Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD06-02108
StatusFinaled
Name GB MANNISTO INC
Site Address 330 N MILWAUKEE ST
Project NameTHE CHEESECAKE FACTORY BTS
Customer Number 
ePlanReviewNo
Description
(Cheesecake Factory at Boise Towne Square) To construct a 9,488 sq. ft. restaurant with and fenced in storage/equipment area on the south side of the Boise Towne Square Mall. Building is a 9,488 sq. ft. one story Type IIB fully fire sprinkled with no openings into the existing mall building. Other work includes all site improvements, landscaping and paving per approved plans and attachments, DRH04-00219Mod # 2. Fire sprinklers are used for an unlimited area mall building. This building including the new addition is to maintain 60 foot open yards.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/8/20071/8/20074/9/2007 DONE
Second Notice has not been responded to.
Second Notice BLD12/27/200612/27/20061/8/2007 DONE
First Notice has not been responded to.
First Notice 12/8/200612/27/2006 DONE
Override - Parcel Holds  12/8/2006  
Permanent occupancy  12/8/2006 DONE
Perm. Occ. Cert. $# 11352 issued 12-8-06 to the Cheesecake Factory.
BLD-Final12/5/200612/5/200612/5/2006PPASS
DetailsMike Jordan
neal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Ok for perm occ.
Code Occupancy Approval  12/5/2006 PASS
landscape in, final signed off and release of bond.
BLD-Final11/24/200611/24/200611/24/2006PPASS
DetailsJim Storey
NEIL; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles temp ok pending all others
FIRE-Final Inspection11/24/200611/24/200611/24/2006PPASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection11/22/200611/22/200611/24/2006PPASS
DetailsTroy Cobbley
Life safety finaled
Temporary occupancy  11/24/2006 DONE
Temp. Occ. Cert. # 5479 issued 11-24-06 to the Cheesecake Factory at Boise Towne Square.
Code Occupancy Approval Temp11/21/200611/21/200611/21/2006PDONE
DetailsScott M.Brown
NEEDS TO BOND FOR LANDSCAPE $33,000
FIRE-Conference11/16/200611/17/200611/17/2006APASS
DetailsTroy Cobbley
Went over maximum occupant load signs and their location with the general contractor.
BLD-Other11/16/200611/16/200611/16/2006PPASS
DetailsMike Jordan
neil Note: suspended ceiling t-Bars ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in11/3/200611/3/200611/3/2006PPART
DetailsMike Jordan
neil - note: suspended ceiling ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. grid in back work areas only. pending other trades insp.
FIRE-Conference10/25/200610/26/200610/26/2006ADONE
DetailsTroy Cobbley
Discussed pull station placement for the hood systems. Where they want to place them does not meet code
BLD-Framing/Rough-in10/24/200610/24/200610/24/2006PCANC
DetailsMike Jordan
neil ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in10/23/200610/23/200610/23/2006PPASS
DetailsMike Jordan
neil ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Interior framed walls.
BLD-Energy code compliance10/23/200610/23/200610/23/2006PPASS
DetailsMike Jordan
neil ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in10/19/200610/19/200610/20/2006PPART
DetailsMike Jordan
neil; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Ok to rock Walls at existing cmu walls. Ok rock sides on walls at ceiling, will leave soffitt open.
BLD-Framing/Rough-in10/17/200610/17/200610/17/2006PPART
DetailsMike Jordan
neil; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. ok to rock soffitt at service counter. May one interior walls.
BLD-Framing/Rough-in10/12/200610/13/200610/13/2006ACANC
DetailsMike Jordan
john - note: insulation also - early as possible ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in10/11/200610/13/200610/13/2006ACANC
DetailsMike Jordan
nell; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Energy code compliance10/13/200610/13/200610/13/2006APART
DetailsMike Jordan
john - note: insulation also - early as possible ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. East wall behind cooler, north wall at existing cmu wall. Upper portions of east wall and at octagon.
BLD-Framing/Rough-in10/12/200610/12/200610/12/2006PPASS
DetailsMike Jordan
neal; Phone #: ###-#### Internet Inspection Request from: Patricia Smith All clips were added, ok to insul.
BLD-Framing/Rough-in10/11/200610/12/200610/12/2006APART
DetailsMike Jordan
nell; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. South wall ok, east wall, all clips not installed per plan at upper elev. Will remove insul and sheet rock to install clips. Needs to remove sheetrock from westwall to verify clips.
BLD-Energy code compliance10/12/200610/12/200610/12/2006APART
DetailsMike Jordan
nell; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. South demissing wall at existing block wall. ok to cover.
BLD-Framing/Rough-in10/3/200610/4/200610/4/2006APART
DetailsMike Jordan
NEIL; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Exterior steel stud framing at east wall, upper tower and lower tower. Contractor to get rfi for sub of fillet welds to hilti shot pins at angle to bent plate connections.
BLD-Footing9/28/20069/29/20069/29/2006PPART
DetailsMike Jordan
neal; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. Perimeter footings and grade beams. wip. Wiil have special insp.
BLD-Footing9/15/20069/15/20069/15/2006PPART
DetailsMike Jordan
neil ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Interior column pad footings.
