Third Notice BLD | 10/30/2007 | 10/30/2007 | 12/7/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/1/2007 | 10/1/2007 | 10/30/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/13/2007 | 10/1/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/13/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | CANC |
Joe R Venneman
|
|
|
|
Code Occupancy Approval | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | PASS |
Joe R Venneman
|
|
|
|
BLD-Final | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | PASS |
Dave Hannah
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Hattie James ok for perm occ
|
BLD-Final | 6/13/2007 | 6/14/2007 | 6/14/2007 | P | PART |
Dave Hannah
|
|
|
scott - please call 1/2 hr prior to inspection ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for temp occ on west half
|
BLD-Final | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | PART |
Dave Hannah
|
|
|
scott - pls call 30 mins prior; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok to occ east wing
|
Temporary occupancy | | | 6/1/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5602 issued 6-1-07 to the Modern Hotel.
|
FIRE-Final Inspection | 5/31/2007 | 5/31/2007 | 5/31/2007 | P | PASS |
Forrest France
|
|
|
Corrections are complete, fire life safety inspection passed.
|
FIRE-Final Inspection | 5/29/2007 | 5/30/2007 | 5/30/2007 | P | FAIL |
Forrest France
|
|
|
Provide approved door hardware at four locations, repair and retest emergency exit discharge lights on both the first and second floors.
|
BLD-Conference | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | CANC |
Dave Hannah
|
|
|
scott - please call 1/2 hr prior to inspection ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PART |
Dave Hannah
|
|
|
matf; Phone #: ###-#### Internet Inspection Request from: Victoria Beall framing ok but need to fire block walls
|
BLD-Conference | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | PART |
Dave Hannah
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall shafts ok in lounge area
|
BLD-Conference | 2/26/2007 | 2/27/2007 | 2/27/2007 | P | PART |
Dave Hannah
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall handrails and gaurd rails
|
BLD-Framing/Rough-in | 2/2/2007 | 2/2/2007 | 2/5/2007 | P | PART |
Dave Hannah
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall rooms not much change
|
BLD-Concrete | 1/10/2007 | 1/10/2007 | 1/10/2007 | P | PASS |
Dave Hannah
|
|
|
dean - late as possible ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to pour ftgs for stairs
|
BLD-Foundation | 1/5/2007 | 1/8/2007 | 1/9/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/5/2007 at 4:38:45 PM. Contact: ###-####.
|
BLD-Footing | 1/4/2007 | 1/5/2007 | 1/8/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/4/2007 at 3:37:14 PM. Contact: ###-####.ftgs for cmu wall
|
Plan Reviewer's activity | | | 12/15/2006 | | DONE |
|
|
|
Modified fire review comments. Removed new construction requirements for single station smoke alarms.
|
BLD-Concrete | 11/13/2006 | 11/13/2006 | 11/13/2006 | P | PASS |
Dave Hannah
|
|
|
dean Note: after 1:00 pm Mud is coming 11:30 tomarrow morning; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Issue PAID IN FULL permit | | | 9/19/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/28/2006 | | 9/14/2006 | | PASS |
|
|
|
9/14/2006 07:05:49 CJW - activity updated through activity BLDA022 from case BLD06-02053.
|
Routing - PLAN CHECK | 9/13/2006 | | 9/14/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/14/2006 | | DONE |
|
|
|
lft ms with secretary for duane carber ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/14/2006 | | |
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2006 | | 9/13/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 9/13/2006 | | 9/13/2006 | | PASS |
|
|
|
Approved per DRH06-000266
|
Plan resubmittals received | | | 9/12/2006 | | |
|
|
|
Received 1 copy of response letter from Trout Architects (2pages), 2 copies of the following sheets--A2.1, A3.2, A3.5, A3.12 and taken to Carl Westfall
|
Routing - PLAN CHECK | 8/22/2006 | | 9/12/2006 | | FAIL |
|
|
|
Completed the 2nd IBC plan review report. Two items needed to be resolved. Sent E-Mail to the Architect's representative. Waiting for response
|
Plan resubmittals received | | | 8/30/2006 | | |
|
|
|
Received 14pg. response, 6pg. Legacy Report, 2pg. Performance Test Report, 2 copies of the following: cover sheet A0.0, A2.1, A2.2, A2.5, A3.2, A3.5, A3.12, A3.13, A4.2, A4.3, A8.2, M1.2, M3.2, P1.1, P2.1; taken to Carl Westfall
|
Routing - FIRE | 8/18/2006 | | 8/22/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 8/22/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 8/4/2006 | | 8/18/2006 | | FAIL |
|
|
|
The IBC plan review was started on August 14, 2006 and was finished on August 18. Revised drawings were required. See the plan review report.
|
Routing - PLANNING | 8/3/2006 | | 8/4/2006 | | PASS |
|
|
|
Andrea Tuning Approved per DRH06-00266.
|
Routing - PLUMBING | 8/2/2006 | | 8/3/2006 | | PASS |
|
|
|
additional cross connection protection may be required.
|
Routing - Erosion and Sediment | 8/1/2006 | | 8/2/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 7/28/2006 | | 8/1/2006 | | PASS |
|
|
|
|
Application received | | | 7/18/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2006 | | |
|
|
|
|