Case Summary (BLD) | | | 3/12/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/21/2011 | | |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/25/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/17/2006 | 12/27/2006 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 11/15/2006 | | PASS |
|
|
|
FINAL SIGNED OFF
|
Permanent occupancy UNPAID FEE | | | 11/14/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11297 issued 11-14-06 to Planet Kid.
|
BLD-Final | 11/3/2006 | 11/6/2006 | 11/6/2006 | P | PASS |
Tom Arcoraci
|
|
|
chris ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for perm when others sign perm
|
FIRE-Final Inspection | 11/3/2006 | 11/6/2006 | 11/6/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. Max occupant load signs at three locations to be posted prior to structural final for verification at final field inspection.
|
Permanent Occupancy | | 11/6/2006 | 11/6/2006 | | DONE |
|
|
|
|
BLD-Final | 11/3/2006 | 11/3/2006 | 11/3/2006 | P | NR |
Jim Sly
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 11/2/2006 | 11/3/2006 | 11/3/2006 | A | FAIL |
Forrest France
|
|
|
The project related fire sprinkler permit must be finaled prior to life safety final.
|
BLD-Other | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PASS |
Tom Arcoraci
|
|
|
chris - note: ceiling grade ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 10/3/2006 | 10/4/2006 | 10/4/2006 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 9/27/2006 | 9/28/2006 | 9/28/2006 | P | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles int ok
|
Issue PAID IN FULL permit | | | 8/29/2006 | | |
|
|
|
|
OVERRIDE | | | 8/24/2006 | | |
|
|
|
|
OVERRIDE | | | 8/24/2006 | | |
|
|
|
|
OVERRIDE | | | 8/24/2006 | | |
|
|
|
|
Print Occupancy Form | | | 8/24/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/24/2006 | | DONE |
|
|
|
tlk to brandon shelton ###-#### that permit and fees are ready to be picked up but needs GC/RCE #
|
Override - People Holds | | | 8/24/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 8/24/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/21/2006 | | 8/22/2006 | | PASS |
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2006 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 6/20/2006 | | 8/22/2006 | | PASS |
|
|
|
8/22/2006 16:33:38 DRS - activity updated through activity BLDA022 from case BLD06-01555.
|
Routing - PLUMBING | 8/21/2006 | | 8/21/2006 | | PASS |
|
|
|
per plans and previous plan review comments.
|
Routing - Erosion and Sediment | 8/19/2006 | | 8/21/2006 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Routing - PLAN CHECK | 8/19/2006 | | 8/19/2006 | | PEND |
|
|
|
No resubmittals required. Routing to plumbing plan review for re-review.
|
Plan resubmittals received | | | 8/17/2006 | | |
|
|
|
Received cover transmittal, 2 page letter from Houston-Bugatsch for plan review response, 1 copy of letter from Tikker Engineering, 2 copies of revised structural calcs, 2 copies of the following sheets--A2.1, A2.2, A4.3, A6.0, A8.0, A8.1, M3.0 and taken to Dan Stuart
|
1st review completed | | | 7/14/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - FIRE | 7/11/2006 | | 7/14/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan resubmittals requested | | | 7/11/2006 | | DONE |
|
|
|
Copy of correction conditions faxed and e-mailed to architect.
|
Routing - PLAN CHECK | 6/7/2006 | | 7/11/2006 | | FAIL |
|
|
|
Resubmittals required. copy of plan review corrections e-mailed and faxed to Rick Bugatsch. Routing to fire code analyst for review.
|
Plan assigned to (JCB) | 6/2/2006 | | 6/20/2006 | | ---- |
|
|
|
REASSIGNED TO DAN STUART BY MSOUTHARD
|
Plan resubmittals received | | | 6/9/2006 | | |
|
|
|
Received 1 copy of cover transmittal, 1 copy of waiver letter addressed to Steve Webb, 2 copies of A1.0, 2 copies of A2.0 and taken to Jason B
|
Routing - Erosion and Sediment | 6/6/2006 | | 6/7/2006 | | FAIL |
|
|
|
ESC plan failed. No ESC narrative or waiver request included in submittal. Notifed RP (Matt Nason ###-####).adh.
|
Routing - PLUMBING | 6/7/2006 | | 6/7/2006 | | FAIL |
|
|
|
all kitchen fixtures except hand sinks must be indirectly wasted. P-6 grease trap is listed on the fixture schedule, where is it on the plans, is there more than one. is waste piping to be provided to K-21. floor sink behind the ice maker must be 50% exposed.
|
Routing - PLANNING | 6/7/2006 | | 6/7/2006 | | PASS |
|
|
|
Approved per DRH06-00092
|
Routing - PUBLIC WORKS | 6/5/2006 | | 6/6/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/2/2006 | | DONE |
|
|
|
|
Application received | | | 5/30/2006 | | |
|
|
|
|