrest France
On site discussion regarding FDC and pump test header locations.
BLD-Aging Inspection5/13/20085/13/20085/12/2008 PASS
DetailsDave Hannah
wip
BLD-Conference5/7/20085/7/20085/7/2008PPART
DetailsDave Hannah
Dave; We are doing more shaft drywall vertical. We will be installing both layers,then fire taping.Drywall forman said you were OK with them installing both layers as long as it was called in. Is that stair towers third level res ok on outer layer of sheetrock
OK? Call me if it is not OK. Thanks,Bob
Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference5/5/20085/5/20085/5/2008PPASS
DetailsDave Hannah
Dave; Need quick answer on notching bottom 2 of 4 top plates at corridors. Could talk over phone if you want. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
Plan resubmittals received  5/1/2008  
per Dan Stuart take in as a resubmittal- received transmittal sheet & letter from erstad arch. Also from yu & trochalakis pllc -structural eng (3) pages. also penthouse floor ceiling assembly (9) pages. Also roof framing revision supplemental calcs (29) pages- took plans to Dan Stuart
BLD-Conference4/29/20084/29/20084/29/2008APASS
DetailsDave Hannah
Dave , conf with Dixie 9: 00 AM
BLD-Conference4/28/20084/29/20084/29/2008APASS
DetailsDave Hannah
Dave; I need to go over some steel deck
installation issues.

Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference4/16/20084/17/20084/17/2008PPART
DetailsDave Hannah
Dave; We need you to look at first layer drywall on exhaust shaft. Same nail pattern as ext.gyp.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover
BLD-Conference4/14/20084/15/20084/15/2008APART
DetailsDave Hannah
Dave; Could we get inspection for 1st layer of drywall on stairway walls?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin first level ext sheet rock first layer west wall ok second level stair tower first layer ok
Plan resubmittals received  4/14/2008  
Received transmittal and three copies of cover sheet; taken to Marlene S.
BLD-Conference4/8/20084/9/20084/9/2008APART
DetailsDave Hannah
Dave; Could we get the nailing checked for exterior ply sheathing? 8" edge,12" field.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ext fire rated ply wood 1st level of wood east side nailing ok
Plan resubmittals received  3/27/2008  
Received letter, two copies of structural calculations, and three copies of sheets S2.08, A800, A801, A810, A902; taken to Marlene Southard
BLD-Conference3/21/20083/21/20083/21/2008PPART
DetailsDave Hannah
Dave; Could you inspect the 2nd layer of drywall on stair walls? Thanks Phone #: ###-#### Internet Inspection Request from: bob austin ok first floor
BLD-Conference3/20/20083/20/20083/20/2008PPART
DetailsDave Hannah
Dave; Could you drop by about 2:30-3:00 and
take a look at 1st layer of drywall at stairway walls.The drywall forman and framing ok to add second layereforman would like to be there. Let me know if this time is not good.Thanks. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference3/18/20083/18/20083/18/2008APASS
DetailsDave Hannah
Dave; Could we meet for a quick discussion on stair drywalling sequence?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
Plan resubmittals received  1/18/2008 DONE
Received letter of request from Erstad Architects for reinterpretation of allowable openings on the east elevation and forwarded to Marlene.
Issue PAID IN FULL permit  12/27/2007 DONE
Telephone call  11/20/2007 DONE
left mess for leonard butler at ###-#### that plans need to be picked up by dec 31st 2007
Telephone call  11/7/2007 DONE
Called David Holm at ###-####, told him fees, and faxed over letter with fees attached, need ACHD
Permit Ready to Issue  11/7/2007 DONE
Routing - PLAN CHECK10/9/2007 11/6/2007 PASS
All departments have approved. Prepared plans and took them to permit desk to be issued. (msouthard)
PLANS/APPL TAKEN TO FRONT DESK  11/6/2007 DONE
Print Occupancy Form  11/6/2007 DONE
Plan assigned to (M_P)5/22/2006 11/6/2007 PASS
11/6/2007 11:29:13 MYS - activity updated through activity BLDA022 from case BLD06-01451.
Routing - PLUMBING10/8/2007 10/9/2007 PASS
tie pump discharge to 8" gravity line. suds relief will be required through out.
Routing - PLAN CHECK9/16/2007 10/8/2007 PEND
Routing to plumbing for sign off.
Plan resubmittals received  10/4/2007  
Received transmittal, 8pg. response, 3pg. (double sided) 8 1/2" x 1" mechanical drawings, two copies of memo, one copy of Lighting Compliance, and two copies of pages A002a, A0005, A200, A201, A202, A203, A204, A205, A206, A220, A221, A222, A223, A224, A225, A240, A241, A250, A251, A301, A361, A700, A800, A801, A802, A810, A811, A812, A900, A901, A902, S2-01-F, S2-01-R, S2-03-W, S2-04, S2-05, S2-06, S2-07, S2-08, S5-03, M202, M601, M602, M603, M604; inserted by arch. rep and taken back to Mike Phillips
Routing - FIRE9/11/2007 9/16/2007 PASS
Plans are approved as noted in red on issue set. Updated review comments have been attached to the plans.
