Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD06-01613
StatusFinaled
Name ROUSSE JERRIE I
Site Address 2023 N WESTGATE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
"11/7/2006 THIS PERMIT IS MODIFIED TO REFLECT THE ADDITION OF 150S.F. TO THE EXISTING ATTACHED GARAGE. 11/7/2006 pep" "NO CONTRACTOR REGISTRATION PROVIDED. APPLICANT CERTIFIES EXEMPTION PER IDAHO STATUTE 54-5205". This project is for a 798s.f. 2-story addition to an existing 1000s.f. 1-story single family dwelling. "The permit holder is responsible to comply with current wall bracing requirements as adopted by Boise City." R-1C ok per Sue Hansen. Separate electrical, plumbing, mechanical and ESC permits are required. All per the approved plans as marked REScheck and plan review notes. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  9/7/2018 DONE
BLD-Final12/7/200612/7/200612/7/2006PPASS
DetailsJim Sly
###-#### - tim
c/c issued
DOC - Permit Finaled12/7/200612/7/200612/7/2006PPASS
DetailsJim Sly
CHANGE ISSUED DATE  12/7/2006 DONE
Issue & PRINT permit  12/7/2006 DONE
BLD-Framing/Rough-in12/4/200612/5/200612/5/2006APART
DetailsJim Sly
###-#### - tim
Garage framing OK
BLD-Foundation11/13/200611/13/200611/13/2006PPASS
DetailsJim Sly
###-#### - tim Note: garage
Footing and wall....OK
Routing Walk-In (BLD)11/7/200611/7/200611/7/2006ADONE
11/7/2006 13:36:45 CTC - activity updated through activity BLDI252 from case BLD06-01613.
Routing Walk-In (BLD)11/7/200611/7/200611/7/2006PDONE
11/7/2006 13:37:24 CTC - activity updated through activity BLDI254 from case BLD06-01613.
Routing Walk-In (Zoning)11/7/200611/7/200611/7/2006 PASS
Update permit to add 6' to garage. Setbacks O.K. SAH
Case Summary (BLD)  11/7/2006  
Inspection Record Card- Bld  11/7/2006  
PLANS/APPL TAKEN TO FRONT DESK  11/7/2006 DONE
(F) Reprint permit  11/7/2006 DONE
BLD-Energy code compliance9/14/20069/14/20069/14/2006PPART
DetailsJim Sly
TIM; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Energy Ok......Need to check stairway at final !
BLD-Framing/Rough-in9/12/20069/12/20069/12/2006PFAIL
DetailsJim Sly
tim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Non Complying stairway.....Check headroom after corr completed. OK'd to rock 2nd flr ceiling Ok'd to insulate......
BLD-Foundation6/12/20066/12/20066/12/2006PPASS
DetailsJim Sly
tim or jerrie; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Mono pour foot and wall OK
BLD-Footing6/12/20066/12/20066/12/2006PPASS
DetailsJim Sly
tim or jerrie; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Mono foot and found OK
Routing Walk-In (BLD)6/6/20066/6/20066/6/2006ADONE
6/6/2006 14:22:20 PEP - activity updated through activity BLDA022 from case BLD06-01613.
Case Summary (BLD)  6/6/2006  
Inspection Record Card- Bld  6/6/2006  
PLANS/APPL TAKEN TO FRONT DESK  6/6/2006 DONE
Routing Walk-In (Zoning)6/5/20066/5/20066/5/2006ADONE
6/5/2006 11:41:11 SAH - activity updated through activity BLDI252 from case BLD06-01613.
Routing Walk-In (BLD)6/5/20066/5/20066/5/2006APASS
CHANGE STATUS TO (PND)  6/5/2006 DONE
need more information...REScheck and roof final plan.
Application received  6/5/2006