Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-02048
StatusFinaled
Name DIAMOND RIDGE CONSTRUCTION
Site Address 10112 W OVERLAND RD
Project NameWILLIAMSBURG OFFICE #4
Customer Number 
ePlanReviewNo
Description
(Williamsburg Office Park Building #4 -Shell & Core) To construct a new 3,100 square foot, one story, wood framed office shell and core building and related site improvements. This building will contain two future office spaces. The core areas include a common entry vestibule and one accessible restroom and mechanical room for each tenant space. This is a shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/16/201010/22/2010 DONE
ok to sign off per Rita
Second Notice 10/4/201010/11/2010 DONE
First Notice9/13/20109/13/20109/24/2010 DONE
DetailsMike Jordan
BLD-Final9/10/20109/13/20109/13/2010PPASS
DetailsMike Jordan
Marty Phone #: ###-####
DOC - Permit Finaled9/13/20109/13/20109/13/2010PPASS
DetailsMike Jordan
letter of compliance issued.
FIRE-Final Inspection9/10/20109/13/20109/13/2010APASS
DetailsTroy Cobbley
life safety already passed.
FIRE-Final Inspection9/8/20109/9/20109/9/2010APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final9/8/20109/9/20109/9/2010ANR
DetailsMike Jordan
marty Phone #: ###-####
Zoning Approval9/9/20109/9/20109/9/2010 DONE
DetailsSarah Schafer
BLD-Aging Inspection8/26/20108/26/20108/26/2010 PASS
DetailsMike Jordan
Work is in progress.
BLD-Conference6/15/20106/15/20106/15/2010PPASS
DetailsMike Jordan
Per Bob A. ok to reopen expired trades permits and charge 2hr. admin fee.
BLD-Aging Inspection5/17/20105/17/20105/18/2010 PASS
DetailsMike Jordan
Building has been sold and ti work is in progress.
Case Summary (BLD)  5/17/2010 DONE
Case Summary (BLD)  5/7/2010 DONE
Case Summary (BLD)  7/31/2009 DONE
DetailsTisha Gallop
FIRE-Final Inspection9/2/20089/3/20089/3/2008AFAIL
DetailsTroy Cobbley
Provide the permanent address, provide sticker "door to remain unlocked when building is occupied" at the main exit, provide approved hardware on the remaining exterior exit doors and provided "issued" tenant improvement plans or the shell scope of work needs to be changed to reflect the revised interior wall layout.
BLD-Energy code compliance8/29/20088/29/20088/29/2008PPASS
DetailsMike Jordan
marty Phone #: ###-####
BLD-Final1/15/20081/15/20081/15/2008PCANC
DetailsMike Jordan
marty Phone #: ###-####
BLD-Energy code compliance1/15/20081/15/20081/15/2008PPASS
DetailsMike Jordan
marty Phone #: ###-####. Shell and core framing only is ok. ok to insul. exterior walls only.
BLD-Final7/19/20077/19/20077/19/2007PPART
DetailsMike Jordan
marty Phone #: ###-####. Needs to provide truss engineering. Will complete framing insp. when insp for ti is ready. Will need to resubmit floor plan noting deletion of tenant demising wall.
BLD-Final7/16/20077/16/20077/16/2007PNR
DetailsMike Jordan
marty Phone #: ###-####. Provide approved plans and truss engineering. Needs to complete airseal package. c/n posted.
BLD-Framing/Rough-in6/14/20076/14/20076/14/2007PPART
DetailsMike Jordan
marty; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang. Exterior shear nailing ok. Needs to provide non shrink grout under baseplates of ts columns. Prior to sign off of shell and core, plans will be resubmitted to reflect deletion of tenant demissing wall.
BLD-Foundation3/7/20073/8/20073/8/2007APART
DetailsMike Jordan
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beal. wip. repairs being made.
BLD-Foundation3/7/20073/7/20073/7/2007PFAIL
DetailsMike Jordan
Matt; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Missing #5 verts from column pad footings for front canopy. #3 ties installed improperly. Will needs rfi from engineer for epoxy and special insp.
BLD-Footing3/2/20073/5/20073/5/2007PPART
DetailsMike Jordan
donnie ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. wip. Went over plans withj contractor. Noted to contractor that special insp. is required.
(F) Reprint permit  12/27/2006  
Issue PAID IN FULL permit  12/22/2006 DONE
Telephone call  12/21/2006  
tlk to chris laraway - ###-#### that permit and fees are ready to be picked up
Inspection Record Card- Bld  11/14/2006 DONE
Telephone call  11/14/2006  
tlk to chris laraway - ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  11/14/2006  
Routing - Erosion and Sediment11/9/2006 11/9/2006 PASS
ESC plan approved with attached conditions.
Routing - PLAN CHECK11/9/2006 11/9/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/9/2006 DONE
Plan assigned to (JCM)7/18/2006 11/9/2006 PASS
11/9/2006 13:28:31 JCM - activity updated through activity BLDA022 from case BLD06-02048.
Routing - PLAN CHECK11/6/2006 11/8/2006  
Plan resubmittals received  11/8/2006  
Received transmittal letter for Catherine Chertudi and 1pg. trash enclosure drawing, transmittal letter to Aimee Hughes, 1pg. letter to Aimee, 1pg. ESC plan review checklist, 2 copies of 2pg. ESC narrative, 2 copies of page SW.1; taken to John Menard
Routing - FIRE11/8/2006 11/8/2006 PASS
Attached updated review comments to plans.
Routing - FIRE11/2/2006 11/6/2006 FAIL
Faxed resubmittal item to architect.
Routing - PLANNING10/26/2006 11/2/2006 PASS
Routing - PLUMBING10/24/2006 10/26/2006 PASS
per plans and 2003 upc
Routing - Erosion and Sediment10/26/2006 10/26/2006 FAIL
ESC plan failed. Does not meet BMC8-17 requirements. Faxed check list to PD.
Routing - PUBLIC WORKS10/23/2006 10/24/2006 PASS
Routing - PLAN CHECK8/2/2006 10/23/2006  
Plan Reviewer's activity  10/23/2006 DONE
Plan resubmittals inserted into plans, reviewed and approved requested revisions. JCM
1st review completed  8/4/2006 FAIL
Failed planning, plan check , plumbing and fire.
Routing - FIRE7/31/2006 8/4/2006 FAIL
Faxed resubmittal item to architec.
Routing - PLANNING7/31/2006 8/2/2006 PASS
DRH00-00073-Marty S Approved per DRH00-00073 Mod. #2
Routing - PLAN CHECK7/28/2006 7/31/2006 FAIL
John Menard
Routing - PLUMBING7/25/2006 7/31/2006 FAIL
IBC will require a mop sink. show location and resubmit.
Plan resubmittals requested  7/25/2006 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PUBLIC WORKS7/20/2006 7/25/2006 FAIL
No dimensions on trash enclosure, no dimensions showing width of approach, no detail showing that gates open 180°. Contact Pam Williams ###-####
Routing - Erosion and Sediment7/25/2006 7/25/2006 FAIL
ESC plan waiver request denied; informed applicant that a plan will be required.
Routing - PLANNING Land Div7/18/2006 7/20/2006 PASS
Applicant must file amended condo plat and declarations prior to occupancy of the units.
Recd Pcfee & Taken To Pln CK  7/18/2006 DONE
Plans ACCEPTED BY PLAN TECH  7/18/2006  
Plan routing begun/NEW & ADDTN  7/18/2006  
Application received  7/17/2006  
Routing - PLAN CHECK8/4/2006