Routing - PLAN CHECK8/22/2007 9/11/2007 ----
Routing to fire.
Routing - PLAN CHECK4/9/2007 8/22/2007 FAIL
Second review failed, sent correction report to the architect. Additional information is required to be submitted and review prior to issuing permit.
Plan resubmittals received  8/7/2007  
received AOO6, AOO7, A2O1, A2O2, A22O, (2 PAGES) OF A222, A224, A225, A24O, A250, A251, A252, A3OO, A3O1, A361, A7OO, A8O1, A810, A811, A812, A902, M1O2, M103, M2O1, M2O2, M301, M3O2, M3O3, M3O4, M3O5, M306, M307, M4O1, M402, M403, M4O4, M504, M604, EO.O, E1.OE1.1, E1.2, E1.3, E1.4, E2.O, E2.1L, E2.1S, E2.2L, E2.2S, E2.3L,E2.3P, E2.3S, E2.4L, E2.4P, E2.4S, E2.5L, E2.5P, E2.5S, E2.6L, E2.6P, E2.6S, E2.7R, & E3.O--plans taken to mike phillips
Plan resubmittals received  8/1/2007  
received transmittal letter from erstad architects (2) pages, response to corrections from driscoll arch (8) pages. Also AOO6, AOO7, A2O1, A2O2, A22O, A222, A222, A224, A225, A24O, A25O, A251, A252, A3OO, A3O1, A361, A7OO, A8O1, A81O, A811, A812, A9O2, M1O2, M1O3, M2O1, M2O2, M3O1, M3O2, M3O3, M3O4, M3O5, M3O6, M3O7, M4O1, M4O2, M4O3, M4O4, M5O4, M6O4, EO.O, E1.O, E1.1, E1.2, E1.3, E1.4, E2.O, E2.1L, E2.1S, E2.2L, E2.2S, E2.3L, E2.3P, E2.3S, E2.4L, E2.4P, E2.4S, E2.5L, E2.5P, E2.5S, E2.6L, E2.6P, E2.6S, E2.7R, & E3.O--plans taken to Mike Phillips
Plan resubmittals received  6/27/2007 DONE
received 2 copys of sheets S2.02-F, S2.02-R taken to Mike P
Plan resubmittals received  6/25/2007  
Received 1 cover transmittal, 2 copies of sheets- L100, L200, 3 copies of sheets S1.00, S1.01, S2.00-F, S2.01-F, S2.01-R, S2.02-F, S2.02-R, S2.03-F, S2.03-R, S2.03-W, S2.04, S2.05, S2.06, S2.07, S2.08, S3.00, S3.01, S3.02, S3.03, S3.03a, S3.04, S3.05, S4.00, S4.01, S4.02, S4.03, S4.04, S5.00, S5.01, S5.02, S5.03, S5.04, S5.05, S5.06 and taken to Mike Phillips
Plan resubmittals received  6/13/2007  
Received transmitta and two copies of pages A001, A003, A004, A005, A006, A007, A100, A200, A201, A202, A203, A204, A205, A206, A220, A221, A222, A223, A224, A240, A241, A242, A250, A251, A252, A300, A301, A310, A311, A312, A360, A361, A362, A500, A501, A700, A702, A703, A704, A710, A800, A801, A802, A810, A811, A812, A820, A821, A822, A900, A901, A902, M101, M102, M103, M201, M202, M301, M302, M303, M304, M305, M306, M307, M401, M402, M403, M404, M501, M502, M503, M504, M505, M601, M602, M603, M604, E0.0, E1.0, E1.1, E1.2, E1.3, E1.4, E2.0, E2.1L, E2.1S, E2.2L, E2.2S, E2.3L, E2.3P, E2.3S, E2.4L, E2.4P, E2.4S, E2.5L, E2.5P, E2.5S, E2.6L, E2.6P, E2.6S, E2.7R, E3.0; taken to Mike Phillips
Plan resubmittals received  4/25/2007  
Received transmittal letter and 2 copies of page A203; taken to Mike Phillips
Plan resubmittals received  4/23/2007  
Received transmittal letter, 13pg. response letter, 1pg. letter from Musgrove Eng., and 2 copies of the following pages: Cover, A001, A002a, A002b, A003, A004, A005, A006, A007, A100, A200, A201, A202, A203, A204, A205, A206, A220, A221, A222, A223, A224, A240, A241, A250, A251, A252, A300, A301, A310, A311, A312, A360, A361, A362, A500, A501, A700, A702, A703, A704, A710, A800, A801, A802, AA810, A811, A812, A820, A821, A822, A900, A901, A902, E0.0, E1.0, E1.1, E1.2, E1.3, E1.4, E2.0, E2.1L, E2.1S, E2.2L, E2.2S, E2.3P, E2.3L, E2.4L, E2.1P, E2.4S, E2.5L, E2.5P, E2.5S, E2.6L, E2.6P, E2.6S, E2.7R, E3.0, I-1.01, I-1.02, I-1.03, I-1.04, I1.05, I-1.06, I-1.07, I-1.08, I-1.09; taken to Mike Phillips
Routing - PLANNING4/6/2007 4/9/2007 PASS
Construction must comply with the requirements of CUP, DR, and DA related to the project.
