Third Notice BLD | 10/30/2007 | 10/30/2007 | 11/6/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/1/2007 | 10/1/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/4/2007 | 10/1/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | 9/4/2007 | 9/4/2007 | 9/4/2007 | P | PASS |
Michael Garner
|
|
|
follow up inspection complete - I noted that the trash enclosure has been completed - this was the last item to be completed - PASS
|
Permanent Occupancy | | | 9/4/2007 | | DONE |
|
|
|
|
BLD-Final | 8/31/2007 | 8/31/2007 | 8/31/2007 | P | PASS |
Dave Hannah
|
|
|
derrick; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt ok for perm occ
|
BLD-Final | 8/29/2007 | 8/29/2007 | 8/30/2007 | P | NR |
Dave Hannah
|
|
|
Derek; Phone #: ###-#### Internet Inspection Request from: Hattie James everything ok but needs to get code enforcements sign off and fix openning in gaurd rail at risers
|
Code Occupancy Approval Temp | 8/29/2007 | 8/29/2007 | 8/29/2007 | P | DONE |
Michael Garner
|
|
|
SITE INSPECTION COMPLETE - I OBSERVED SUBSTANTIAL COMPLIANCE WITH APPROVED PLANS AND PERMITS - TRASH ENCLOSURE IS NOT COMPLETE - DEREK, THE CONTRACTOR, TOLD ME HE IS HAVING A DISCUSSION WITH THE OWNERS REGARDING THE SIZE OF TEH ENCLOSURE - I AGREED TO SIGN THE TEMPORARY, SCHEDULED A FOLLOW UP INSPECTION FOR 11SEPT2007 TO ENSURE COMPLIANCE
|
FIRE-Final Inspection | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
FIRE-Final Inspection | 8/24/2007 | 8/24/2007 | 8/27/2007 | P | DEFR |
Forrest France
|
|
|
###-#### - derick
|
PubWorks Occupancy Approval | 8/24/2007 | 8/24/2007 | 8/24/2007 | | DONE |
|
|
|
|
Override - People Holds | | | 8/24/2007 | | |
|
|
|
|
BLD-Framing/Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 | A | PASS |
Dave Hannah
|
|
|
derick Phone #: ###-#### Note: please call before 1/2 hr prior to inspections
|
BLD-Framing/Rough-in | 6/25/2007 | 6/25/2007 | 6/25/2007 | P | PART |
Dave Hannah
|
|
|
derick Note: please call 1/2 hr prior to inspection Phone #: ###-#### ok to cover ceilings in soffit areas
|
BLD-Conference | 6/21/2007 | 6/21/2007 | 6/21/2007 | A | PASS |
Dave Hannah
|
|
|
dixie called in to set this up
|
BLD-Other | 6/7/2007 | 6/7/2007 | 6/7/2007 | P | PART |
Dave Hannah
|
|
|
derick Note: nailing; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles shear ok to cover ext
|
BLD-Other | 5/30/2007 | 5/31/2007 | 5/31/2007 | P | PART |
Dave Hannah
|
|
|
derrick - nailing; Phone #: ###-#### Internet Inspection Request from: Victoria Beall shear ok
|
BLD-Footing | 4/30/2007 | 4/30/2007 | 4/30/2007 | P | PASS |
Dave Hannah
|
|
|
Derrick; Phone #: ###-#### Internet Inspection Request from: Andrea Whiteman
|
BLD-Foundation | 4/18/2007 | 4/19/2007 | 4/19/2007 | A | PASS |
Dave Hannah
|
|
|
darrick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Footing | 4/13/2007 | 4/16/2007 | 4/17/2007 | A | PART |
Dave Hannah
|
|
|
Derek; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
Issue PAID IN FULL permit | | | 3/28/2007 | | |
|
|
|
|
Ready Permit EXTENDED | | | 2/26/2007 | | DONE |
|
|
|
One-time 108 day permit application extension to July 9, 2007. Original expiration date January 8, 2007.
|
Telephone call | | | 2/15/2007 | | DONE |
|
|
|
derrick come in to the office to see if he could file for an extension. told him to write a letter to jenifer g.
|
Telephone call | | | 2/13/2007 | | DONE |
|
|
|
tlk to brian cooper ###-#### that permit and fees are ready to be picked up-said that they may not be doing job????will let me know.
|
Print Occupancy Form | | | 11/29/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2006 | | DONE |
|
|
|
tlk to brian cooper ###-#### that permit and fees are ready to be picked up & need achd
|
Permit Ready to Issue | | | 11/29/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/17/2006 | | 11/28/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2006 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/28/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/28/2006 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 7/17/2006 | | 11/28/2006 | | PASS |
|
|
|
11/28/2006 15:21:20 M_P - activity updated through activity BLDA022 from case BLD06-02000.
|
Plan resubmittals received | | | 11/17/2006 | | |
|
|
|
Received 1 copy o f cover letter, 2 copies of cantilevered beam at balcony calcs, 2 copies of the following sheets--A3.0, A4.0, A5.0, A7.0, A8.0, M-1 and taken to Mike Phillips
|
Routing - PLAN CHECK | 8/23/2006 | | 10/17/2006 | | FAIL |
|
|
|
Second review failed, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 10/12/2006 | | |
|
|
|
Received 1- 2 page cover letter, a copy of a letter from Brian Murphy regarding grading & drainage, 2 copies of mechanical calcs, 2 copies of Structural Design booklets, 2 copies of the following sheets--C100, A0, A2.0, A3.0, A4.0, A5.0, A6.0, A7.0, A8.0, A10.0, M-1, M-2, E-1, E-2 and taken to Mike Phillips
|
1st review completed | | | 8/22/2006 | | FAIL |
|
|
|
Failed Planning & Plan Check.
|
Routing - PLAN CHECK | 8/22/2006 | | 8/22/2006 | | |
|
|
|
Routing to Planning
|
Routing - PLANNING | 8/22/2006 | | 8/22/2006 | | PASS |
|
|
|
Approved per DRH06-00115.
|
Routing - FIRE | 8/18/2006 | | 8/22/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 7/28/2006 | | 8/18/2006 | | FAIL |
|
|
|
Plan review completed, sent correction report to the architect requesting additional informaiton to be submitted for further review prior to issuing permit.
|
Case Summary (BLD) | | | 8/18/2006 | | |
|
|
|
|
Routing - PLUMBING | 7/24/2006 | | 7/28/2006 | | PASS |
|
|
|
min. 1" cold water supply to each unit, per plans and 2003 upc.
|
Routing - PLANNING | 7/28/2006 | | 7/28/2006 | | FAIL |
|
|
|
DRH06-00115--Greg Johnson
Failed: applicant has not met all conditions and has not submitted all revised drawings.
|
Routing - Erosion and Sediment | 7/20/2006 | | 7/24/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 7/17/2006 | | 7/20/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/17/2006 | | 7/17/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/14/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/14/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/13/2006 | | DONE |
|
|
|
|
Application received | | | 7/12/2006 | | |
|
|
|
|