Third Notice BLD | 4/18/2007 | 4/18/2007 | 4/30/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 4/5/2007 | 4/5/2007 | 4/18/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/22/2007 | 4/5/2007 | | DONE |
|
|
|
|
BLD-Final | 3/21/2007 | 3/22/2007 | 3/22/2007 | P | PASS |
Tony Young
|
|
|
Ryan; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok for full occ.
|
Permanent Occupancy | | 3/22/2007 | 3/22/2007 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/22/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11495 issued 3-22-07 to Design West Furniture.
|
Code Occupancy Approval | | | 3/14/2007 | | PASS |
|
|
|
ALL LANDSCAPING FINALED PER JOE VENNEMAN
|
BLD-Final | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | PART |
Tony Young
|
|
|
Ryan; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ.,, full occ. ok after all trades are done
|
Temporary occupancy | | | 2/2/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5531 issued 2-2-07 to Design West Furniture.
|
BLD-Final | 1/31/2007 | 2/1/2007 | 2/1/2007 | P | NR |
Tony Young
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
FIRE-Final Inspection | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
Code Occupancy Approval Temp | 1/26/2007 | 1/26/2007 | 1/26/2007 | P | DONE |
Michael Garner
|
|
|
site inspection complete - officer met with Ryan, the contractor - officer explained what code enforcement does - what I looked for - officer signed for a temporary - more than 60% of the work is complete - the landscapers are the business next door - no bonding required - officer will re-inspect in 2 2 weeks
|
COD-Stop Work/Reinspection Fee | 1/26/2007 | 1/26/2007 | 1/26/2007 | P | CANC |
Michael Garner
|
|
|
|
BLD-Final | 1/17/2007 | 1/18/2007 | 1/18/2007 | P | NR |
Tony Young
|
|
|
ron Note: late as possible; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles conf only,, need trades, etc
|
BLD-Conference | 12/12/2006 | 12/13/2006 | 12/13/2006 | A | PASS |
Tony Young
|
|
|
Ryan; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt fire riser room ok to cover,, will include the electrical room also
|
BLD-Energy code compliance | 12/6/2006 | 12/6/2006 | 12/6/2006 | P | PASS |
Tom Arcoraci
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 12/6/2006 | 12/6/2006 | 12/6/2006 | P | PART |
Tom Arcoraci
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Cathy Chilesok to cover ext walls int ok after rough ins riser room has elec panel in wall must resolve
|
BLD-Foundation | 9/27/2006 | 9/28/2006 | 9/28/2006 | A | PART |
Jim Sly
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Foundation wall OK pending MTI special insp, tests and approvals
|
BLD-Framing/Rough-in | 9/26/2006 | 9/26/2006 | 9/26/2006 | P | CANC |
Tom Arcoraci
|
|
|
ryan - rebar - concrete at 2:30; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Footing | 9/26/2006 | 9/26/2006 | 9/26/2006 | P | PASS |
Tom Arcoraci
|
|
|
ryan - rebar - concrete at 2:30; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley mti spec on site
|
(F) Reprint permit | | | 9/15/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/14/2006 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/12/2006 | | 9/13/2006 | | PASS |
|
|
|
Called Action Courrier for pick up @ 10:00 on 9/12/06 BAS
|
Case Summary (BLD) | | | 9/13/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/13/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/13/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2006 | | DONE |
|
|
|
called ###-#### and told Ron Imel that permit is ready, fees, and need ACHD
|
Plan assigned to (MLO) | 8/10/2006 | | 9/13/2006 | | PASS |
|
|
|
9/13/2006 15:50:04 MLO - activity updated through activity BLDA022 from case BLD06-02023.
|
Routing - FIRE | 9/8/2006 | | 9/11/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PUBLIC WORKS | 9/1/2006 | | 9/7/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/6/2006 | | |
|
|
|
received letter from hansen-rice const & "2" sheets A0.00 for overall site plans-plans taken to mike otto
|
Plan resubmittals received | | | 9/1/2006 | | DONE |
|
|
|
Received transmittal letter, 3 response,3 structural calcs & 3 copys of sheets S0.1,S1.1,S2.1 taken to Mike Otto
|
1st review completed | | | 8/31/2006 | | FAIL |
|
|
|
Failed Structural and Fire.
|
Routing - FIRE | 8/25/2006 | | 8/31/2006 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Attached review comments to plans.
|
Routing - PLAN CHECK | 8/16/2006 | | 8/25/2006 | | PASS |
|
|
|
Route to MLO for review.
|
Plan resubmittals received | | | 8/3/2006 | | |
|
|
|
Received transmittal sheet, and 3 copies of the following: 1pg. response, Supplemental Structural Design Calculations, S0.1, S1.1, S1.2, S2.1, S2.2, S2.3; takent to John Menard
|
Routing - PLANNING | 8/1/2006 | | 8/2/2006 | | PASS |
|
|
|
Approved per DRH05-00316
|
Routing - PLUMBING | 7/25/2006 | | 8/1/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing Off Site - STRUCTURAL | 7/17/2006 | | 7/27/2006 | | FAIL |
|
|
|
Called Action Couriers for pick up. - Received comment list from consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 7/27/2006 | | DONE |
|
|
|
FAxed the architect a copy of the comment letter from the consulting structural engineer requesting revisions. JCM
|
Routing - Erosion and Sediment | 7/25/2006 | | 7/25/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 7/20/2006 | | 7/25/2006 | | FAIL |
|
|
|
Drainage revisions required. Contact Brian Murphy ###-####: Inadequate trash access-no safe and efficient way for truck to exit after emptying container. Contact Pam Williams ###-####
|
Routing - PLANNING Land Div | 7/17/2006 | | 7/20/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/17/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/17/2006 | | |
|
|
|
|
Application received | | | 7/14/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/14/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 8/2/2006 | | | | |
|
|
|
John M.
|
Routing - PLAN CHECK | 8/31/2006 | | | | |
|
|
|
|
Routing - PLAN CHECK | 9/11/2006 | | | | |
|
|
|
|