BLD-Final | 2/21/2007 | 2/22/2007 | 2/22/2007 | A | PASS |
Jim Sly
|
|
|
please call 30 min prior//Rob ###-#### C/C issued
|
DOC - Permit Finaled | 2/22/2007 | 2/22/2007 | 2/22/2007 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 10/12/2006 | 10/12/2006 | 10/12/2006 | P | PASS |
Jim Sly
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Framing/Rough-in | 10/6/2006 | 10/9/2006 | 10/9/2006 | A | PASS |
Jim Sly
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles N 5mi E. Edna L Alliance L Ripl.....
|
BLD-Foundation | 8/4/2006 | 8/7/2006 | 8/7/2006 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/4/2006 at 8:08:27 AM. Contact: ###-####.
|
BLD-Footing | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/4/2006 at 8:07:33 AM. Contact: ###-####.
|
Routing - PLAN CHECK | 7/7/2006 | | 7/18/2006 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 7/10/2006 | | 7/18/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/18/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/18/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/18/2006 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 6/30/2006 | 6/30/2006 | 7/10/2006 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/6/2006 | | 7/7/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 6/30/2006 | | 7/6/2006 | | PASS |
|
|
|
Does not meet setbacks. Left Rob a message on 7/3/06 SH. Rob provided letter re: PUD setbacks in this sub. Discussed with Scott and approved 7/6/06
|
Routing - Addressing | 6/30/2006 | | 6/30/2006 | | PASS |
|
|
|
|
Application received | | | 6/30/2006 | | |
|
|
|
|