Issue PAID IN FULL permit  8/31/2006 DONE
Plan assigned to (MLO)8/8/2006 8/30/2006 PASS
8/30/2006 10:21:51 MLO - activity updated through activity BLDA022 from case BLD06-02108.
Routing Off Site - STRUCTURAL8/24/2006 8/30/2006 PASS
Called Action Couriers for pick up
PLANS/APPL TAKEN TO FRONT DESK  8/30/2006 DONE
Print Occupancy Form  8/30/2006 DONE
Permit Ready to Issue  8/30/2006 DONE
Telephone call  8/30/2006 DONE
left mess for douglas middleton at ###-#### ext 111 that permit is ready & need achd approval before picking up
1st review completed  8/29/2006 DONE
Routing - PLUMBING8/29/2006 8/29/2006 PASS
cross connection control per awwa cross connection control manual.
Routing - Erosion and Sediment8/29/2006 8/29/2006 PASS
ESC plan approved with attached conditions.
Routing - PLAN CHECK8/29/2006 8/29/2006 PASS
Routing - FIRE8/23/2006 8/29/2006 PASS
Attached review comments to plans.
Plan resubmittals received  8/24/2006 DONE
Received 1 project start up special inspections,1 response,1 transmittal,1 review report, 1 memo GLP Engeering inc,4 copys of sheets E-4,E-12,TS,A2.1,A6.0,A6.1,A8.0,A8.5,ID-0.0,ID-0.1,ID-1.1,ID-2.1,ID-3.1,ID-3.2,ID-4.1,ID-4.2,ID-4.3,ID-4.4,ID-4.5,ID-4.6,ID-5.1,ID-5.2.0,ID-5.2.1,ID-5.3,ID-5.4,ID-6.1,ID-6.2.0,ID-6.2.1,ID-6.2.3,ID-6.2.4,ID-6.3,ID-6.4 taken to Mike Otto
Plan resubmittals requested  8/23/2006 DONE
IBC corrections
Routing - PLAN CHECK8/9/2006 8/23/2006 FAIL
corrections sent to architect. Note fax failed, corrections mailed. MLO
Plan resubmittals received  8/22/2006  
Received 1 copy of response letter, 3 copies of Structural calcs, 4 copies of S1.1 & S3 and taken to Mike Otto's desk
Plan resubmittals requested  8/21/2006 DONE
Faxed the applicant a copy of the second structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL8/11/2006 8/18/2006 FAIL
Sent revised structural to outside engineer for review.
Plan resubmittals received  8/17/2006  
received transmittal sheet from CSHQA & "4" sheets of A1.0-plans taken to marlene southard
Plan resubmittals received  8/16/2006 FAIL
received 4 copies of sheet A1.0 and taken to Marlene///Given back to Cathy with CSHQA as they were not dimensioned as requested by Marlene///8/16/06 @ 11:30am BAS
Telephone call  8/16/2006 DONE
Spoke with Craig Oka and faxed him information on what we require for a dimensioned site plan. Included a copy of the Record of Survey 7234 in the fax transmittal so he would have parcel line dimensions. He is preparing dimensioned site plans and will submit. (Marlene S.)
Plan resubmittals received  8/11/2006  
Received 1 copy of Review comments, 3 copies of revised calculations, 4 copies of sheet S1, S3, S7 and taken to Marlene
Plan resubmittals received  8/10/2006 DONE
Received 1 revision/change/comment & 4 copys of sheets P-1,P-2,P-3,P-4,P-5,P-6,P-7,P-8,P-9 taken to Mike Otto /care of Marlene S.
Plan resubmittals requested  8/10/2006 DONE
Faxed the applicant a copy of the comment list from the consulting structural engineer. JCM
Routing Off Site - STRUCTURAL7/24/2006 8/10/2006 FAIL
Called Action Courier 7/24/06 @ 3:10 for pick in the morning
Routing - PLANNING8/2/2006 8/3/2006 PASS
Approved per DRH04-00219 MOD #2--Greg Johnson
Routing - PLUMBING7/26/2006 8/2/2006 FAIL
(1)provide loading on existing 4" sewer. (2) pipe floor sinks to the conventionally vented waste line under the assembly area and vent to the wall behind the cook line, the floor sinks under the beverage area are ok on a combination waste and vent system. (3)an R.P. backflow preventor will be required upstream of any filter racks. (4) additional cross connection protection may be required. address items #1 and #2 and resubmit.
Routing - PUBLIC WORKS7/25/2006 7/26/2006 PASS
Routing - Erosion and Sediment7/26/2006 7/26/2006 FAIL
RP not certified; Informed contact with CSHQA--Cathy Duchek.
Plan resubmittals received  7/26/2006  
Received 2 copies of HVAC load calcs, 3 copies of structural calcs, 4 copies of sheets AC-1, AC-2, AC-3, AC-4AC-5, E-11, S1, S1.1, S2, S3, S4, S5, S6, S7, S8 and taken to John Menard
Routing - PLANNING Land Div7/24/2006 7/25/2006 PASS
Plans ACCEPTED BY PLAN TECH  7/24/2006  
Plan routing begun/NEW & ADDTN  7/24/2006  
Application received  7/21/2006  
Override - Parcel Holds  7/21/2006  
Recd Pcfee & Taken To Pln CK  7/21/2006  
Override - Parcel Holds  7/21/2006