Routing - PLUMBING4/4/2007 4/6/2007 FAIL
resent review, corrections not made.
Routing - PLAN CHECK4/6/2007 4/6/2007 ----
Routing to Planning.
Routing - PLANNING3/30/2007 4/4/2007 FAIL
Routing - PLAN CHECK4/4/2007 4/4/2007 ----
Routing to Plumbing.
Routing - PLAN CHECK1/31/2007 3/30/2007 ----
Routing to Planning.
Routing - PLANNING1/29/2007 1/31/2007 FAIL
Building elevations do not match those approved by DR. Contacted the applicant via email today.
Routing - PLAN CHECK1/16/2007 1/29/2007 ----
Routing to Planning.
Routing - PLAN CHECK1/8/2007 1/16/2007 ----
Routing to Land Division
Routing - PLANNING Land Div1/16/2007 1/16/2007 PASS
1st review completed  1/8/2007 FAIL
Routing - FIRE1/4/2007 1/8/2007 FAIL
Faxed resubmittal items to architect. Inserted review comments into plans.
Routing - PLAN CHECK6/27/2006 1/4/2007 FAIL
Plan review complete, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
Routing - Erosion and Sediment6/14/2006 9/15/2006 PASS
No additional ESC permit required, original ESC permit covers thes part of the project.adh.
Routing Off Site - STRUCTURAL  9/11/2006 PASS
Received date unknown as revised structural sent directly to Boise's contract engineer by the designing engineer. Revisions were approved on 9/11/06.
Routing Off Site - STRUCTURAL7/18/2006 8/9/2006 FAIL
Called Action Couriers for pick up
Second review failed.
Plan resubmittals received  7/13/2006  
Received 1 copy of cover transmittal, 3 copies of Review comments, 4 copies each of the following sheets--A206, S1.00, S1.01, S2.00F, S2.01F, S2.01R, S2.02F, S2.02R, S2.03F, S2.03R, S2.03W, S2.04, S2.05, S2.06, S2.07, S2.08, S3.00, S3.01, S3.02, S3.03, S3.04, S3.05, S4.00, S4.01, S4.02, S4.03, S4.04, S5.00, S5.01, S5.02, S5.03, S5.04, S5.05, S5.06 and taken to Mike Phillips
Plan resubmittals received  7/13/2006  
Received 1 cover transmittal letter, 1 copy of the following sheets--A06, S1.00, S1.01, S2.00-F, S2.01-R, S2.02-F, S2.02-R, S2.03-F, S2.03-R, S2.03-W, S2.04, S2.05, S2.06, S2.07, S2.08, S3.00, S3.01, S3.02, S3.03, S3.04, S3.05, S4.00, S4.01, S4.02, S4.03, S4.04, S5.00, S5.01,S5.02, S5.03, S5.04, S5.05, S5.06 and taken to Mike Phillips
Routing - PLANNING6/22/2006 6/27/2006 FAIL
DRH05-00396, CUP05-00150 Cody R.

Issues with changes to elevations, parking requirements, and required easments. Faxed applicant a list of necessary corrections.
Routing - PLUMBING6/14/2006 6/22/2006 FAIL
see bld06-01450 for review comments
Routing - PUBLIC WORKS6/1/2006 6/14/2006 PASS
Routing Off Site - STRUCTURAL5/23/2006 6/7/2006 FAIL
E-mailed comments to the architect additional review requried.
Routing - PLANNING Land Div5/23/2006 6/1/2006 FAIL
An application for a record of survey (ROS06--00041) has been submitted for the property. Do not issue a Building Permit until the record of survey has been finalized.
Plans ACCEPTED BY PLAN TECH  5/23/2006 DONE
Plan routing begun/NEW & ADDTN  5/23/2006  
Telephone call  5/22/2006 DONE
called Action Couriers for pick-up to Stapley Eng.
Application received  5/19/2006  
First Notice 7/23/2009