Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-01452
StatusFinaled
Name DANIEL MCCOWN
Site Address 2102 N 21ST ST
Project Name 
Customer Number 
ePlanReviewNo
Description
UPDATED PERMIT ON 8-9-06 TO INCLUDE: Deck over covered front porch, deck over rear porch, and a hot tub deck over Master bathroom as per approved plans.(SRZ) "CONTRACTOR McCOWN REGISTRATION NUMBER RCE-7905" --Early start approved per Steve Munroe///6/2/06 BAS To construct a 3447sq.ft. three story single family dwelling (1603sq.ft. First floor / 1409sq.ft. Second floor / 435sq.ft. Third floor Bonus Room) with a 93sq.ft. Covered front porch, and a 182sq.ft. Covered rear patio per approved plans, all red-lining, Engineering, and Plan review report. THE PERMIT HOLDER is responsible to comply with current wall bracing requirements adopted by Boise city. R-1C zoning district and building setbacks as per Sue Hanson with Planning and Zoning. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/6/20076/13/20076/13/2007ADONE
DetailsTony Young
Daniel
BLD-Final6/11/20076/12/20076/12/2007APASS
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
DOC - Permit Finaled6/12/20076/12/20076/12/2007PPASS
DetailsTony Young
c of o issued
BLD-Final6/6/20076/6/20076/6/2007PFAIL
DetailsTony Young
daniel; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
need hand rail clearance and guard rail space
BLD-Energy code compliance11/15/200611/15/200611/16/2006PPASS
DetailsTony Young
daniel; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in11/9/200611/13/200611/13/2006APART
DetailsTony Young
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
need to fire block 2 areas,, front entry closet and chase walls at top of stairs
BLD-Conference10/31/200610/31/200610/31/2006PPART
DetailsTony Young
scott; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
general frame conf.,, ok to cover upstairs mechanical room,, and detached garage
BLD-Framing/Rough-in10/26/200610/27/200610/27/2006AFAIL
DetailsTony Young
scott; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
c/n posted,, do not insulate,, need trades 1st
BLD-Framing/Rough-in8/25/20068/25/20068/25/2006PNR
DetailsTony Young
william; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing8/24/20068/24/20068/24/2006PPART
DetailsTony Young
kenny; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
garage ftgs,, wip
BLD-Framing/Rough-in8/16/20068/16/20068/16/2006PPART
DetailsDave Hannah
daniel - pre-siding; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok to cover ext
Case Summary (BLD)  8/9/2006  
Plan Reviewer's activity  8/9/2006 DONE
Updated existing building permit to include front upper deck, deck over rear patio, and a Hot tub deck over Master bath. (SRZ)
BLD-Footing6/26/20066/26/20066/26/2006PPART
DetailsTony Young
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Permit Ready to Issue  6/26/2006 DONE
Telephone call  6/26/2006 DONE
spoke to daniel mccown@###-####/told him that permit was ready and fees associated with it
Issue PAID IN FULL permit  6/26/2006  
BLD-Footing6/22/20066/23/20066/23/2006PNR
DetailsTony Young
###-#### - mike
Plan assigned to (SRZ)6/21/20066/21/20066/23/2006 PASS
6/23/2006 12:04:08 SRZ - activity updated through activity BLDA022 from case BLD06-01452.
Routing - PLAN CHECK5/22/2006 6/23/2006 PASS
Plan Reviewer's activity  6/23/2006 PASS
Recieved truss framing plan. Designer is to verify girder point loads are incorporated into the floor framing beam designs and call me back. (SRZ)
PLANS/APPL TAKEN TO FRONT DESK  6/23/2006 DONE
Inspection Record Card- Bld  6/23/2006 DONE
Case Summary (BLD)  6/22/2006  
Telephone call  6/22/2006 DONE
I left a message with the Applicant and spoke with the Designer. I requested a new Res-check and resolved a beam question. I was told the Applicant / Builder will get me a Roof framing plan. (SRZ)
Plan assigned to (SAM)5/19/20065/19/20066/21/2006 DONE
Plan Reviewer's activity  6/21/2006 PASS
Pending New Res-check, and Roof Framing Plan. (SRZ)
Early Start Permit  6/2/2006 DONE
Routing - PUBLIC WORKS5/19/2006 5/22/2006 PASS
Application received  5/19/2006  
Routing - PLANNING5/19/2006 5/19/2006 PASS
Redlined rear setback after discussion with Daniel. See memo from Wayne Gibbs re: side street setbacks on lots platted prior to 5/27/90.