Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD06-01887
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 1555 W SHORELINE DR
Project NameSHORELINE OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
(AGRI BEEF - SHORELINE OFFICE BLDG - 3RD FLR) To remodel a 9,656 sq.ft. office space located on the 3rd floor per approved plans. Work to include, construction of interior partitions to create a new test kitchen, breakroom, work room, reception area, and two conference rooms, installation of a type one hood system, to upgrade restrooms for accessiblity compliance, this building is fully fire sprinklered any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. Rmh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  12/17/2007 DONE
Letter of Compliance issued 12-17-07
BLD-Final12/12/200712/12/200712/13/2007PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/12/2007 at 11:02:54 AM. Contact: ###-####. ok for perm occ
FIRE-Final Inspection12/11/200712/12/200712/12/2007APASS
DetailsForrest France
Fire life safety is satisfactory.
FIRE-Final Inspection9/20/20079/21/20079/21/2007PCANC
DetailsForrest France
Overbooked.
Print Occupancy Form  5/1/2007 DONE
FIRE-Final Inspection1/17/20071/17/20071/17/2007PFAIL
DetailsTroy Cobbley
I gave Don with Russell Corp. permission to use the phase one area of the third floor. See the building approved plans for the exact location marked and signed by me that was inspected. The items remaining include providing an air balance report for the hood and a K class extinguisher. Only the portion of the phase one area on the third floor alarm was tested. The other area was not complete. The lobby areas of the first and second floor fire alarm was tested. This includes the new facp panel, NAC panel, phone lines and elevator recall. See the approved fire alarm prints for devices marked "ok" that have been tested. Signals have been verified as well. Need 120volt monitoring of the elevator power and the correct orfice in the inspectors test connection. Asbuilts will be required to be submitted to the city prior to final.
FIRE-Conference12/20/200612/21/200612/21/2006ADONE
DetailsForrest France
On site confrence to discuss project schedule and phased completion of tenant permits.
BLD-Conference12/19/200612/20/200612/20/2006APASS
DetailsDave Hannah
Don; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Conference11/17/200611/20/200611/20/2006APART
DetailsDave Hannah
Don, ceiling inspection please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to drop in tiles after elec oks
BLD-Framing/Rough-in10/13/200610/16/200610/16/2006PPASS
DetailsDave Hannah
Don; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Issue PAID IN FULL permit  8/31/2006 DONE
Telephone call  8/3/2006  
lft ms with secretary for wes steele ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  8/3/2006 DONE
1st review completed  8/2/2006 PASS
Routing - PLAN CHECK8/2/2006 8/2/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/2/2006 DONE
Print Occupancy Form  8/2/2006 DONE
Print Occupancy Form  8/2/2006  
Plan assigned to (R_H)7/3/2006 8/2/2006 PASS
8/2/2006 13:42:17 RMH - activity updated through activity BLDA022 from case BLD06-01887.
Routing - FIRE7/31/2006 8/2/2006 PASS
Attached review comments to plans.
Case Summary (BLD)  7/31/2006 DONE
Routing - PLAN CHECK7/7/2006 7/31/2006 PASS
No corrections by building department review routed plans to fire on 7/31/06, permit pending fire departments review.
Routing - PLUMBING7/5/2006 7/7/2006 PASS
per plans and 2003 upc
Routing - PUBLIC WORKS7/3/2006 7/5/2006 PASS
Routing - Addressing7/3/2006 7/3/2006 PASS
Application received  6/30/2006  
Recd Pcfee & Taken To Pln CK  6/30/2006  
Plans ACCEPTED BY PLAN TECH  6/30/2006