Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD06-01818
StatusFinaled
Name PETRA INC
Site Address 2768 S FEATHERLY WAY
Project NameSheffield Building #2 -Shell
Customer Number 
ePlanReviewNo
Description
(Sheffield Building #2 - Shell Only) To build a new 7,150 square foot, one story office warehouse shell building and related site improvements. This building is constructed of concrete slab floors, concrete masonry exterior walls and wood trussed roof system. this is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  7/28/2008 DONE
Second Notice BLD4/18/20074/18/20074/30/2007 DONE
First Notice has not been responded to.
First Notice4/2/20074/2/20074/18/2007 DONE
DetailsMike Jordan
BLD-Final4/2/20074/2/20074/2/2007PPASS
DetailsMike Jordan
clint; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
DOC - Permit Finaled4/2/20074/2/20074/2/2007PPASS
DetailsMike Jordan
Final ok. Letter of compliance issued for shell and core.
Code Occupancy Approval4/2/20074/2/20074/2/2007PPASS
DetailsScott M.Brown
ALL IN AS REQUIRED OK FOR FINAL
BLD-Final3/29/20073/30/20073/30/2007ANR
DetailsMike Jordan
clint; Phone #: ###-#### Internet Inspection Request from: Victoria Beal. Needs code enforcement.
FIRE-Final Inspection3/23/20073/26/20073/26/2007APASS
DetailsTroy Cobbley
life safety passed.
FIRE-Final Inspection3/20/20073/20/20073/20/2007PFAIL
DetailsTroy Cobbley
Inspection was for a conference. I went over life safety items with the superintendant.
BLD-Conference3/19/20073/19/20073/19/2007PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/19/2007 at 9:53:12 AM. Contact: ###-####.
BLD-Framing/Rough-in2/26/20072/26/20072/26/2007PPASS
DetailsMike Jordan
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Repair to girder truss ok.
BLD-Framing/Rough-in2/19/20072/20/20072/20/2007APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/19/2007 at 9:05:51 AM. Contact: ###-####. Roof framing and draft stops.
BLD-Foundation9/26/20069/26/20069/26/2006PPASS
DetailsMike Jordan
greg - as early as possible-concrete at 2; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Footing9/21/20069/21/20069/21/2006PPART
DetailsMike Jordan
greg ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. majority of concrete placed when on site. No special insp. no conc. vibrator on site. Noted to contractor that if no special insp. is required that conc. is not to be placed until city insp. has approved footings. Footings that were inspected were as approved plans.
(F) Reprint permit  8/24/2006  
Issue PAID IN FULL permit  8/23/2006 DONE
Inspection Record Card- Bld  8/8/2006  
Permit Ready to Issue  8/8/2006 DONE
Telephone call  8/8/2006 DONE
left mess for matt rhees at ###-#### permit is ready & need achd
Plan Reviewer's activity  8/7/2006 PASS
Reviewed and approved revised structural calculations and drawings. JCM
PLANS/APPL TAKEN TO FRONT DESK  8/7/2006 DONE
Routing - PLAN CHECK7/25/2006 8/7/2006 PASS
Plan assigned to (JCM)6/26/2006 8/7/2006 PASS
8/7/2006 11:51:36 JCM - activity updated through activity BLDA022 from case BLD06-01818.
Plan resubmittals received  8/3/2006  
Received transmittal cover, 2pg. transmittal letter, 3 copies of Supplemental Calculations, 3 copes of pages S4.0 & S5.0; taken to John Menard
1st review completed  7/25/2006 FAIL
Failed planning and plan check.
Routing - FIRE7/21/2006 7/25/2006 PASS
Attached review comments to plans.
Routing - PLAN CHECK7/19/2006 7/21/2006 PASS
Routing - PLANNING7/17/2006 7/19/2006 PASS
Meets the ordinance requirements for landscaping. All accessible spaces must comply with ADA requirements.
Routing - PLAN CHECK7/7/2006 7/17/2006  
John M
Plan resubmittals requested  7/11/2006 DONE
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL6/27/2006 7/10/2006 FAIL
Received letter from consulting structural engineer requesting revisions. JCM
Routing - PLANNING7/6/2006 7/7/2006 FAIL
The applicant has not complied with the requirements of DRH06-00144. The applicant will be required to submit a revised site plan incorporating the conditions of approval and will be required to submit a landscape plan to be reviewed and approved by DR staff.
Routing - PLUMBING6/30/2006 7/6/2006 PASS
per plans and 2003 upc
Routing - PUBLIC WORKS6/27/2006 6/30/2006 PASS
Routing - Erosion and Sediment6/30/2006 6/30/2006 PASS
ESC plan approved with attached conditions.
Routing - Addressing6/28/2006 6/28/2006 PASS
Routing - PLANNING Land Div6/27/2006 6/27/2006 PASS
parcel is a platted lot.
Recd Pcfee & Taken To Pln CK  6/27/2006 DONE
Plans ACCEPTED BY PLAN TECH  6/27/2006  
Plan routing begun/NEW & ADDTN  6/27/2006  
Application received  6/23/2006