Second Notice BLD | 4/9/2007 | 4/9/2007 | 4/23/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/29/2007 | 4/9/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/29/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/29/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11506 issued 3-29-07 to Idaho Association of Realtors.
|
BLD-Final | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PASS |
Dave Hannah
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for perm occ
|
Permanent Occupancy | | 1/30/2007 | 1/30/2007 | | DONE |
|
|
|
|
BLD-Final | 1/11/2007 | 1/12/2007 | 1/12/2007 | P | PART |
Dave Hannah
|
|
|
matt - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for temp occ need to finish installing glassing and divider wall in conf rm
|
FIRE-Final Inspection | 1/12/2007 | 1/12/2007 | 1/12/2007 | P | PASS |
Forrest France
|
|
|
Verified necessary corrections, fire life safety finaled.
|
FIRE-Final Inspection | 1/11/2007 | 1/12/2007 | 1/12/2007 | A | FAIL |
Forrest France
|
|
|
Missing building address numbers at the front entrance, two exit signs at the training room are not installed as red lined on approved plans, one emergency light is missing in the confrence room, need max. occupant load signs in the training rooms per review notes.
|
BLD-Other | 1/10/2007 | 1/10/2007 | 1/10/2007 | P | PART |
Dave Hannah
|
|
|
jack Note: ceiling ins is possible after 2:00 pm; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover
|
BLD-Other | 1/4/2007 | 1/4/2007 | 1/5/2007 | P | FAIL |
Dave Hannah
|
|
|
###-#### - jack Note: ceiling grid needs to patch fire proofing and add a wire to mec fixtures
|
FIRE-Sprinkler Rough-in | 12/29/2006 | 12/29/2006 | 12/29/2006 | P | PART |
Troy Cobbley
|
|
|
See approved plans for areas where piping is ok to cover. I found one pendant in front of the restrooms overspaced and four pendants overspaced off of the accordian door in the training room. See approved plans these locations.
|
BLD-Other | 12/20/2006 | 12/21/2006 | 12/21/2006 | A | PART |
Dave Hannah
|
|
|
Jack Note: sup ceiling insp; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett ok to cover front area after all other trades ok
|
BLD-Framing/Rough-in | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PASS |
Dave Hannah
|
|
|
matt ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to cover ext walls insulation ok fireproofing also ok
|
BLD-Framing/Rough-in | 11/22/2006 | 11/22/2006 | 11/24/2006 | P | PART |
Dave Hannah
|
|
|
loressa; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to insulate ext wall ok to cover int walls
|
BLD-Framing/Rough-in | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/21/2006 at 2:15:21 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 9/19/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/18/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/18/2006 | | DONE |
|
|
|
tlk to alex lebear ###-#### that permit and fees are ready to be picked up but needs RCE/GC
|
Permit Ready to Issue | | | 9/18/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 9/14/2006 | | 9/15/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 9/15/2006 | | |
|
|
|
Received transmittal letter, 1pg. response, 1pg. typical support section, 2 copies of pg EN1.0; taken to Carl Westfall
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/18/2006 | | 9/15/2006 | | PASS |
|
|
|
9/15/2006 13:48:26 CJW - activity updated through activity BLDA022 from case BLD06-01951.
|
Routing - FIRE | 9/13/2006 | | 9/14/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 8/1/2006 | | 9/13/2006 | | FAIL |
|
|
|
(8-24-06) Resubmittal review completed. Not all items were resolved. E-mailed a copy of the report to the Architect. See the revised plan review report. (9-13-06) Reviewed resubmitted drawings. Called the Architect's representative. Two items not resolved: economizers and wood.
|
Plan resubmittals received | | | 9/11/2006 | | |
|
|
|
Received transmittal sheet, 1pg. response from Hummel Architects, 2 copies of Structural Design Calculations, 2 copies of pages EN1.0 & M1.0; taken to Carl Westfall
|
Plan resubmittals received | | | 8/22/2006 | | |
|
|
|
Received 1 copy of 2 page response letter, 1 copy of split system a/c schedule, 1 copy of heating & cooling load summary, 1 copy of detailed heating & cooling load breakdown, 2 copies of the following sheets--A1.0, A2.0, A3.0, A3.1, A5.0 and taken to Carl Westfall
|
Routing - FIRE | 7/29/2006 | | 8/1/2006 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Attached review comments to plans.
|
1st review completed | | | 8/1/2006 | | FAIL |
|
|
|
Failed plan Check and Fire.
|
Routing - PLAN CHECK | 7/19/2006 | | 7/29/2006 | | FAIL |
|
|
|
The IBC plan review was started on July 28 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 7/18/2006 | | 7/19/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/10/2006 | | |
|
|
|
|
Application received | | | 7/7/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/7/2006 | | |
|
|
|
|