Permit Information
Permit NumberBLD06-01694
StatusFinaled
Name ORCHARDS DEVELOPMENT CO
Site Address 6855 W FAIRVIEW AVE
Project NameFairview Commercial Bldg B
Customer Number 
ePlanReviewNo
Description
(ORCHARDS DEVELOPMENT COMPANY - FAIRVIEW COMMERCIAL OFFICE BUILDING B) This building is NOT fire sprinklered. To create a 1,955 square foot office tenant space within a 4,461 square foot, one story building. Work is to include interior nonbearing walls, a restroom / shower room adaptable to the disabled, interior finishes, millwork, interior doors, interior windows, and suspended ceilings. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD9/22/20089/22/20081/27/2009 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 4/25/20088/11/2008 DONE
Permanent Occupancy  4/25/2008 DONE
FIRE-Final Inspection2/14/20082/15/20082/15/2008APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final2/14/20082/15/20082/15/2008PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 2/14/2008 at 4:36:33 PM. Contact: ###-####.
OK for Perm Occ.
CHANGE STATUS TO (ISS)  2/12/2008 DONE
Re-open per Tom Arcoraci
BLD-Aging Inspection10/31/200710/31/200710/31/2007 CANC
DetailsTom Arcoraci
DOC - Permit Expired10/31/200710/31/200710/31/2007PPASS
DetailsTom Arcoraci
BLD-Aging Inspection8/28/20078/28/20078/28/2007 NR
DetailsTom Arcoraci
FIRE-Final Inspection2/6/20072/6/20072/6/2007PFAIL
DetailsTroy Cobbley
Need suite number, fire extinguisher and the doors/hardware installed.
BLD-Aging Inspection1/12/20071/12/20071/12/2007 PASS
DetailsTom Arcoraci
BLD-Aging Inspection10/11/200610/11/200610/11/2006 PASS
DetailsTom Arcoraci
Issue PAID IN FULL permit  7/12/2006 DONE
Permit Ready to Issue  7/5/2006 DONE
Print Occupancy Form  7/5/2006 DONE
Telephone call  7/5/2006 DONE
Spoke with Matt and told him that permit is ready, fees and that we need GC information///7/5/06 @11:25am BAS
Plan assigned to (CJW)6/20/2006 7/3/2006 PASS
7/3/2006 14:40:05 CJW - activity updated through activity BLDA022 from case BLD06-01694.
Routing - FIRE6/29/2006 7/3/2006 PASS
Attached review comments to plans.
1st review completed  7/3/2006 PASS
Routing - PLAN CHECK7/3/2006 7/3/2006  
PLANS/APPL TAKEN TO FRONT DESK  7/3/2006 DONE
Routing - PLAN CHECK6/20/2006 6/29/2006 PASS
The IBC plan review was started on June 28 and was finished the next day. The drawings were approved with "red lines". See the plan review report.
Routing - PUBLIC WORKS6/20/2006 6/20/2006 PASS
Recd Pcfee & Taken To Pln CK  6/14/2006 DONE
Plans ACCEPTED BY PLAN TECH  6/14/2006  
Application received  6/13/2006