Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD06-01921
StatusFinaled
Name DAVE'S CONSTRUCTION
Site Address 6824 S EISENMAN RD
Project NameFACTORY OUTLET BLDG #2
Customer Number 
ePlanReviewNo
Description
(RCE-715) (FACTORY BRAND SHOES - BOISE FACTORY OUTLET - BLDG #2) This building is fire sprinklered for building area increase and for fire area. To remodel an existing 4,400 square foot retail sales tenant space. Work is to include an interior nonbearing wall and display fixtures. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/7/200612/7/200612/8/2006PPASS
DetailsJim Storey
von; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Final10/19/200610/20/200610/20/2006PNR
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/19/2006 at 8:12:42 AM. Contact: ###-####. pending plm.
FIRE-Final Inspection10/19/200610/19/200610/19/2006PPASS
DetailsForrest France
Fire life safety is satisfactory, the provided PFE to be attatched to the new wall when paint is completed per contractor.
BLD-Framing/Rough-in10/17/200610/17/200610/17/2006PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/17/2006 at 8:09:39 AM. Contact: ###-####.
Issue PAID IN FULL permit  10/13/2006 DONE
Telephone call  9/18/2006 DONE
left mess for aaron jagiel at ###-#### that permit is ready & need gc. & rce info
Print Occupancy Form  8/15/2006 DONE
Telephone call  8/15/2006 DONE
tlk to aaron ###-#### 585 that permit and fees are ready to be picked up but needs GC and RCE #
Permit Ready to Issue  8/15/2006 DONE
Routing - PUBLIC WORKS8/12/2006 8/14/2006 PASS
Sent back for fee adjustment
PLANS/APPL TAKEN TO FRONT DESK  8/14/2006 DONE
Plan assigned to (CJW)7/10/2006 8/14/2006 PASS
8/14/2006 13:57:39 CJW - activity updated through activity BLDA022 from case BLD06-01921.
Routing - PLAN CHECK7/24/2006 8/12/2006 PASS
Approved after resubmittal review.
Plan resubmittals received  8/10/2006  
Received 1 copy of cover transmittal, response letter, cut sheet for delta faucet, 2 copies of the following sheets--A1, A2, A3, A4, A4.1, A5 and taken to Carl Westfall
Routing - FIRE7/19/2006 7/24/2006 PASS
Attached review comments to plans.
1st review completed  7/24/2006 FAIL
Failed Plan check.
Routing - PLAN CHECK7/11/2006 7/19/2006 FAIL
The IBC plan review was started on July 18, 2006 and was finished the next day. Revised drawings were required. See the plan review report.
Routing - PUBLIC WORKS7/10/2006 7/11/2006 PASS
Application received  7/5/2006  
Plans ACCEPTED BY PLAN TECH  7/5/2006  
Recd Pcfee & Taken To Pln CK  7/5/2006