Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/8/2006 | 12/27/2006 | | DONE |
|
|
|
|
BLD-Final | 11/7/2006 | 11/8/2006 | 11/8/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 4:25:27 PM. Contact: ###-####. ok for perm occ
|
BLD-Final | 11/6/2006 | 11/7/2006 | 11/8/2006 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/6/2006 at 3:54:56 PM. Contact: ###-####.
|
Permanent Occupancy | | 11/8/2006 | 11/8/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/8/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11289 issued 11-8-06 to the Idaho State Dept. of Finance on the 2nd floor of the MK Plaza Bldg.
|
FIRE-Final Inspection | 11/6/2006 | 11/7/2006 | 11/7/2006 | A | PASS |
Forrest France
|
|
|
Items on c/n have been completed, fire life safety inspection passed.
|
FIRE-Final Inspection | 11/6/2006 | 11/6/2006 | 11/7/2006 | P | FAIL |
Forrest France
|
|
|
Need to repair door hardware and relocate exit signage.
|
BLD-Other | 10/13/2006 | 10/16/2006 | 10/16/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/13/2006 at 3:12:34 PM. Contact: ###-####. ok to drop in feild tiles
|
BLD-Framing/Rough-in | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/15/2006 at 3:09:43 PM. Contact: ###-####. ok to sheet rock
|
Issue PAID IN FULL permit | | | 8/2/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/31/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/31/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2006 | | DONE |
|
|
|
tlk to john maulin ###-#### that permit and fees are ready to be picked up but needs GC and RCE #
|
Permit Ready to Issue | | | 7/31/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/24/2006 | | 7/29/2006 | | PASS |
|
|
|
Inserted resubmittals into original plans. Taking plans to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2006 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 6/27/2006 | | 7/29/2006 | | PASS |
|
|
|
7/29/2006 13:49:42 DRS - activity updated through activity BLDA022 from case BLD06-01798.
|
Plan resubmittals received | | | 7/28/2006 | | |
|
|
|
Received 1 copy of cover transmittal, 1 copy of plan review response letter, 1 copy of letter from American resurgens Management Corp, 2 copies of the following sheets--A0.1, A2.1, A10.1, MP1.1, E2.1E3.0, E3.12, E4.0 and taken to Dan Stuart
|
1st review completed | | | 7/24/2006 | | FAIL |
|
|
|
Failed Plan Check.
|
Routing - FIRE | 7/20/2006 | | 7/24/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan resubmittals requested | | | 7/20/2006 | | DONE |
|
|
|
Fax and e-mail of plan review sent to John Maulin.
|
Routing - PLAN CHECK | 6/27/2006 | | 7/20/2006 | | FAIL |
|
|
|
Copy of plan review e-mailed and faxed to John Maulin, CSHQA. Routing to fire code analyst for review.
|
Routing - PUBLIC WORKS | 6/27/2006 | | 6/27/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/23/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/23/2006 | | |
|
|
|
|
Application received | | | 6/22/2006 | | |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | | | |
|
|
|
Second Notice has not been responded to.
|