Permit Information
Permit NumberBLD06-02018
StatusFinaled
Name INTEGRATED BUILDING GROUP
Site Address 1417 S EUCLID AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
"CONTRACTOR SCOTT PATTEN REGISTRATION NUMBER RCE-3298" To construct a 1555sq.ft. Two story single family dwelling (976sq.ft. First floor / 579sq.ft. Second floor) with a 77sq.ft. Covered front porch, a 77sq.ft. second floor covered deck, a 11sq.ft. Covered rear porch, and a 437sq.ft. Detached garage per approved plans, all red-lining, and Plan review report. THE PERMIT HOLDER is responsible to comply with current wall bracing requirements adopted by Boise city. R-2D Zoning district, building setbacks, and DRH06-00252 per Greg Johnson with Planning and Zoning. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/16/200611/16/200611/16/2006PPASS
DetailsJim Storey
roy ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
DOC - Permit Finaled11/16/200611/16/200611/16/2006PPASS
DetailsJim Storey
BLD-Final11/6/200611/7/200611/7/2006ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 11/6/2006 at 1:59:32 PM. Contact: ###-####.need zoning sign off 1st,, conf. walk through on final,, front landing, deck waterprooof, roof finish, backfill, etc.. only did a walk on 1417
BLD-Energy code compliance9/8/20069/11/20069/11/2006PPASS
DetailsMike Jordan
roy; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. All framing issues have been resolved. Airseal ok. insul ok. ok to cover.
BLD-Framing/Rough-in9/6/20069/7/20069/7/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/6/2006 at 11:19:46 AM. Contact: ###-####. stud shoes/ beam for 2nd floor roof/ truss bracing/ soffit protection 7 oc.spot check ec seal./ sd at bottom of stair.
BLD-Foundation8/22/20068/22/20068/22/2006APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/22/2006 at 6:51:53 AM. Contact: ###-####.
BLD-Foundation8/18/20068/21/20068/21/2006APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/18/2006 at 9:33:26 AM. Contact: ###-####.
BLD-Footing8/21/20068/21/20068/21/2006APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/21/2006 at 6:32:47 AM. Contact: ###-####.
BLD-Footing8/18/20068/18/20068/18/2006PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/18/2006 at 9:33:00 AM. Contact: ###-####.
BLD-Foundation8/9/20068/10/20068/10/2006PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/9/2006 at 8:53:22 AM. Contact: ###-####.
BLD-Footing8/9/20068/9/20068/9/2006PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/9/2006 at 8:52:56 AM. Contact: ###-####.
Telephone call  8/4/2006 DONE
spoke to scott@###-####/told permit was ready, lot & block, and fees
Permit Ready to Issue  8/4/2006 DONE
Issue PAID IN FULL permit  8/4/2006 DONE
Plan assigned to (SRZ)8/1/20068/1/20068/3/2006 PASS
8/3/2006 09:32:07 SRZ - activity updated through activity BLDA022 from case BLD06-02018.
Routing - PLAN CHECK7/24/2006 8/3/2006 PASS
Case Summary (BLD)  8/3/2006  
PLANS/APPL TAKEN TO FRONT DESK  8/3/2006 DONE
Inspection Record Card- Bld  8/3/2006 DONE
Plan assigned to (SAM)7/14/20067/14/20068/1/2006 DONE
Plan Reviewer's activity  8/1/2006 PASS
Plans do not meet Plan submittal requirements. Recived new plans with corrections. (SRZ)
Plan resubmittals requested  8/1/2006  
Telephone call  8/1/2006 DONE
Called Applicant and requested resubmittals. (SRZ)
Routing - PLANNING7/21/2006 7/24/2006 PASS
Approved per DRH06-02018
Routing - PUBLIC WORKS7/24/2006 7/24/2006 PASS
Routing - PLANNING Land Div7/21/2006 7/21/2006 PASS
Application received  7/14/2006  
Routing - Addressing7/14/2006 7/14/2006 PASS