Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-01734
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 190 E BANNOCK ST
Project NameST LUKES
Customer Number 
ePlanReviewNo
Description
(RCE 3018 - Tim Austin) (ST LUKES - 4 WEST - CLINICAL ENGINEERING - 4TH FLR) To finish the interior of the 4th floor West Wing Shell & Core of 2,790 sq. ft., constructed under BLD04-02293 for first time tenant use as a Bio-Med support facility for the hospital. Work includes selective interior demolition; construct interior non-combustible, non-bearing walls to create (4) Bio-Med rooms, a Clean/Storage room, an office, reception area and accessible route to all areas of this tenant improvement build-out. To construct a 2-hour mechanical shaft, install a suspended ceiling grid system and complete electrical, mechanical, plumbing, sprinkler and alarm systems to meet tenant needs and comply with adopted codes and ordinances of Boise City. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD2/22/20072/22/20073/22/2007 DONE
Second Notice has not been responded to.
Telephone call  3/22/2007 DONE
call to dixie w/ cloverdale, she will check on the difference btwn GC fv and her fv and call tomorrow.
Second Notice BLD2/7/20072/7/20072/22/2007 DONE
First Notice has not been responded to.
First Notice 1/24/20072/7/2007 DONE
Permanent occupancy  1/24/2007 DONE
Perm. Occ. Cert. # 11403 issued 1-24-07 to St. Luke's RMC for the bio-med support facility
BLD-Final12/1/200612/4/200612/5/2006APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/1/2006 at 10:51:00 AM. ok for perm occ
BLD-Final12/4/200612/4/200612/4/2006PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/1/2006 at 10:51:00 AM. ok for perm occ
FIRE-Final Inspection12/1/200612/4/200612/4/2006APASS
DetailsForrest France
Fire life safety passed inspection.
Permanent Occupancy 12/4/200612/4/2006 DONE
Details
BLD-Wall cover10/18/200610/18/200610/18/2006ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/18/2006 at 7:00:24 AM. Contact: ###-####.
BLD-Wall cover9/13/20069/14/20069/14/2006APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/13/2006 at 1:47:08 PM. Contact: ###-####.
Issue & PRINT to be Invoiced  8/1/2006 DONE
Print Occupancy Form  7/28/2006 DONE
Telephone call  7/28/2006 DONE
tlk to jill ###-#### left ms for curtis that permit and fees are ready to be picked up
Override - Parcel Holds  7/28/2006  
Permit Ready to Issue  7/28/2006 DONE
Plan assigned to (DRS)6/20/2006 7/27/2006 PASS
7/27/2006 17:31:09 DRS - activity updated through activity BLDA022 from case BLD06-01734.
Routing - PLAN CHECK7/24/2006 7/27/2006 FAIL
Inserted resubmittal plans into original sets repalcing changed sheet. Reviewed letter of explanation from architect on exit hardware and use of exit door E100, opposite swing double doors between the new Clinical Engineering area and the existing exit corridor serving the 4th floor of hospital. This door is part of a 2-hour horizontal exit and needs proper door hardware in both direction to allow required exit access per code. Sent e-mail to Dana requesting further clarification and correction.
Plan resubmittals requested  7/27/2006 DONE
Need further clarification & correction of proposed door hardware on existing doors E100. Copy of needed information e-mailed to Dana at Insight architects.
Plan resubmittals received  7/27/2006  
Received 1 transmittal, & 1 letter taken to Dan S.
Routing - PLAN CHECK7/27/2006 7/27/2006 PASS
Received clarification from Dana Kaufman concerning proper exit door hardware and its function for Door E100. Routing to permit desk to issue.
PLANS/APPL TAKEN TO FRONT DESK  7/27/2006 PASS
Plan resubmittals received  7/26/2006 DONE
Recedived 1 transmittal ,2 letters , & 2 copys of sheets A0.1,A2.0,A5.0,P2.1 taken to Dan S.
1st review completed  7/24/2006 FAIL
Failed plan check.
Routing - FIRE7/18/2006 7/24/2006 PASS
Attached review comments to plans.
Plan resubmittals requested  7/19/2006 DONE
Copy of plan review conditions to architect for response.
Override - Parcel Holds  7/19/2006  
Routing - PLAN CHECK6/26/2006 7/18/2006 FAIL
Copy of plan review e-mailed and faxed to Dana Kaufman. Routing to fire code analyst.
Routing - PLUMBING6/21/2006 6/26/2006 PASS
per plan and 2003 UPC
no med gas shown.
Routing - PUBLIC WORKS6/20/2006 6/21/2006 PASS
Plans ACCEPTED BY PLAN TECH  6/19/2006  
Recd Pcfee & Taken To Pln CK  6/19/2006  
Application received  6/15/2006